[Ord. 277, 2/10/2015]
The identified floodplain area shall consist of the following
specific areas/districts:
1. The Floodway Area/District identified as "floodway" in the FIS, which
represents the channel of a watercourse and the adjacent land areas
that must be reserved in order to discharge the base flood without
any increase in the water surface elevation at any point. This term
shall also include floodway areas which have been identified in other
available studies or sources of information for those special floodplain
areas where no floodway has been identified in the FIS.
A. Within any Floodway Area, no encroachments, including fill, new construction,
substantial improvements, or other development, shall be permitted
unless it has been demonstrated through hydrologic and hydraulic analysis
performed in accordance with standard engineering practice that the
proposed encroachment would not result in any increase in flood levels
within the community during the occurrence of the base flood discharge.
B. No new construction or development shall be allowed, unless a permit
is obtained from the Department of Environmental Protection's
regional office.
2. The AE Area/District shall be those areas adjacent to the floodway
and identified as an AE Zone on the FIRM included in the FIS prepared
by FEMA for which base flood elevations have been provided.
3. The A Area/District shall be those areas identified as an A Zone
on the FIRM included in the FIS prepared by FEMA and for which no
one-percent annual chance flood elevations have been provided. For
these areas, elevation and floodway information from other federal,
state, or other acceptable source shall be used when available. Where
other acceptable information is not available, the elevation shall
be determined by hydrologic and hydraulic engineering techniques.
Hydrologic and hydraulic analyses shall be undertaken only by registered
professional engineers or others of demonstrated qualifications, who
shall certify that the technical methods used correctly reflect currently
accepted technical concepts. Studies, analyses, computations, etc.,
shall be submitted in sufficient detail to allow a thorough technical
review by the Township.
4. For areas adjoining streams, ponds, and lakes not included in the
FIS prepared by FEMA, the applicant shall be required to determine
the elevation and area of the floodplain with hydrologic and hydraulic
engineering techniques. Hydrologic and hydraulic analyses shall be
undertaken only by registered professional engineers or others of
demonstrated qualifications, who shall certify that the technical
methods used correctly reflect currently accepted technical concepts.
Studies, analyses, computations, etc., shall be submitted in sufficient
detail to allow a thorough technical review by the Township. All areas
inundated by the one-hundred-year flood shall be included in the floodplain
area.
[Ord. 277, 2/10/2015]
The identified floodplain area may be revised or modified by the Board of Supervisors where studies or information provided by a qualified agency or person documents the need for such revision. However, prior to any such change within the A Area/District or AE Area/District, approval must be obtained from FEMA. Additionally, as soon as practicable, but not later than six months after the date such information becomes available, FEMA shall be notified of the changes by submission of technical or scientific data. Refer to §
8-502, Subsection
1, for situations where FEMA notification is required.
[Ord. 277, 2/10/2015]
Should a dispute concerning any identified floodplain boundary
arise, an initial determination shall be made by the floodplain administrator,
and any party aggrieved by this decision or determination may appeal
to the Zoning Hearing Board. The burden of proof shall be on the appellant.
[Ord. 277, 2/10/2015]
Prior to development occurring in areas where annexation or
other corporate boundary changes are proposed or have occurred, the
Township shall review flood hazard data affecting the lands subject
to boundary changes. The Township shall adopt and enforce floodplain
regulations in areas subject to annexation or corporate boundary changes