[Amended 1-9-2012 by L.L. No. 1-2012]
A. Application procedure.
(1)
Initiation of application. A property owner, or its duly authorized
agent, or other persons having a contractual interest shall make an
application required under this chapter for the subject property.
(2)
Compliance required.
(a)
No application for site plan review, special permit and variances
shall be considered where there are existing violations or delinquent
real estate Town taxes assessed against the subject property, except
where such application is intended to cure the violations. The Zoning/Code
Enforcement Officer shall be responsible for accessing all records
in order to make this determination.
[Amended 11-12-2013 by L.L. No. 2-2013]
(b)
Additionally, proof that all local, state and federal regulations
and permits have been complied with or obtained shall be submitted
as part of the application.
(3)
Simultaneous processing. Whenever two or more forms of review
and approval are required under this chapter, applications for those
development approvals may be processed simultaneously.
(4)
Application forms and application filing fees. Applications
required under this article shall be submitted in a form and in such
numbers as required by the Zoning/Code Enforcement Officer. Applications
shall be accompanied by the fee amount that shall be established by
the Town Board from time to time. Application fees are nonrefundable,
unless otherwise expressly stated. The Zoning/Code Enforcement Officer
shall have the authority to waive application requirements that are
not applicable to a specific project.
(5)
Application completeness.
(a)
An application shall be submitted in the required form, including
all mandatory information, all exhibits and accompanied by the applicable
fee. A determination of application completeness shall be made within
five business days by the Zoning/Code Enforcement Officer.
[Amended 11-12-2013 by L.L. No. 2-2013]
(b)
If an application is determined to be incomplete, the Zoning/Code
Enforcement Officer shall provide written notice to the applicant
along with an explanation of the application's deficiencies. No further
processing of the application shall occur and no public hearings shall
be scheduled until the deficiencies are corrected.
(c)
Upon certification that an application is complete, the Zoning/Code
Enforcement Officer shall circulate the application to all relevant
departments for their recommendations and, within 15 business days,
refer the application to the appropriate authority. An application
shall be considered complete following departmental review and transmittal
to the appropriate authority.
B. Referral to Niagara County Planning Department.
(1)
Applications subject to General Municipal Law § 239-n
shall be referred to the Niagara County Planning Board in accordance
with the provisions of General Municipal Law § 239-n.
[Amended 11-12-2013 by L.L. No. 2-2013]
(2)
The County Planning Board shall have 30 days upon receipt of
an application to approve, disapprove, or approve with modifications
of the application.
(3)
If the County approves a referral, then the local board's decision
is governed by majority vote.
(4)
If the County disapproves or approves subject to stated conditions
or modifications, the local board may override the county's opinion
only by a majority plus one vote.
(5)
The local board shall send a copy of its final decision and
reasons for such decision on a County referral case to the County
Planning Board within seven days after the local decision is reached.
C. Public hearing procedure.
(1)
Public hearings shall be required for the following:
(a)
Zoning Map or Zoning Text Amendments by Town Board;
(b)
Incentive Developments by the Town Board:
(c)
Special permit by the Zoning Board of Appeals;
(d)
Variances by the Zoning Board of Appeals.
(e)
Site plan approval applications.
[Added 9-8-2014 by L.L.
No. 3-2014]
(2)
Setting hearing. For all matters properly brought before the
Town Board, Planning Board or Zoning Board of Appeals for which a
public hearing is required by this chapter, the body charged with
conducting the hearing shall, upon receipt of a completed application,
select a reasonable time and place for such hearing, provided, however,
that such time shall be not later than 45 days following the receipt
of the application, unless the applicant shall agree to some later
time.
(3)
Notification.
[Amended 7-8-2019 by Ord.
No. 4-2019]
(a)
Mailed notice.
[1]
The appropriate board secretary shall be required to mail the
appropriate notices for public hearings to all property owners within
500 feet measured from property lines of the subject property both
within and outside the Town boundaries and all involved agencies and
officials.
[2]
Notice by mail shall be given not more than 20 nor less than
10 days before the hearing by regular United States mail, except that
notice to Town agencies or officials may be by interdepartmental memorandum.
[3]
A written notice of any proposed change or amendment affecting
property within 500 feet of the boundaries of a state park or parkway
shall be given to the Niagara Frontier State Park Commission at least
10 days prior to the date of such public hearing.
[4]
A written notice of any proposed change or amendment affecting
property within 500 feet of the boundaries of any city, village, town
or county shall be given the Clerk of such municipality and to the
Clerk of the County Legislature at least 10 days prior to the date
of such hearing.
(b)
Published notice. A published notice shall be placed in an official
newspaper or a newspaper of general circulation in the Town at least
once, not more than 20 nor less than 10 days before the hearing.
(c)
Notice information. The notice of public hearing, both mailed
and published, shall include:
[1]
The general location of land that is the subject of the application;
[2]
The legal description or street address;
[3]
The substance of the application, including the magnitude of
proposed development and the current zoning district;
[4]
The time, date and location of the public hearing;
[5]
A phone number to contact the Town; and
[6]
A statement that interested parties may appear at the public
hearing.
D. Compliance with New York State Environmental Quality Review Act (SEQRA).
All agencies shall comply with the provisions of SEQRA under Article
8 of the Environmental Conservation Law and its implementing regulations.
E. Engineering and SEQRA cost recovery.
(1)
Any person who applies to the Town of Porter or its duly constituted
Boards may be required to pay an engineering fee deposit.
(2)
No approval, permit, recommendation or review shall be processed
until the required deposit is paid to the building department.
(3)
The amount of deposit shall be in accordance with the Fee Schedule
of the Town of Porter.
(4)
Such deposit shall be in addition to all other fees required
by law.
(5)
In addition to the engineering deposit and fee schedule, where
the Town incurs additional engineering, administrative and legal costs
pursuant to SEQRA, the Town shall recover the actual cost for preparing
and reviewing all EIS or DEIS, including costs for scoping, when the
Town is the lead agency and requires a DEIS or EIS.
(6)
The fee for residential projects shall not exceed 2% of the
total cost, as estimated by the developer and verified by the Town.
The total project cost shall be the cost of the land, plus the cost
of all improvements required, not including the cost of buildings
and structures.
(7)
The fee for nonresidential construction projects shall not exceed
0.5% of the total project cost. The total project cost shall be the
cost of supplying utility service to the project, cost of site preparation,
and the cost of labor and materials as determined with reference to
a current construction cost data publication in common usage, such
as building construction cost data by means. All costs shall include
any legal expense, engineering and administrative costs according
to contract that are incurred by the Town.
(8)
The fee paid hereunder shall be deposited in a trust account
in the name of the Town of Porter.
(9)
Procedure upon completion.
(a)
Within 120 days of the final action by the Town or board(s)
or the issuance of a certificate of occupancy, whichever is later,
on an application for the improvement or SEQRA review, the Building
Department shall report to the Town Board the actual cost to the Town
for engineering.
(b)
The Town Board shall determine whether the Town costs exceed
the total engineering fee charged. If the fee paid by the Town to
its consulting engineers exceeds the fee paid by the applicant, the
moneys deposited shall become the property of the Town of Porter.
(c)
In the event that the deposit paid by the developer is more
than the actual amount paid by the Town to its consulting engineers
or its attorney, then the excess shall be returned with interest,
as provided above. SEQRA review fees shall be billed to the applicant
and paid prior to approval.
(10)
In no event shall the Town charge against or utilize a fee paid
hereunder for deficiencies in Town-owned improvements, routine maintenance
or matters not directly related to the engineering cost for the specific
improvement proposed.
F. Filing of approvals. The appropriate board secretary shall file all
applicable restrictions and other conditions as approved by the Planning
Board, Town Board or Zoning Board of Appeals. All covenants, deed
restrictions, easements and similar restrictions to be recorded in
connection with the approval shall provide that they may not be modified,
removed or released without the express consent of the Town Board
and shall provide that they may be enforced by the Town of Porter.
All filing fees and expenses are the responsibility of the applicant.
[Amended 1-9-2012 by L.L. No. 1-2012]
A. Purpose. The purpose of site plan review is to provide a mechanism
for a detailed review of development proposals to ensure that they
are consistent with this chapter and the comprehensive plan, will
not adversely affect the neighborhood, and promote the safety and
general welfare of the community.
B. Requirement. All new developments for a use which are required by
this chapter in the district in which it is located to obtain site
plan approval or a special use permit shall obtain site plan approval
before a building permit or special use permit may be issued.
C. Reviewing authority. The Planning Board shall be responsible for
approving site plans if all specifications contained in this chapter
are met. If there are minor variations to any of the specifications,
the Planning Board may still approve a site plan.
