[CC 1985 § 25-81; Ord. No. 277, A4, 11-7-1966; Ord. No. 659, 8-7-2000]
The subdivider shall install and construct all improvements required by this Article. All required improvements shall be installed and constructed in accordance with the specifications and under the supervision of the City Council and to its satisfaction.
[CC 1985 § 25-82; Ord. No. 277, A4 § 1, 11-7-1966; Ord. No. 659, 8-7-2000]
All streets within the platted area which are dedicated for public use shall be brought to the grade approved by the City Council and after receiving the report and recommendations of the City Engineer.
[CC 1985 § 25-83; Ord. No. 60 § 12, 11-17-1937; Ord. No. 277, A4 § 3, 11-7-1966; Ord. No. 515, 12-2-1991; Ord. No. 659, 8-7-2000; Ord. No. 960, 8-3-2009]
A. 
Water lines shall be provided by the subdivider to City standards.
B. 
Where a public water main is reasonably accessible, the subdivider shall connect with such water main and provide a water connection for each lot in accordance with City standards, procedure and supervision.
C. 
Standards/Specifications.
1. 
All connections of service pipe with the City water mains shall be made by tapping a corporation stop into the side of the water main, and such tapping shall in no case be made nearer than eighteen (18) inches to a caulked joint.
2. 
The consumer will pay all costs of all material from this point for the tapping of the main. The property owner will provide three-fourths (3/4) inch K copper to meter. The service pipe shall extend from the main to the meter setter, which will be set just inside of the property line.
3. 
The meter shall be connected to such service line by standard fittings supplied with the meter. The meter setter and the meter shall be set together in a vitrified meter box eighteen (18) inches in diameter with a regulation metal lid, said box to extend not less than two (2) inches above the surface of the ground. SDR 13.5 PVC plastic pipe can be used from the meter to the house or copper pipe. No solder containing lead can be used.
4. 
All valves, corporation cocks, curb cocks, meter settings, meter boxes and in general the entire installation from the main to and including the meter shall be inspected and approved by the Water Commissioner before water will be turned on the service.
5. 
If any special connection with the water mains is required or any service that requires a larger size service pipe than three-fourths (3/4) inch, special instructions will be given to the plumber or property owner for such connection by the City Water Commissioner.
D. 
Procedures.
1. 
All new construction of water mains and the water service lines from the main to the meter box at the edge of the property will be at the developer's or owner's expense. Upon approval of a building permit of a new building, the owner may install new service line from the newly constructed building and only make connection to the meter with supervision of City Utilities after line from main to meter is flushed by City Utilities personnel.
2. 
Any deviation from these standards and procedures will require written approval by the Municipal Utility Board.
[CC 1985 § 25-84; Ord. No. 277, A4 § 4, 11-7-1966; Ord. No. 659, 8-7-2000]
A. 
Sanitary sewer lines shall be provided by the subdivider to City standards.
1. 
Where public sanitary sewer is reasonably accessible, the subdivider shall connect or provide for the connection with such sanitary sewer, and shall provide within the subdivision the sanitary sewer system required to make the sewer accessible to each lot in the subdivision. Sewer systems shall be approved by the City Council and Board of Health of the State of Missouri, and the construction subject to the supervision of the City Engineer. Each lot or separate building shall be provided with individual access to a City owned sanitary line.
2. 
Where sanitary sewers are not available, other facilities as approved by the City Council and the Board of Health of the State of Missouri must be provided for the adequate disposal of sanitary wastes.