The design standards and requirements set forth in this article
shall be observed as minimums by the subdivider in the design of each
subdivision within the Town of Delaware. The Planning Board may require
more restrictive standards where necessary to protect the health,
safety and welfare of the public and where circumstances unique to
the property so dictate.
All subdivisions shall be served with an adequate water supply
meeting the following standards:
A. Service required. All residential, commercial and industrial lots
shall contain a suitable area for an on-site water supply well or
be served by an approved off-site water supply system.
B. Public water supply.
(1) Availability. When a proposed subdivision is located within an existing
water district or where a public water supply is available within
reasonable proximity, generally 1,000 feet of the proposed subdivision,
the developer shall construct a system of water mains and connect
with such system and provide a connection for each lot, provided capacity
is available and necessary agreements with the water district or public
system owner. The developer shall absorb all costs associated therewith.
Suitable agreements shall also be established for the design, specifications,
construction, ownership and maintenance of such distribution system,
and shall be submitted to the Planning Board for approval prior to
final approval of the subdivision.
(2) Design. Plans and specifications for the extension of an existing
system shall be prepared by a professional engineer and shall conform
to accepted engineering practices and requirements of the system operator
as well as the Town of Delaware and New York State Department of Health
and Department of Environmental Conservation standards.
C. Community water supply.
(1) Design. When a new or connection to an existing private community
water supply is proposed, plans and specifications shall be prepared
by a professional engineer and shall conform to accepted engineering
practices as well as the Town of Delaware and New York State Department
of Health standards. The system shall be designed to furnish adequate
main sizes and, if deemed necessary by the Planning Board, fire hydrants
located to meet the specifications of an appropriate electrical inspection
person or agency, as determined by the Town and the local fire district.
Suitable agreements shall also be established for the design, specifications,
construction, ownership and maintenance of such distribution system,
and shall be submitted to the Planning Board for approval prior to
final approval of the subdivision.
(2) Capacity. The subdivider must demonstrate ability to provide a minimum
of 75 gallons of water per capita or 150 gallons per bedroom per day
for each single-family residential dwelling unit or equivalent to
be serviced.
(3) Installation. New wells shall be sited, drilled and tested under
the direct supervision of a professional engineer or a professional
groundwater geologist.
(4) Location. Any new community water supply well shall be located on
a reserved parcel of adequate size and suitable configuration to provide
for necessary access for operation and maintenance in accord with
New York State Department of Health and Department of Environmental
Conservation requirements.
All subdivisions shall be served with adequate sewage disposal
systems meeting the following standards:
A. Service required. All residential, commercial and industrial lots
shall contain suitable areas for on-lot sewage disposal systems or
be served by an approved off-site sewage disposal system.
B. Public sewage systems.
(1) Availability. When a proposed subdivision is located within an existing
sewer district or where a public sewage disposal system is available
within reasonable proximity, generally 1,000 feet of the proposed
subdivision, the developer shall construct a collection and conveyance
system and connect with such system and provide a connection for each
lot, provided capacity is available and necessary agreements with
the sewer district or public system owner. The developer shall absorb
all costs associated therewith. Suitable agreements shall also be
established for the design, specifications, construction, ownership
and maintenance of such system, and shall be submitted to the Planning
Board for approval prior to final approval of the subdivision.
(2) Design. Plans and specifications for the extension of an existing
system shall be prepared by a professional engineer and shall conform
to accepted engineering practices and requirements of the system operator
as well as the Town of Delaware and New York State Department of Environmental
Conservation and Department of Health standards.
C. Community sewage disposal system.
(1) Requirement. Community sewage disposal systems are required for all
residential, commercial and industrial lots outside sewer districts
where soil conditions are unsuitable for on-lot subsurface sewage
disposal systems according to New York State Department of Health
and Department of Environmental Conservation standards as certified
by a professional engineer.
(2) Design. When a new or connection to an existing private community
sewage disposal system is proposed, plans and specifications shall
be prepared by a professional engineer and shall conform to accepted
engineering practices as well as the Town of Delaware and New York
State Department of Health and Department of Environmental Conservation
standards. Suitable agreements shall also be established for the design,
specifications, construction, ownership and maintenance of such distribution
system and shall be submitted to the Planning Board for approval prior
to final approval of the subdivision.
D. On-site sewage disposal systems.
(1) Use of systems. Where connection to a community sewage system is
not required, on-site systems shall be provided in accord with criteria
set forth by the New York Department of Health and Department of Environmental
Conservation.
(2) Site suitability. Suitable soil characteristics on each lot shall
be demonstrated in accord with the requirements of the New York Department
of Health and Department of Environmental Conservation.
Should any proposed subdivision involve the disturbance of any
land area by grading, filling, excavating or the removal or destruction
of the natural topsoil or vegetation, the Planning Board may require
an erosion and sedimentation plan prepared by a professional engineer
in cooperation with the Sullivan County Conservation District.
Should any proposed subdivision involve the installation of
any streets or other impervious surfaces or in any other manner increase
the volume of stormwater leaving the site, or cause the interruption
or change in any existing drainage course, the Planning Board may
require a stormwater management plan. Such plan shall be prepared
by a professional engineer in consultation with the Sullivan County
Conservation District. The following additional requirements shall
apply:
A. Design.
(1) Stormwater management facilities shall be designed for a storm frequency
of 10 years, using generally accepted engineering principles appropriate
for the proposed site and development. Detention facilities shall
be designed to retain a one-hundred-year storm without facility failure.