D. Optional presubmission consultation. The owner or owners of land
to be developed in any district may consult with the Planning Board,
the Zoning/Code Enforcement Officer, or any other public officials
prior to the preparation of the site plan. Requirements for site plan
approval and the relationship of the application to the Comprehensive
Plan should be determined in advance of the preparation of the site
plan.
E. Submission requirements.
(1)
A completed application form.
(2)
A statement indicating the financial capability of the applicant
to carry out the proposed development.
(3)
A completed Environmental Assessment Form (EAF).
(4)
Ten copies of a plat accurately drawn to a scale of not less
than one inch equals 50 feet certified by a registered/licensed engineer,
architect, landscape architect or surveyor as appropriate, as to existing
features, design features and boundaries. The plat shall include or
be accompanied by the following information:
(a)
Date of preparation. All revisions shall be noted and dated.
(b)
A location map showing the location of the tract with reference
to the surrounding properties, existing streets and streams within
1,000 feet of the property lines of the proposed development.
(c)
Name of the development, North arrow, graphic scale, parcel
number, the name and address of the record owner, the name and address
of the applicant, the name, address, license number, and seal and
signature of the person preparing the survey. If the owner of the
premises is a corporation, the name and business address of the president
and secretary shall be submitted on the application.
(d)
All distances shall be in feet and 0.01 of a foot and all bearings
shall be given to the nearest 10 seconds.
(e)
The zoning classification of properties within 200 feet of the
boundaries of the property for which the application is made shall
be illustrated on a map.
(f)
A boundary and topographical survey by a surveyor of the total
proposed development. If the developer intends to develop a tract
of land in phases, the plat shall include the total tract.
(g)
A copy of any existing or proposed covenants, deed restrictions,
which are applicable to the property.
(h)
The distance, measured along the right-of-way lines of existing
streets abutting the property, to the nearest intersections with other
public streets within 200 feet of the site boundaries.
(i)
The location and dimensions of proposed buildings and structures,
all accessory structures, signs and fences, if any, including front,
side and rear yard setbacks, height of buildings, first floor elevations
of all structures and floor plans of buildings.
(j)
Location of existing buildings and all other structures, including
walls, fences, culverts and bridges, with spot elevations of such
buildings and structures. Structures to be removed shall be indicated
by dashed lines. Structures to remain shall be indicated by solid
lines.
(k)
If any proposed construction or development is located within
or adjacent to any identified flood-prone area, the following information
shall be submitted:
[1]
A plan which accurately delineates the area which is subject
to flooding, the location of the proposed construction, the location
of any other flood-prone development or structures, and the location
of any existing or proposed stream improvements or protective works,
information concerning the one-hundred-year flood elevations, descriptions
of uplift forces, associated with the one-hundred-year flood, size
of structures, location and elevations of streets, water supply and
sanitary sewage facilities, soil types and floodproofing measures.
[2]
A document certified by a registered professional engineer or
architect that the proposed construction has been adequately designed
to protect against flood damage. Such statement shall include a description
of the type and extent of floodproofing measures that have been incorporated
into the design of the structure.
(l)
Existing and proposed contours, referred to as United States
Coast and Geodetic Survey datum, now known as North American Vertical
Datum of 1988 (NAVD 88), with a contour interval of two feet for slopes
of less than 20% and an interval of five feet for slopes of 20% or
more. Regardless of slope, contours within areas of disturbance shall
be plotted at two-foot intervals. Dashed lines shall be used to indicate
existing contours and solid lines shall be used to indicate proposed
contours.
(m)
Location of existing rock outcrops, high points, watercourses,
depressions, ponds, marshes, wooded areas and other significant existing
features, including previous flood elevations of watercourses, ponds
and marsh areas as determined by survey.
(n)
Identification of any wetlands on the site and the regulatory
agency approved design techniques proposed to accommodate them.
(o)
Any and all existing streets related to the proposed development;
including the names, widths, approximate gradients and sidewalk widths.
(p)
If any new streets are proposed, profiles, indicating grading;
cross-sections showing the width and design of roadways and sidewalks.
(q)
Acreage, to the nearest hundredth of an acre of the site to
be developed for nonresidential purposes and/or the area, in square
feet, of each lot to be developed for residential purposes.
