It is suggested that before preparing a preliminary plat each
subdivider should first consult with the commission, or its designated
representative, for preliminary information, advice, and suggestions.
A rough sketch of the proposed subdivisions, showing existing features
and ideas for development would be helpful in this discussion.
Eight blue or black-line copies of a preliminary plat shall
first be submitted for approval at least two weeks prior to a regularly
scheduled meeting of the commission at which action thereon is desired.
Such preliminary plat shall adhere to the following requirements:
(1) It shall be drawn to a scale not smaller than one inch to 200 feet,
on one or more sheets.
(2) It shall contain the following information:
a. Name of subdivision, owner, subdivider, surveyor or engineer, date
of drawing, number of sheets, north point and scale. If true north
is used, method of determination shall be shown.
b. Location of proposed subdivision by an inset map at a scale of not
less than two inches equal one mile, showing adjoining roads and their
names, subdivisions, other landmarks and how proposed roads or streets
tie into the present or existing road system.
c. The boundary survey or existing survey of record; provided, that
such survey shows a closure with an accuracy of not less than one
in 5,000, total acreage of subdivided area, number and approximate
area and frontage of all building sites, building lines shown to scale
with their dimensions existing buildings within the boundaries of
the tract, names of owners and their property lines within the boundaries
of the tract and adjoining such boundaries.
d. All existing, platted and proposed streets, their names and widths;
existing utility or other easements, public areas and parking spaces;
culverts, drains and watercourses, their names and other pertinent
data.
e. The conceptual drainage layout, including proposed drainage easements,
detention areas and means of transporting the drainage to a well defined
open stream or river which is considered natural drainage.
f. A cross section showing the proposed street construction, depth and
type of base, type of surface, etc.
g. A profile or contour map showing the proposed grades for the streets
and drainage facilities including elevations of existing and proposed
ground surface at all street intersections and at points of major
grade change along the centerline of streets together with proposed
grade lines connecting therewith.
h. Proposed connections with existing sanitary sewers and existing water
supply.
i. All parcels of land and all easements to be dedicated for public
use and the condition of such dedication.
j. In cluster subdivisions the required buffer area and other common
areas.
[Amended by Ord. of 9-9-2002]
Within 60 days after the receipt thereof the commission shall
approve in writing the preliminary plat if it conforms to the requirements
of this ordinance; otherwise, it shall be disapproved in writing with
reasons given for the disapproval. The reasons for disapproval shall
identify deficiencies in the plat which cause the disapproval by reference
to specific duly adopted ordinances, regulations or policies and shall
generally identify such modifications or corrections as will permit
approval of the plat. If only minor changes are required, a conditional
approval may be granted, or an extended time may be given the subdivider
for submission of revised plans. One copy of the approved plat shall
be returned to the subdivider with the conditions of approval attached
thereto or noted thereon, and a like copy shall be retained in the
commission's files. Approval of a preliminary plat shall be valid
for not more than one year, unless extended in appropriate cases by
the commission in its discretion.
Approval of a preliminary plat does not constitute a guarantee
of approval of the final plat, and no property shall be transferred
or offered for sale, nor shall a building permit be issued, on the
basis of an approved preliminary plat.
[Amended by Ord. of 9-9-2002]
Subdividers who are creating a minor subdivision (not requiring
the construction of a new street or the extension of public utilities
and not adversely affecting the development of the remainder, if any,
of the parcel from which the new subdivision lots are created) are
not required to submit a preliminary plat.