(2) In cases where detention of stormwater is proposed, the post-development
peak rate of stormwater discharge from the parcel being developed
shall not exceed the predevelopment peak rate of stormwater discharge
from the parcel being developed. The calculation of post-development
discharge shall, in addition to areas disturbed during development,
include the estimated effect of all runoff expected from driveways,
buildings, walkways, parking areas and other impervious areas associated
with the ultimate build-out of the subdivision or land development.
(3) The Planning Board shall, in cases where existing drainage problems,
flooding or other factors relating to the public health, safety and
welfare ,and upon the recommendation of the Town Engineer, require
that the proposed stormwater control facilities be designed to a twenty-five-year
storm frequency and/or other more stringent criteria or require the
provision of stormwater control facilities in areas where no such
facilities are proposed by the developer.
B. Additional requirements.
(1) Lots shall be laid out and graded to prevent cross-lot drainage away
from proposed building areas. Natural drainage courses shall be maintained
to the greatest extent possible.
(2) The existing points of natural drainage discharge onto adjacent property
shall not be altered, nor shall the rate of water runoff be increased
because of development without the written approval of all affected
landowners.
(3) No stormwater runoff or natural drainage water shall be so diverted
as to overload existing drainage systems or create flooding or the
need for additional drainage structures on other private properties
or public lands without complete approval of provisions being made
by the developer for properly handling such conditions.
(4) Where a subdivision is traversed by a watercourse, drainageway, channel
or stream, there shall be provided a drainage easement of at least
25 feet on each side of the stream measured from the stream bank or
such additional width as will be adequate to preserve the unimpeded
flow of natural drainage and/or for the purpose of widening, deepening,
relocating, improving or protecting such drainage facilities.
(5) Drainage structures that are located on state or county highway rights-of-way
shall be approved by the respective authorities, and a letter indicating
such approval shall be directed to the Town prior to preliminary final
plan approval.
(6) All streets shall be so designed as to provide for the discharge
of surface water from their rights-of-way. The slope of the crown
on proposed streets shall be 1/4 inch per foot away from the center
line unless a greater crown is required by other Town standards.
(7) All proposed surface drainage structures shall be indicated on the
preliminary plan.
(8) Drainage plans shall include all appropriate designs, details and
dimensions necessary to clearly explain proposed construction materials
and elevations.
(9) Whenever storm drains are required by the Planning Board such storm
sewer systems shall be separate from the sanitary sewer system. Storm
drains or storm sewer facilities may be required in any development
situation where the Planning Board determines that surface drainage
facilities are inadequate to prevent excessive erosion and lot or
road maintenance problems.
(10)
Drainage systems shall be designed in accord with such design
standards as may be promulgated by the New York State Department of
Transportation, Sullivan County or the Town of Delaware, using hydraulic
computations to show effects of the flow of water. In no case shall
any pipe system of less than 15 inches in diameter be used underneath
a street or driveway. All dams, lakes, ponds or stream encroachments
shall be designed in accord with state design standards.
(11)
All drainage systems and structures shall be subject to the
approval of the Town Engineer, Town Highway Superintendent or any
such other qualified person as may be appointed for this purpose by
the Town Board.
In addition to all other requirements imposed by this chapter,
all commercial and industrial subdivisions shall comply with the requirements
of the sections below:
A. Street systems.
(1) Traffic flow. Traffic movements in and out of commercial and industrial
areas should not interfere with external traffic, nor should they
create hazards for adjacent residential areas.
(2) Internal circulation. The design of streets, service drives and pedestrianways
should provide for safe and hazard-free internal circulation, including
provision for fire lanes where appropriate.
(3) Entrance/exit. The points of ingress and egress shall be designed
to prevent commercial or industrial traffic from passing through residential
areas.
B. Block layout. Block layout shall, with due consideration of site
conditions, provide for the best possible service to customers, traffic
and parking circulation, and pickup and delivery services. In no case
shall a block length be less than 600 feet. Where safety considerations
mandate, 800 feet may be required as a minimum.
C. Lot size. Lot sizes shall be based on the following factors:
(1) Adequate space. The total area shall be sufficient to provide adequate
space for off-street parking and loading, landscaping and other facilities.
(2) Consolidated design. Whenever possible, commercial parcels should
include enough land to provide for a group of commercial establishments,
planned, developed and operated as a unit.
The multiple dwelling standards contained in Chapter
220, Zoning, shall apply to all multiple dwelling residential subdivisions and townhouse developments, but no building permits for the same shall be issued until preliminary plan approval has first been obtained under this chapter. No certificates of use or occupancy shall be granted until final plan approval has been first obtained hereunder.
Mobile home parks, campgrounds and recreational vehicle park
subdivisions are regulated pursuant to separate local laws and/or
special zoning provisions.
Any developer may erect a single model home or dwelling unit
within a subdivision for purposes of promoting sales within such subdivision.
Such model home or unit may be erected upon preliminary approval with
a building permit from the Town but shall, however, be situated on
a lot or individual site planned for a dwelling and so identified
on the plans submitted. Such model home, as well as the lot or site
on which it is erected, shall meet all standards contained herein
or in other Town of Delaware regulations and be capable of being eventually
sold or used at its proposed location. The model home or unit shall
also be connected to all utilities and provided with sewage and water
services as well as road access prior to its use in the desired location,
or a performance guarantee shall be posted with the Town providing
for the same.