[Ord. No. 54, art. IV, § 1, eff. 9-12-1975]
Any proposed canal shall have a minimum width of 50 feet and plans for any such canal shall be approved by the township board before construction is commenced. Canals shall be designed to provide for a canal bottom at an elevation of 568.0 (U.S. Geodetic Survey datum) which is 4.2 below record low water.
[Ord. No. 54, art. IV, § 2, eff. 9-12-1975]
No boat wells shall be constructed, installed or located closer than 10 feet to a side lot line; excepting, however, this prohibition shall not apply to boat wells of adjacent lots which abut at the common side lot line. Notwithstanding the foregoing provision, the end walls of a boat well installed or constructed parallel to the shoreline shall not be located closer than three feet from the side lot line where the end wall intersects the shoreline; and the end walls shall angle in toward the boat well shoreline and each other intersecting the boat well shoreline at not less than 135° nor more than 45°, as the case may be. The township board may vary the provisions of this section upon finding that strict compliance therewith will result in practical difficulties by reason of the area, dimensions or configuration of the lot involved. The following sketch depicts the requirements of this article relative to parallel boat wells:
072 Boat Wells.tif
[Ord. No. 54, art. IV, § 3, eff. 9-12-1975]
Seawall construction for commercial or business property shall be designed for the site by a registered professional engineer taking into account all backfill weight as well as any surcharge weight due to parking, buildings, etc.
[Ord. No. 54, art. IV, § 4, eff. 9-12-1975]
Seawall construction for residential property shall be in accordance with the following requirements:
(1) 
Record high water elevation prior to 1974 was elevation 577.6 (all elevations are based on the U.S. Geodetic Survey datum) based on conditions of no wind or waves. Winds and waves can increase the lake level several feet at the shoreline, lakes and canals depending on the direction of the wind and other causes. The top of any seawall constructed under this article shall not be less than elevation 580.0 which is 0.4 feet above the record high water, unless 60% of the highest walls 300 feet on either side of the proposed wall is less than such elevation then and in that event the top elevation may conform to the medium elevation of the highest 60% of the seawalls 300 feet on either side of the proposed seawall. Depending on location and exposure the owner of the proposed seawall should give consideration to the effects of wind and waves in determining the need for additional height above that elevation.
(2) 
Wall construction materials shall be one of the following:
a. 
Interlocking steel sheet piling, minimum 3/16 inch thick;
b. 
Two-inch-thick tongue-and-groove pressure-treated one-piece wood; or
c. 
Concrete or other material to be approved by the township engineer.
(3) 
The stability of a seawall is dependent on the bottom section being embedded in the ground to a sufficient extent to provide enough ground resistance to prevent the bottom of the seawall sheeting from sliding laterally. Sliding resistance is dependent on stiffness of the ground and the amount of embeddment of the sheeting in the ground. The stiffer the ground the less embeddment of the sheeting is required. Therefore, walls shall have from 40% to 60% of their total length embedded in the ground with the lesser figure being used for this stiffer or firmer ground stratas and the greater figure being used for the soft clay ground through which little effort is needed to drive the sheeting during installation. Embeddment shall be defined as the part of the total sheeting length driven in the ground below an elevation two feet below the existing lake or canal bottom or below elevation 568.0, whichever is higher.
(4) 
Walls shall be complete with waler, capping, tie-backs and deadman.
(5) 
Deadman shall consist of one section of steel sheet piling driven vertically with a one-foot horizontal such that the bottom of the piling is one foot closer to the wall than the top of the piling. The top of the deadman pile shall be 3 1/2 feet below the top of the wall. The deadman sheet piling shall be 10 feet long and located not less than 16 feet back of the seawall, except that deadman sheet piling installed on seawalls parallel to side lot lines may be a minimum of 10 feet from the seawall but shall be increased in length one foot for each foot less than 16 feet the spacing is between the deadman and the seawall. No deadman shall be less than 10 feet from the seawall. Deadman must be installed within the property on which the seawall is installed.
(6) 
Tie-backs connecting the waler and the deadman shall consist of not less than three-quarter-inch diameter solid one-piece steel rods. Tie-backs shall connect for the deadman sheet piling 3 1/2 feet below the top of the deadman; however, a waler shall not be required with steel sheeting, but a top cap shall be necessary with steel sheeting, but a waler shall be required with all wood seawalls.
(7) 
Deadman and tie-backs shall be spaced a maximum of eight feet center to center.
(8) 
Walers shall be installed 2 1/2 to 3 1/2 feet below the top of the wall.
(9) 
Design of the seawall shall take into account all backfill weight as well as any surcharge due to parking, buildings and the like. However, a minimum for a seawall length shall be 12 feet for canals and rivers and 14 feet for lake construction for the total length of the sheeting.
(10) 
Standards set forth in subsections (3) and (5) and (6) through (8) of this section may be varied to other configurations when supported by a solid investigation and a full engineering design substantiating a proposed variation if approved by the township engineer.