ZONING PERMIT
A document signed by the Zoning Officer which:
A.
Is required by this chapter as a condition precedent to the
commencement of a use or the erection, construction, reconstruction,
alteration, conversion, expansion or installation of a structure or
building; and
B.
Acknowledges that such use, structure or building complies with
the provisions of the Municipal Zoning Ordinance or variance therefrom
duly authorized by a municipal agency pursuant to N.J.S.A. 40:55D-60
and 40:55D-70 of the Municipal Land Use Law.
Pursuant to Code §
4-41B(3), the Zoning Officer shall review and process applications for zoning permits. The Zoning Officer is hereby authorized to prepare application forms for zoning permits.
The Zoning Officer shall issue a zoning permit within 10 business
days from the date of application. Failure to issue requested permit
within said 10 business days will be considered an approval.
Where new construction is proposed, no construction permit shall
be issued unless a zoning permit covering the use and location of
the proposed building and structure has first been obtained. Where
applicable, issuance of a zoning permit may be conditioned upon payment
of any taxes or assessment for local improvements which due or delinquent
on the property for which any application is made.
No certificate of occupancy shall be issued until a zoning permit
is issued.