Prior to filing an application for approval of a preliminary
plat, development plan or certified survey, the subdivider shall consult
with the Village for advice and assistance for the purpose of determining
land suitability and reviewing the procedures and requirements of
this chapter and other ordinances, and any plans or data which may
affect the proposed development. All applications hereunder shall
be made on Village forms.
If the preliminary plat has been approved or been approved conditionally
by the Village Board, the subdivider may make written application
to the Village and pay the required fees for the approval of a final
plat. The application shall be submitted at least seven business days
prior to the scheduled meeting and shall be accompanied by five copies
of the plat. The final plat may be for all or part of the preliminary
plat. The Village Board shall refer the final plat to the Plan Commission
for a recommendation that the final plat conforms to the provisions
of this chapter. The Plan Commission shall refer the plat to the Village
Engineer and appropriate committees for comments and recommendations.
After receipt of these comments and recommendations, the Plan Commission
shall make a determination and forward its recommendation to the Village
Board. Upon determining that the final plat meets the requirements
of this chapter and any additional requirements, and has been submitted
within six months from the approval date of the preliminary plat and
all preliminary plat conditions have been met, the Village Board shall
approve the final plat within 60 days of the date all required information
has been received by the Board. A copy of the recorded plat shall
be returned to the Village Clerk/Treasurer prior to the issuance of
a building permit.
When a land division is created as defined herein, the developer shall submit an application to Village staff at least seven business days prior to the scheduled Village Board meeting and pay the appropriate fees. The application shall be accompanied by five copies of a certified survey map prepared in accordance with Wis. Stats., § 236.34, and this chapter. The requirements of §
325-16 of this chapter regarding preliminary plat procedures, and of §§
325-9,
325-10,
325-12 and
325-29, relating to fees and dedications, shall also apply to certified survey maps unless specifically waived by the Village Board. The Village Board shall, within 90 days after submission to the Village Clerk/Treasurer, approve, approve conditionally or reject the certified survey map based on its determination of conformance with the provisions of this chapter. A copy of the recorded survey map shall be returned to the Village Clerk/Treasurer prior to the issuance of a building permit. The developer will be required to specify drainage plans, which must be approved by the Village Engineer and will be enforced by the Village Building Inspector. The developer will be required to pay all costs incurred by the Village for engineering and legal review as well as preparation of a development agreement.