[Ord. 3-2016, 10/13/2016]
1.
The Canton Township Engineer or his designee shall inspect all phases of development of the site, including, but not limited to:
A.
Completion of preliminary site preparation, including stripping of vegetation, stockpiling of topsoil and construction of temporary stormwater management and erosion control facilities.
B.
Completion of rough grading, but prior to placing topsoil, permanent drainage or other site development improvements and ground covers.
C.
During construction of the permanent stormwater facilities at such times as specified by the Canton Township Engineer.
D.
Upon completion of permanent stormwater management facilities, including established ground covers and plantings.
E.
Upon completion of any final grading, vegetative control measures or other site restoration work done in accordance with the approved plan and permit.
2.
No work shall begin on a subsequent stage until the preceding stage has been inspected and approved by the Canton Township Engineer.
3.
It is the responsibility of the permittee to notify the Canton Township Engineer 48 hours in advance of the completion of each identified phase of development.
4.
Any portion of the work which does not comply with the approved plan must be corrected by the permittee within 48 hours. No work may proceed on any subsequent phase of the stormwater management plan, the subdivision or land development or building construction until the required corrections have been made.
5.
If at any stage of the work the Canton Township Engineer determines that the soil or other conditions are not as stated or shown in the approved application, he may refuse to approve further work and Canton Township may revoke existing permits until a revised plan is submitted and approved as required by § 17-406 of this chapter.
6.
Subsequent/Periodic Inspections. SWM BMPs should be inspected by the landowner/developer (including the Township for dedicated facilities) according to the following list of frequencies: