[Ord. 266, 7/11/2005, § 601]
The fee required by this Chapter
25B and the specific figures of which are adopted by separate Borough resolution is the municipal review fee. The municipal review fee shall be established by the municipality to defray review costs incurred by the municipality and the municipal engineer. All fees shall be paid by the applicant.
[Ord. 266, 7/11/2005, § 602]
The municipality shall establish a review fee schedule by resolution
of the municipal governing body based on the size of the regulated
activity and based on the municipality's costs for reviewing
drainage plans. The municipality shall periodically update the review
fee schedule to ensure that review costs are adequately reimbursed.
[Ord. 266, 7/11/2005, § 603]
1. The fees required by this Chapter
25B shall at a minimum cover:
B. The review of the drainage plan by the municipality and the municipal
engineer.
D. The inspection of stormwater management facilities and drainage improvements
during construction.
E. The final inspection upon completion of the stormwater management
facilities and drainage improvements presented in the drainage plan.
F. Any additional work required to enforce any permit provisions regulated by this Chapter
25B, correct violations, and ensure proper completion of stipulated remedial actions.