A.
Alteration or relocation of watercourse.
(1)
No encroachment, alteration, or improvement of any kind shall be
made to any watercourse until all adjacent municipalities which may
be affected by such action have been notified via certified mail by
the applicant proposing such modification, and until all required
permits or approvals have first been obtained from the Department
of Environmental Protection Regional Office.
(2)
No encroachment, alteration, or improvement of any kind shall be
made to any watercourse unless it can be shown that the activity will
not reduce or impede the flood-carrying capacity of the watercourse
in any way.
(3)
In addition, FEMA and the Pennsylvania Department of Community and
Economic Development shall be notified prior to any alteration or
relocation of any watercourse.
B.
When Schuylkill Township proposes to permit the following encroachments:
1) any development that causes a rise in the base flood elevations
within the floodway; or 2) any development occurring in Zone AE without
a designated floodway, which will cause a rise of more than one foot
in the base flood elevation; or 3) alteration or relocation of a stream,
the applicant shall (as per 44 CFR 65.12):
(1)
Apply to FEMA for conditional approval of such action prior to permitting
the encroachments to occur.
(2)
Upon receipt of the FEMA Administrator's conditional approval
of map change and prior to approving the proposed encroachments, a
community shall provide evidence to FEMA of the adoption of floodplain
management ordinances incorporating the increased base flood elevations
and/or revised floodway reflecting the post-project condition.
(3)
Upon completion of the proposed encroachments, the applicant shall
provide as-built certifications to FEMA and to Schuylkill Township.
FEMA will initiate a final map revision upon receipt of such certifications
in accordance with 44 CFR Part 67.
C.
Any new construction, development, uses or activities allowed within
any identified floodplain area shall be undertaken in strict compliance
with the provisions contained in this chapter and any other applicable
codes, ordinances and regulations.
D.
Within any identified floodplain area, no new construction or development
shall be located within the area measured 50 feet landward from the
top-of-bank of any watercourse, extended for such additional distance
from said banks as is or may be subject to inundation by waters of
the base flood with an additional "no structure" setback of 50 feet,
except as permitted by Zoning Ordinance[1] or herein.
Within any identified floodplain area any new construction or substantial improvements shall be prohibited. If a variance is obtained for new construction or substantial improvements in the identified floodplain area in accordance with the criteria in Article VIII, and from Article XI in the Zoning Ordinance,[1] then the following provisions apply:
A.
Residential structures.
(1)
In AE Zones, any new construction or substantial improvement shall
have the lowest floor (including basement) elevated up to, or above,
the regulatory flood elevation.
(2)
In A Zones and/or where there are no base flood elevations specified on the FIRM, any new construction or substantial improvement shall have the lowest floor (including basement) elevated up to, or above, the regulatory flood elevation determined in accordance with § 186-18C and/or D of this chapter.
(3)
The design and construction standards and specifications contained
in the 2009 International Building Code (IBC) and in the 2009 International
Residential Code (IRC) or the latest edition thereof adopted by the
Commonwealth of Pennsylvania, and ASCE 24 and 34 Pa. Code (Chapters
401 to 405, as amended) shall be utilized, where they are more restrictive.
B.
Nonresidential structures.
(1)
In AE Zones, any new construction or substantial improvement of a
nonresidential structure shall have the lowest floor (including basement)
elevated up to, or above, the regulatory flood elevation, or be designed
and constructed so that the space enclosed below the regulatory flood
elevation:
(2)
In A Zones and/or where no base flood elevations are specified on the FIRM, any new construction or substantial improvement shall have the lowest floor (including basement) elevated or completely floodproofed up to, or above, the regulatory flood elevation determined in accordance with § 186-18C of this chapter.
(3)
Any nonresidential structure, or part thereof, made watertight below
the regulatory flood elevation shall be floodproofed in accordance
with the W1 or W2 space classification standards contained in the
publication entitled "Flood-Proofing Regulations," published by the
U.S. Army Corps of Engineers (June 1972, as amended March 1992) or
with some other equivalent standard. All plans and specifications
for such floodproofing shall be accompanied by a statement certified
by a registered professional engineer or architect which states that
the proposed design and methods of construction are in conformance
with the above-referenced standards. There should be a statement submitted
with the permit application and a statement submitted with the as-built
floodproofing certificate prior to the issuance of the certificate
of occupancy.
