[Ord. No.
5918 § 1, 4-25-2013; Ord. No. 7655, 6-23-2022]
A fee of one hundred dollars ($100.00) shall be assessed to
any user for each day that a report required by this Chapter, a permit
or order issued hereunder is late, beginning five (5) days after the
date the report is due (higher penalties may also be assessed where
reports are more than thirty (30) to forty-five (45) days late at
the discretion of the Manager). Actions taken by the Manager to collect
late reporting penalties shall not limit the Manager's authority
to initiate other enforcement actions that may include penalties for
late reporting violations.
[Ord. No.
5918 § 1, 4-25-2013; Ord. No. 7655, 6-23-2022]
The Manager may decline to issue or reissue an individual wastewater
discharge permit to any user who has failed to comply with any provision
of this Chapter, a previous individual wastewater discharge permit,
or order issued hereunder, or any other pretreatment standard or requirement,
unless such user first files a satisfactory bond, payable to the City,
in a sum not to exceed a value determined by the Manager to be necessary
to achieve consistent compliance.
[Ord. No.
5918 § 1, 4-25-2013; Ord. No. 7655, 6-23-2022]
The Manager may decline to issue or reissue an individual wastewater
discharge to any user who has failed to comply with any provision
of this Chapter, a previous individual wastewater discharge permit,
or order issued hereunder, or any other pretreatment standard or requirement,
unless the user first submits proof that it has obtained financial
assurances sufficient to restore or repair damage to the POTW caused
by its discharge.
[Ord. No.
5918 § 1, 4-25-2013; Ord. No. 7655, 6-23-2022]
The Manager may decline to issue or reissue an individual wastewater
discharge permit to any user who has failed to pay any outstanding
fees, fines or penalties incurred as a result of any provision of
this Chapter, a previous individual wastewater discharge permit, or
order issued hereunder.
[Ord. No.
5918 § 1, 4-25-2013; Ord. No. 7655, 6-23-2022]
Whenever a user has violated or continues to violate any provision
of this Chapter, an individual wastewater discharge permit, or order
issued hereunder, or any other pretreatment standard or requirement,
water service to the user may be severed. Service will recommence,
at the user's expense, only after the user has satisfactorily
demonstrated its ability to comply.
[Ord. No.
5918 § 1, 4-25-2013; Ord. No. 7655, 6-23-2022]
A violation of any provision of this Chapter, an individual wastewater discharge permit, or order issued hereunder, or any other pretreatment standard or requirement is hereby declared a public nuisance and shall be corrected or abated as directed by the Manager. Any person(s) creating a public nuisance shall be subject to the provisions of Chapter
215 governing such nuisances, including reimbursing the City for any costs incurred in removing, abating, or remedying said nuisance.
[Ord. No.
5918 § 1, 4-25-2013; Ord. No. 7655, 6-23-2022]
Users which have not achieved compliance with applicable pretreatment
standards and requirements are not eligible to receive a contractual
award for the sale of goods or services to the City. Existing contracts
for the sale of goods or services to the City held by a user found
to be in significant non-compliance with pretreatment standards or
requirements may be terminated at the discretion of the Manager.