[R.O. 2008 § 415.170; R.O. 2007 § 415.170; Ord. No. 4974 § 1, 3-30-2006; Ord. No. 6206 § 15, 4-28-2016]
A.
In all areas of special flood hazards (Zones A, AE,) or areas that have had fill placed to remove it from the special flood hazard area, the following provisions are required:
1.
No permit for floodplain development shall be granted for new construction, substantial-improvements, and other improvements, including the placement of manufactured homes, within any numbered or unnumbered A Zones and AE Zones, unless the conditions of this Section are satisfied.
2.
All new construction, including manufactured homes and substantial improvements, shall be designed (or modified) and adequately anchored to prevent flotation, collapse or lateral movement of the structure resulting from hydrodynamic and hydrostatic loads, including the effects of buoyancy.
3.
All new construction and substantial improvements shall be constructed with materials resistant to flood damage.
4.
All new construction and substantial improvements shall have adequate drainage provided and shall be constructed by methods and practices that minimize flood damage.
5.
All new construction and substantial improvements shall be constructed with electrical, heating, ventilation, plumbing and air-conditioning equipment and other service facilities that are designed and/or located so as to prevent water from entering or accumulating within the components during conditions of flooding.
6.
All new and replacement water supply systems shall be designed to minimize or eliminate infiltration of floodwaters into the system.
7.
New and replacement sanitary sewage systems shall be designed to minimize or eliminate infiltration of floodwaters into the systems and discharged from the systems into floodwaters.
8.
On-site waste disposal systems shall be located to avoid impairment to them or contamination from them during flooding.
9.
The storage or processing of materials that are in time of flooding buoyant, flammable, and explosive or could be injurious to human, animal or plant life is prohibited.
10.
Storage of other material or equipment may be allowed if not subject to major damage by floods and firmly anchored to prevent flotation or if readily removable from the area within the time available after flood warning.
11.
Until a floodway has been designated, no development, including landfill, may be permitted within Zones A and AE on the City's FIRM unless the applicant for the land use has demonstrated that the proposed use, when combined with all other existing and reasonable anticipated uses, will not increase the water surface elevation of the one-hundred-year flood as shown on the Flood Insurance Rate Study incorporated by reference, Article III, Section 415.070.
12.
All areas identified as unnumbered A Zones on the FIRM are subject to inundation of the 100-year flood; however, the base flood elevation is not provided. Development within unnumbered A Zones is subject to all provisions of this Chapter. If Flood Insurance Study data is not available, the developer shall supply the community with and the community shall review and reasonably utilize any base flood elevation or floodway data currently available from Federal, State, or other sources.
13.
All proposals for development, including proposals for manufactured home parks and subdivisions [if the development is five (5) acres or more, or fifty (50) lots or more] must depict the base flood elevation data on the plan.
B.
Hazardous Materials.
1.
All hazardous material storage and handling sites shall be located out of the floodplain.
C.
Cumulative Improvement. A structure may be improved (remodeled or enlarged) without conforming to current requirements for elevation so long as the cumulative value of all work done within the last five calendar years does not exceed fifty percent (50%) of the structure's current market value. If the cumulative value of the improvement exceeds fifty percent (50%) of the structure's current market value, the structure must be brought into compliance with Article V, Section 415.190 which requires elevation of residential structures to or above the base flood elevation or the elevation/flood proofing of non-residential structures to or above the base flood elevation.
D.
Non-Conforming Use. A structure, or the use of a structure or premises that was lawful before the passage or amendment of the ordinance, but which is not in conformity with the provisions of this ordinance, may be continued subject to the following conditions:
1.
If such structure, use, or utility service is discontinued for twelve (12) consecutive months, any future use of the building shall conform to this ordinance.
2.
If any nonconforming use or structure is destroyed by any means, including flood, it shall not be reconstructed if the cost is more than fifty percent (50%) of the pre-damaged market value of the structure. This limitation does not include the cost of any alteration to comply with existing State or local health, sanitary, building, safety codes, regulations or the cost of any alteration of a structure listed on the National Register of Historic Places, the State Inventory of Historic Places, or local inventory of historic places upon determination.
E.
Critical Facilities.
1.
All new or substantially improved critical nonresidential facilities including, but not limited, to governmental buildings, police stations, fire stations, hospitals, orphanages, penal institutions, communication centers, water and sewer pumping stations, water and sewer treatment facilities, transportation maintenance facilities, places of public assembly, emergency aviation facilities, and schools shall be elevated above the 500-year flood level or together with attendant utility and sanitary facilities, be flood proofed so that below the 500-year flood level the structure is water tight with walls substantially impermeable to the passage of water and with structural components having the capability of resisting hydrostatic and hydrodynamic loads and the effects of buoyancy. A registered professional engineer or architect shall certify that the standards of this Subsection are satisfied. Such certification shall be provided to the Floodplain Administrator as set forth in the National Flood Insurance Program (NFIP) regulations.
2.
All critical facilities shall have access routes that are above the elevation of the 500-year flood.