[Ord. 963, 10/18/2006, § 401]
1.
The developer shall notify the Borough Engineer at least 72 hours prior to beginning any installation of public improvements in an approved plan. While work is in progress, the developer shall notify the Borough Engineer at least 72 hours prior to the time that the following required progress inspections are desired:
A.
Inspection of subgrade of streets prior to laying of base.
B.
Inspection of base as it is being constructed and prior to final paving of streets.
C.
Inspection of paving of streets while they are being constructed.
D.
Inspection on installation of sanitary sewers, storm sewers and drainage facilities as they are being constructed.
E.
Inspection of all utility street crossings within the public right-of-way.
2.
The Borough Engineer shall prepare a written report of all inspections in duplicate on forms provided by the Borough. One copy shall be retained by the Borough and one copy shall be retained by the Borough Engineer.