A.
Nonrefundable fees shall be as follows:
(1)
Wind energy conversion system/wind energy permit: $2,000 per megawatt of rated maximum capacity.
(2)
Wind measurement towers wind energy permit: $1,500 per tower, and $1,000 for any other structure or part thereof not a tower.
(3)
Small WECS wind energy permit: $500 per WECS.
(4)
Wind measurement tower or wind energy permits renewals/extensions: $1,000 per permit/WECS.
(6)
Fees are subject to change by Town Board Resolution.
B.
Wind energy permits; review, inspection, and approval fees. The Town believes the review of applications for wind energy facilities and compliance monitoring of issued wind energy permits requires specific third-party expertise. In addition to the permit fees for the WECS system as provided in § 175-25A above, the owner of the WECS shall pay the costs of such review as follows:
(1)
An outside consultant, approved by the Town, to review the plans submitted by the applicant or its representative for compliance with this regulation and inspection of work, together with monitoring compliance with any issued permit for any WECS. All such expense shall be made by the applicant, or holder of such issued permit, if different, providing a cash advance payment to the Town Clerk prior to issuing such permit or such other form of advance payment as the Town Board may direct and approve.
(2)
Permit year annual report. The owner shall file annually a report of the condition and all maintenance and repair work to the WECS system, detailing any improvements, alterations or changes to any WECS or other structure of the system or any of its components, together with a review fee of $200 for each WECS. The report shall be certified by a licensed engineer that such work has not changed any permit condition. The Town, upon notice to the owner, may refer the report to consultant if it reasonably believes that any work may change or adversely impact a permit condition. The owner shall be responsible for any costs of any outside consultant, if necessary, to review the report.
(3)
Any costs associated with reviewing materials submitted by the owner or the review of any condition of a permit, including, but not limited to, ensuring the system continues to be safe and compliant with the terms of such permit issued shall be the expense of the owner of the system. Such expense shall be paid by the applicant/owner. Prior to incurring such costs, the Town agrees to provide the applicant/owner of the system with notice of such costs and reason for the same. The applicant/owner may protest the costs by filing a protest with the Town Clerk within 10 days of such notice. Said protest shall contain a statement of what is protested, and if a cost item is protested, then an estimate from an independent person for the costs protested shall be included. Notwithstanding a protest the Town may engage a consultant to review any submission by the applicant/owner of the system prior to approving the submission and all such expense and costs shall be an expense of the project (applicant/owner of the system). If any such expense shall not be paid the same shall constitute a violation of the permit and be deemed an expense in decommissioning the system or any part thereof in question.
C.
The permit fee for Town Board approval for cutting or clearing in a green buffer area within a site shall be $100 per permit; no permit fee is necessary for maintaining agricultural uses within a green buffer zone.
D.
Applications for approval of transfer of ownership or control pursuant to § 175-5F shall be submitted to the Town Board together with information explaining the proposed change of control or the transfer. Such information shall include the names and addresses of the parties whose interest is being changed or transferred together with their percentage of ownership being transferred and the names and addresses of each person, shareholder, member, partner or individual receiving such interest, together with a fee of $500 and such consultant fees as the Town Board finds necessary to review any financial information submitted therewith. The Town Board reserves the right to request such other information it may reasonably request and finds necessary to complete its review of such application.
E.
Nothing in this chapter shall be read as limiting the ability of the Town to enter into host community agreements with any applicant to compensate the Town for expenses or impacts on the community. The Town shall require any applicant to enter into an escrow agreement to pay the engineering and legal costs of any application review, including the review required by SEQRA. Notwithstanding anything to the contrary provided herein, any and all Town agreements or permit conditions pertaining to a wind energy conversion system shall be filed with the Town and in place prior to the issuance of the wind energy permit, unless the approval for such wind energy conversion system permit expressly provides otherwise, including the host community agreement, decommission plan and proof of funds or escrow accounts, if required, related to the wind energy conversion system.