The Village substreet utility excavation and trench backfill
policy is established. The policy shall become effective as of May
1, 2018, and shall consist of the following provisions.
Placement of CLSM, operation limitations, measurement methods
and basis of payment, if applicable, shall all be in compliance with
the IDOT Special Provision For Controlled Low-Strength Material as
adopted January 1, 1990, and revised thereafter.
When a trench is cut into an existing concrete street or sidewalk,
the pavement shall be replaced in kind with a total thickness two
inches greater than existing, to a maximum of 10 inches. When restoring
concrete pavement, the entire slab into which the trench was cut shall
be removed and replaced. If the surface is either asphalt or oil and
chip, a six-inch concrete replacement layer shall be installed and
two inches of bituminous concrete base shall be placed over the base.
Replacement pavement shall be installed no less than a distance of
two feet in each direction from the edge of the excavation trench.
Any person, firm, corporation or entity which plans to install
any underground utilities within a present or proposed street or sidewalk
right-of-way area is required to notify the Village Superintendent
of Public Works a minimum of 24 hours prior to beginning work. The
notification shall include the exact location and nature of the work
to be performed. In emergency situations, the Village shall be notified
immediately upon the responsible party's decision that excavation
is required. Roadway or sidewalk area repairs or restorations made
without proper notification may require re-excavation and replacement
with approved backfill.