Prior to the issuance of any permit to an applicant to commence
a land development activity that has a SWPPP that includes a stormwater
management facility as one of the requirements, the applicant or developer
shall complete and file with the SMO a stormwater facility registration
statement, which shall include a copy of any proposed permanent stormwater
management facility design, the operations and maintenance plan in
the SWPPP for the permanent facility, the entity that will be responsible
for implementing each practice in the plan, including contact information
for a responsible person, and such fee as required by resolution of
the Town Board. The statement shall be updated within 30 days of a
change or modification in the design, operation or maintenance of
the facility, the designated entity responsible for implementing any
practice or the contact information provided on the statement, or
when the owner or operator of the facility submits a notice of termination
of coverage to the MS4. The statement shall be renewed every three
years thereafter.
The owner or operator of permanent stormwater management practices
installed in accordance with this chapter shall operate and maintain
the stormwater management practices to achieve the goals of this chapter.
Proper operation and maintenance also includes, as a minimum, the
following:
A. A preventive/corrective maintenance program for all critical facilities
and systems of treatment and control (or related appurtenances) which
are installed or used by the owner or operator to achieve the goals
of this chapter.
B. Written procedures for operation and maintenance and training new
maintenance personnel.
C. Discharges from the SMPs shall not exceed design criteria or cause
or contribute to water quality standard violations.