(4)
Any nonresidential structure that will be floodproofed must submit
the following to the Floodplain Administrator along with the nonresidential
floodproofing certificate and prior to the issuance of the certificate
of occupancy:
(a)
An inspection and maintenance plan detailing the annual maintenance
of floodproofed components ensuring that all components will operate
properly under flood conditions. Components that must be inspected
include at a minimum:
(b)
Flood emergency operation plan detailing the procedures to be
followed during a flooding event, and must include information pertaining
to how all components will operate properly under all conditions,
including power failures. The design professional must produce the
plan. An adequate plan must include the following:
[1]
An established chain of command and responsibility with leadership
responsibilities clearly defined for all aspects of the plan.
[2]
A procedure for notification of necessary parties when flooding
threatens and flood warnings are issued. Personnel required to be
at the building should have a planned and safe means of ingress and
should have no other emergency response duties during a flood event.
Alternates should be assigned in the event that the primary persons
responsible are unable to complete their assigned duties under the
plan.
[3]
A list of specific duties assigned to ensure that all responsibilities
are addressed expeditiously. The locations of materials necessary
to properly install all floodproofing components must be included
in the list.
[4]
An evacuation plan for all personnel or occupants; those without
duties for the flood emergency as well as those with duties for implementing
the plan. All possible ingress and egress routes must be identified.
[5]
A periodic training and exercise program to keep personnel and
occupants aware of their duties and responsibilities. Training drills
should be held at least once a year and should be coordinated with
community officials.
(5)
The design and construction standards and specifications contained
in the 2009 International Building Code (IBC) and in the 2009 International
Residential Code (IRC) or the latest revision thereof as adopted by
the Commonwealth of Pennsylvania, and ASCE 24 and 34 Pa. Code (Chapters
401 to 405, as amended) shall be utilized, where they are more restrictive.
C.
Space below the lowest floor.
(1)
Fully enclosed space below the lowest floor (excluding basements)
which will be used solely for the parking of a vehicle, building access,
or incidental storage in an area other than a basement, shall be designed
and constructed to allow for the automatic entry and exit of floodwaters
for the purpose of equalizing hydrostatic forces on exterior walls.
The term "fully enclosed space" also includes crawl spaces.
(2)
Designs for meeting this requirement must either be certified by
a registered professional engineer or architect, or meet or exceed
the following minimum criteria:
(a)
A minimum of two openings having a net total area of not less
than one square inch for every square foot of enclosed space installed
on two separate walls.
(b)
The bottom of all openings shall be no higher than one foot
above grade.
(c)
Openings may be equipped with screens, louvers, or other coverings
or devices provided that they permit the automatic entry and exit
of floodwaters.
D.
Historic structures. Historic structures undergoing repair or rehabilitation
that would constitute a substantial improvement as defined in this
chapter must comply with all chapter requirements that do not preclude
the structure's continued designation as an historic structure.
Documentation that a specific chapter requirement will cause removal
of the structure from the National Register of Historic Places or
the State Inventory of Historic places must be obtained from the Secretary
of the Interior or the State Historic Preservation Officer. Any exemption
from chapter requirements will be the minimum necessary to preserve
the historic character and design of the structure.
The following minimum standards shall apply for all construction
and development proposed within any identified floodplain area:
A.
Fill.
(2)
If fill is used, it shall:
(a)
Extend laterally at least 15 feet beyond the building line from
all points;
(b)
Consist of soil or small rock materials only; sanitary landfills
shall not be permitted;
(c)
Be compacted to provide the necessary permeability and resistance
to erosion, scouring, or settling;
(d)
Be no steeper than one vertical to two horizontal feet unless
substantiated data justifying steeper slopes are submitted to, and
approved by, the Floodplain Administrator; and
(e)
Be used to the extent to which it does not adversely affect
adjacent properties.
B.
Drainage facilities. Storm drainage facilities shall be designed
to convey the flow of stormwater runoff in a safe and efficient manner.
The system shall ensure proper drainage along streets, and provide
positive drainage away from buildings. The system shall also be designed
to prevent the discharge of excess runoff onto adjacent properties.
C.
Water and sanitary sewer facilities and systems.
(1)
All new or replacement water supply and sanitary sewer facilities
and systems shall be located, designed and constructed to minimize
or eliminate flood damages and the infiltration of floodwaters.
(2)
Sanitary sewer facilities and systems shall be designed to prevent
the discharge of untreated sewage into floodwaters.
(3)
No part of any on-site waste disposal system shall be located within
any identified floodplain area except in strict compliance with all
state and local regulations for such systems. If any such system is
permitted, it shall be located so as to avoid impairment to it, or
contamination from it, during a flood.
(4)
The design and construction provisions of the UCC and FEMA No. 348,
Protecting Building Utilities From Flood Damages, and The International
Private Sewage Disposal Code shall be utilized.
D.
Other utilities. All other utilities such as gas lines, electrical
and telephone systems shall be located, elevated (where possible)
and constructed to minimize the chance of impairment during a flood.
E.
Streets. The finished elevation of all new streets shall be no more
than one foot below the regulatory flood elevation.
F.
Storage. All materials that are buoyant, flammable, explosive, or in times of flooding could be injurious to human, animal, or plant life, and not listed in § 186-25, Development which may endanger human life, shall be stored at or above the regulatory flood elevation or floodproofed to the maximum extent possible.
G.
Placement of buildings and structures. All buildings and structures
shall be designed, located, and constructed so as to offer the minimum
obstruction to the flow of water and shall be designed to have a minimum
effect upon the flow and height of floodwater.
H.
Anchoring.
(1)
All buildings and structures shall be firmly anchored in accordance
with accepted engineering practices to prevent flotation, collapse,
or lateral movement.
(2)
All air ducts, large pipes, storage tanks, and other similar objects
or components located below the regulatory flood elevation shall be
securely anchored or affixed to prevent flotation.
I.
Floors, walls and ceilings.
(1)
Wood flooring used at or below the regulatory flood elevation shall
be installed to accommodate a lateral expansion of the flooring, perpendicular
to the flooring grain without causing structural damage to the building.
(2)
Plywood used at or below the regulatory flood elevation shall be
of a marine or water-resistant variety.
(3)
Walls and ceilings at or below the regulatory flood elevation shall
be designed and constructed of materials that are water-resistant
and will withstand inundation.
(4)
Windows, doors, and other components at or below the regulatory flood
elevation shall be made of metal or other water-resistant material.
J.
Paints and adhesives.
(1)
Paints and other finishes used at or below the regulatory flood elevation
shall be of marine or water-resistant quality.
(2)
Adhesives used at or, below the regulatory flood elevation shall
be of a marine or water-resistant variety.
(3)
All wooden components (doors, trim, cabinets, etc.) used, at or below
the regulatory flood elevation shall be finished with a marine or
water-resistant paint or other finishing material.
L.
Equipment.
(1)
Water heaters, furnaces, air-conditioning and ventilating units,
and other electrical, mechanical or utility equipment or apparatus
shall not be located below the regulatory flood elevation and shall
be anchored to resist floatation, collapse, and lateral movement.
(2)
Ductwork shall be elevated to or above the regulatory flood elevation
or floodproofed to remain water resistant.
M.
Fuel supply systems. All gas and oil supply systems shall be designed
to prevent the infiltration of floodwaters into the system and discharges
from the system into floodwaters. Additional provisions shall be made
for the drainage of these systems in the event that floodwater infiltration
occurs.
N.
Uniform Construction Code coordination. The standards and specifications
contained in 34 Pa. Code (Chapters 401 to 405, as amended) and not
limited to the following provisions shall apply to the above and other
sections and subsections of this chapter, to the extent that they
are more restrictive and supplement the requirements of this chapter.
(1)
International Building Code (IBC) 2009 or the latest revision thereof
as adopted by the Commonwealth of Pennsylvania: Secs. 801, 1202, 1403,
1603, 1605, 1612, 3402, and Appendix G.
(2)
International Residential Building Code (IRC) 2009 or the latest
revision thereof as adopted by the Commonwealth of Pennsylvania: Secs.
R104, R105, R109, R322, Appendix E, and Appendix J.
Within any identified floodplain area, any structure of the kind described in Subsection A, below, shall be prohibited. If a variance is obtained in accordance with the criteria in Article VIII and from Article XI in the Zoning Ordinance[1] then the following provisions in Subsections B, C, and
D below shall apply:
A.
