A.
Township: land disturbance permit.
(1)
All land or earth disturbance activities, whether associated with a subdivision and/or land development plan or associated with building construction or other activities, shall be conducted pursuant to and after approval of and issuance of a permit for a plan for the control of stormwater and erosion control due to the said activity. For earth disturbance activities meeting the criteria of § 202-5C(1), stormwater controls will not be required, but erosion and sedimentation controls may be required where deemed necessary by the Township Engineer or Township Supervisors.
(2)
Such plan shall be submitted and processed in accordance with this article for all land or earth disturbances, including but not limited to the following activities:
B.
Conservation District: erosion and sediment control plan.
(1)
The PA DEP has regulations that require an erosion and sediment control plan for any earth disturbance activity of 5,000 square feet or more, under 25 Pa Code § 102.4(b).
(2)
No regulated earth disturbance activity within Marlborough Township shall commence until approval of an erosion and sediment control plan for the earth disturbance activity is obtained by the Montgomery County Conservation District and a copy is provided to the Township.
(3)
A copy of the erosion and sediment control plan, as required by PA DEP regulations, shall be available at the project site at all times.
C.
PA DEP: NPDES construction activities permit.
(1)
Under 25 Pa Code, Chapter 92, a PA DEP NPDES construction activities permit is required for any regulated earth disturbance activities.
(2)
No regulated earth disturbance activity within Marlborough Township shall commence until a permit from the PA DEP is obtained and a copy is provided to the Township.
(3)
A copy of the permit, as required by PA DEP regulations, shall be available at the project site at all times.