A.
General. For the protection of the Town and future residents of the subdivision, a series of inspections during the course of construction are required to ensure compliance with the approved definitive plan and the Board's rules and regulations.
B.
Inspection requests. Inspections shall be requested by the subdivider at least four full working days in advance by written notice to the Board and its duly authorized agent.
C.
Inspections required. The subdivider shall contact the Planning Board and its duly authorized agent for inspections regarding the following aspects of the subdivision, at the specified times:
(1)
Erosion control: following installation of erosion control measures.
(2)
Clearing and grubbing: following completion of roadway and drainage clearing work.
(3)
Roadbed subgrade: following excavation of the roadbed and sidewalk, but prior to any backfilling.
[Amended 10-17-2022]
(4)
Drainage system: following installation of drain pipe, culverts, catch basins, manholes, and all related construction, but prior to any backfilling.
[Amended 10-17-2022]
(5)
Underground utilities: following laying of electric, telephone, and fire alarm cable in roadway and to individual dwellings, but prior to any backfilling.
(6)
Finished subgrade: following grading and compaction of subgrade.
[Amended 10-17-2022]
(7)
Finished gravel roadbase: following application, grading, and compaction of each gravel roadbase material lift or layer.
[Amended 10-17-2022]
(8)
Pavement: notice shall be given so that inspection may be conducted during and upon completion of paving.
(9)
Final inspection: following completion of roadways, permanent benchmarks, curbing, berming, walkways, grading, seeding and cleanup.
(10)
Backfilling: No water main, storm drain, catch basin, utility installation, road subgrade or foundation, or any other item of work designated for inspection, shall be backfilled or paved over until inspected and approved by the Board or its duly authorized agent.