In accordance with the Pennsylvania Flood Plain Management Act,[2] and the regulations adopted by the Department of Community
and Economic Development as required by the Act, any new or substantially
improved structure which: 1) will be used for the production or storage
of any of the following dangerous materials or substances; or 2) will
be used for any activity requiring the maintenance of a supply of
more than 550 gallons, or other comparable volume, of any of the following
dangerous materials or substances on the premises; or 3) will involve
the production, storage, or use of any amount of radioactive substances,
shall be subject to the provisions of this section, in addition to
all other applicable provisions. The following list of materials and
substances are considered dangerous to human life:
Acetone
| |
Ammonia
| |
Benzene
| |
Calcium carbide
| |
Carbon disulfide
| |
Celluloid
| |
Chlorine
| |
Hydrochloric acid
| |
Hydrocyanic acid
| |
Magnesium
| |
Nitric acid and oxides of nitrogen
| |
Petroleum products (gasoline, fuel oil, etc.)
| |
Phosphorus
| |
Potassium
| |
Sodium
| |
Sulphur and sulphur products
| |
Pesticides (including insecticides, fungicides, and rodenticides)
| |
Radioactive substances, insofar as such substances are not otherwise
regulated
|
[2]
Editor's Note: See 32 P.S. § 679.101 et seq.
B.
Within any identified floodplain area, any new or substantially improved structure of the kind described in Subsection A, above, shall be prohibited within the area measured 50 feet landward from the top-of-bank of any watercourse, extended for such additional distance from said banks as is or may be subject to inundation by waters of the base flood with an additional "no structure" setback of 50 feet except as permitted by Zoning Ordinance[3] or herein.
C.
Within any Floodway Area, any structure of the kind described in Subsection A, above, shall be prohibited. Where permitted within any identified floodplain area, any new or substantially improved residential structure of the kind described in Subsection A, above, shall be elevated to remain completely dry up to at least 1 1/2 feet above base flood elevation and built in accordance with §§ 186-22, 186-23 and 186-24.
D.
Where permitted within any identified floodplain area, any new or substantially improved nonresidential structure of the kind described in Subsection A, above, shall be built in accordance with §§ 186-22, 186-23 and 186-24, including:
(1)
Elevated, or designed and constructed to remain completely dry up
to at least 1 1/2 feet above base flood elevation; and
(2)
Designed to prevent pollution from the structure or activity during
the course of a base flood.
(3)
Any such structure, or part thereof, that will be built below the
regulatory flood elevation shall be designed and constructed in accordance
with the standards for completely dry floodproofing contained in the
publication "Flood-Proofing Regulations" (U.S. Army Corps of Engineers,
June 1972 as amended March 1992), or with some other equivalent watertight
standard.
All subdivision proposals and land development proposals containing
at least 50 lots or at least five acres, whichever is the lesser,
in identified floodplain areas where base flood elevation data are
not available, shall be supported by hydrologic and hydraulic engineering
analyses that determine base flood elevations and floodway information.
The analyses shall be prepared by a licensed professional engineer
in a format required by FEMA for a conditional letter of map revision
(CLOMR) and letter of map revision (LOMR). Submittal requirements
and processing fees shall be the responsibility of the applicant.
A.
Within any identified floodplain area manufactured homes shall be
prohibited within the area measured 50 feet landward from the top-of-bank
of any watercourse, extended for such additional distance from said
banks as is or may be subject to inundation by waters of the base
flood with an additional "no structure" setback of 50 feet except
as permitted by Zoning Ordinance[1] or herein.
B.
Where permitted within any identified floodplain area, all manufactured
homes, and any improvements thereto, shall be:
C.
Equipment requirement:
(1)
Water heaters, furnaces, air-conditioning and ventilating units,
and other electrical, mechanical or utility equipment or apparatus
shall not be located below the regulatory flood elevation and shall
be anchored to resist floatation, collapse, and lateral improvement.
(2)
Ductwork shall be elevated to or above the regulatory flood elevation
or floodproofed to remain water resistant.
D.
Installation of manufactured homes shall be done in accordance with
the manufacturers' installation instructions as provided by the
manufacturer. Where the applicant cannot provide the above information,
the requirements of Appendix E of the 2009 International Residential
Building Code or the U.S. Department of Housing and Urban Development's
Permanent Foundations for Manufactured Housing, 1984 Edition, draft
or latest revision thereto and 34 Pa. Code Chapters 401 to 405 shall
apply.
E.
Consideration shall be given to the installation requirements of
the 2009 IBC, and the 2009 IRC or the latest revision thereto as adopted
by the Commonwealth of Pennsylvania, and 34 Pa. Code, as amended where
appropriate and/or applicable to units where the manufacturers'
standards for anchoring cannot be provided or were not established
for the proposed unit(s) installation.