[CC 1985 §5-1; Comp. Ords. §7.01(1); Ord. No. 4137, 1-11-2018; Ord. No. 4218, 6-13-2019]
A.
Application. Any person undertaking the demolition or destruction of any building within the City limits shall first obtain a permit. Demolition permits may be obtained by application to the Building Department on a form provided by the Community Development Administrator.
B.
Duration. Any demolition permit under which no demolition has commenced within thirty (30) days after the date of issuance of the permit, or under which the proposed demolition has not been completed within six (6) months of the date of issuance, shall expire by limitation. No work shall take place under such permit after such expiration. An extension of sixth (6) months for completion of the work under such permit may be granted by the Community Development Administrator upon written request from the applicant or contractor.