(r)
Plans of proposed stormwater systems showing feasible connections
to existing or any proposed utility systems. Pipe sizes, grades and
direction of flow, locations and inlets, manholes or other appurtenances
and appropriate invert and other elevations shall be indicated. All
stormwater facility plans shall be accompanied by a separate sketch
showing all existing drainage within 500 feet of any boundary, and
all areas and any other surface area contributing to the calculations,
and showing methods used in the drainage calculations.
(s)
The location and size of all existing and proposed sanitary
sewers.
(t)
The location and size of all existing and proposed waterlines,
valves and hydrants.
(u)
The location, width and purpose of all existing and proposed
easements and rights-of-way.
(v)
The location, type and approximate size of existing utilities
to serve the development.
(w)
Tree masses and all individual trees having a caliper of four
inches or greater.
(x)
A soil erosion and sedimentation control plan prepared by a
licensed engineer or registered landscape architect.
(y)
The number and density of dwelling units (if residential).
(z)
All means of vehicular access for ingress and egress to and
from the site onto public streets, showing the size and location of
internal streets or driveways and curb cuts, including the organization
of traffic channels, acceleration and deceleration lanes, additional
width and any other improvements on the site or along the site's street
frontage necessary to prevent a difficult traffic situation. All pedestrian
walkways and provisions for handicapped facilities in compliance with
the requirements of the Americans with Disabilities Act (ADA) for
an accessible site shall also be shown. In addition, the development
plan shall show the existing road system, located outside the development
within 200 feet of the development or the next nearest intersection.
(aa)
Computation of the number of parking spaces to be provided,
the location and design of off-street parking areas and loading areas
showing size and location of bays, aisles and barriers and the proposed
direction of movement.
(bb)
Proposed screening and landscaping plan prepared by a registered
landscape architect.
(cc)
The placement and screening of solid waste disposal and storage
facilities.
(dd)
If applicable, a detailed proposal, including covenants, agreements,
or other specific documents showing the ownership and method of assuring
perpetual maintenance to be applied to those areas which are to be
used for private streets, sewers, recreational or other common purposes.
(ee)
If the plan is to be completed in phases, the proposed sequence
of development with projected time schedule for completion of each
of the several phases.
(ff)
The Zoning/Code Enforcement Officer, in consultation with the
Planning Board, may waive any of the above submittal requirements
if he/she finds them to be irrelevant to the proposed project.
(5)
Any required application fees in accordance with the fee schedule.
(6)
The Planning Board may waive any submission requirements which
it deems unnecessary or unduly burdensome taking into consideration
the complexity, size and scope of the request for site plan approval.
F. Procedure.
(1)
Upon certification that the site plan application is complete,
the Zoning/Code Enforcement Officer shall circulate the application
to all relevant departments for their recommendations and, within
30 business days, refer the site plan to the Planning Board.
(2)
The Planning Board, upon receipt of a site plan from the Zoning/Code Enforcement Officer, shall review the application at the next scheduled Planning Board meeting at which the application can be placed on the agenda. The Planning Board will review the application with the Zoning/Code Enforcement Officer and any other persons deemed relevant by the Planning Board to determine the completeness of the application. Once deemed complete, a public hearing will be scheduled in accordance with §
200-100 of this chapter.
[Amended 9-8-2014 by L.L.
No. 3-2014]
(3)
At the public hearing, all persons interested in the application
will be heard. Following the public hearing, the Planning Board shall
make a determination on the application within 30 days to approve,
disapprove, or approve with modification. The time period may be extended
by mutual agreement of the Planning Board and the applicant. If the
proposed development is determined to require further environmental
review pursuant to Article 8 of the Environmental Conservation Law
and 6 NYCRR 617, the time period for approval may be extended until
such review is completed.
[Amended 9-8-2014 by L.L.
No. 3-2014]
(a)
If a permit is denied, the Planning Board shall state, in writing,
to the applicant the reasons for such denial.
(b)
If the site plan is approved with modification, such modifications
shall be stated in writing and considered as a condition for approval.
(5)
Within five business days following such decision, the Planning
Board Secretary shall mail notice of such decision to all persons
entitled to such notice and file such decision with the Town Clerk,
where it shall be public record.
G. Expiration.
(1)
The approval of a site plan for a building permit shall be valid
for a period of two years from the date of the approval for purposes
of obtaining a building permit. Failure to obtain a building permit
within the time period shall cause the approval to become null and
void. Upon application, for good cause shown, the Planning Board may
extend the validity of the approval two times for a period of six
months each time, not to exceed an additional period of one year.
(2)
The approval of a site plan for a special permit application
shall be valid for a period of 90 days for the purpose of applying
to the Zoning Board of Appeals for special permit approval. Upon application,
for good cause shown, the Planning Board may extend the validity of
the approval two times for a period of 30 days each time, not to exceed
an additional period of 60 days.
[Amended 1-9-2012 by L.L. No. 1-2012]
A. Purpose. The Town of Porter allows a variety of uses of land, provided
that such uses do not adversely affect neighboring properties, the
natural environment or the character of the Town and its neighborhoods.
Many of the uses listed in this chapter are, therefore, permitted
only upon issuance of a special use permit by the Zoning Board in
order to ensure that these uses are appropriate to their surroundings
and satisfy performance criteria. Accessory uses or structures used
in connection with a special use permit use shall be subject to the
same special use permit approval requirements as the principal structure
or use. Special use permits are to be necessary for those uses which,
though intended to be allowed when certain criteria are met, are not
allowed as a matter of right. It is the intent of this article to
determine whether such uses are compatible, desirable and allowable
on a case-by-case basis. Special use permits are only allowed where
the Zoning Board makes findings that they meet the criteria of this
section. The burden of establishing that the criteria set forth in
this article have been met shall in all cases be on the applicant.
B. Requirement. All new developments for a use or a change of use which
are required by this chapter in the district in which it is located
to obtain a special use permit shall obtain a special use permit before
a building permit.
C. Reviewing authority. The Zoning Board shall have the authority to
issue a special use permit.
D. Submission requirements.
(1)
A completed application form.
(2)
Completion of site plan approval and receipt of Planning Board
Recommendation.
E. Procedure.
(1)
A special use permit shall only be issued after the completion of a site plan review by the Planning Board pursuant to §
200-106 of this chapter with a recommendation of approval or denial communicated to the Zoning Board of Appeals within 15 days of the completion of the site plan approval process. Upon receipt of the required submissions, the Zoning Board of Appeals shall conduct a public hearing as described in §
200-100 of this chapter. Following the public hearing, the Zoning Board of Appeals shall make a determination on the application within 60 days to approve, disapprove, or approve with modification. The time period may be extended by mutual agreement of the Zoning Board of Appeals and the applicant.
(2)
If the proposed development is determined to require further
environmental review pursuant to Article 8 of the Environmental Conservation
Law and 6 NYCRR 617, the time period for approval may be extended
until such review is completed.
F. Findings.
(1)
In granting or denying special use permits, the Zoning Board
of Appeals shall take into consideration the purposes of this article,
the scale of the proposed project, the possible impact of the proposed
project on the nearby properties and neighborhoods, architectural
aesthetics of the area and measures that will mitigate potential adverse
impacts and preserve or enhance the character of the Town and the
welfare of its citizens. The Zoning Board of Appeals shall not grant
a special use permit unless and until it shall make the following
findings as to whether the proposed special use:
(a)
Will be in compliance with all provisions and requirements of
this and other local laws and regulations and will be in harmony with
the purposes of the land use district in which it is located and with
the general intent and purposes of this article.
(b)
Will not be detrimental to adjacent uses.
(c)
Will not cause undue traffic congestion, unduly impair pedestrian
safety or overload existing roads considering their current width,
surfacing and condition and will have appropriate parking and be accessible
to fire, police and other emergency vehicles.
(d)
Will not overload any public water, drainage or sewer system
or any other municipal facility or degrade any natural resource or
ecosystem.
(e)
Will be suitable for the property on which it is proposed, considering
the property's size, location, topography, vegetation, soils, natural
habitat and hydrology.
(f)
Will not adversely affect the aesthetics of the premises and
adjacent properties and the neighborhoods.
(2)
The Board shall further find whether the adverse impacts of
the proposed special use can be mitigated to such an extent that the
special use permit should be granted and if so, what conditions need
be required to achieve such mitigation.
G. Expiration.
(1)
As a condition in granting a special use permit, the Zoning
Board of Appeals may require that the special use permit be renewed
at regular intervals. Regular intervals for special permit renewal
shall not be less than two years.
(2)
The special use permit may be revoked at any time if the Zoning/Code
Enforcement Officer finds that any of the conditions of the permit
have been violated.