(CHAPTER 1 [CE] SCOPE AND ADMINISTRATION)
|
(SECTION C101 SCOPE AND GENERAL REQUIREMENTS)
|
C101.1 Title. This code shall be known as the Energy
Conservation Code of St. Charles County, Missouri, and shall be cited
as such. It is referred to herein as "this code."
|
(SECTION C103 CONSTRUCTION DOCUMENTS)
|
C103.1 General. Construction documents and other
data shall be submitted as required by the Code Official, with each
application for a permit. The Code Official shall be prepared by a
registered design professional where required by the statutes of the
jurisdiction in which the project is to be constructed. Where special
conditions exist, the Code Official is authorized to require necessary
construction documents to be prepared by a registered design professional.
|
Exception: The Code Official shall
have the authority to waive the submission of construction documents
or other supporting data if the Code Official determines they are
not necessary to confirm compliance with this code.
|
C103.1.2 Electronic submission. Where
design documents, including, but not limited to, plot plans, site
plans, design drawings, specifications, etc. are originally created
electronically, the Building Official is authorized to require electronic
submittal of documents in a portable document format (PDF) or similar
format for review. Where design documents were originally prepared
on paper and are submitted in a paper form, the Code Official is authorized
to charge a fee for converting those drawings to PDF equal to the
cost incurred by County staff recreating the document and not to exceed
more than one dollar ($1.00) per page.
|
Exception: Where submittal documents
were originally prepared by hand and are eleven (11) inches by seventeen
(17) inches or less, the fee for document conversion shall not be
charged.
|
(SECTION C109 STOP WORK ORDER)
|
C109.2 Issuance. The stop work order shall be in
writing and shall be given to the owner of the property, the owner's
authorized agent or the person performing the work. Upon issuance
of a stop work order, the cited work shall immediately cease. The
stop work order shall state the reason for the order and the conditions
under which the cited work will is authorized to resume. Any person
served with a stop work order shall pay an administrative penalty
of up to two hundred fifty dollars ($250.00).
|
(SECTION C110 MEANS OF APPEALS)
|
C110.1 General. For the purposes of this code, all appeals shall be in accordance with the procedure established for the Building Code of St. Charles County, Missouri, in Section 113 of Section 500.100.
|
C110.2 Limitations on authority. Delete in its
entirety.
|
C110.3 Qualifications. Delete in its entirety.
|
(CHAPTER 2 [CE] DEFINITIONS)
|
(SECTION C202 GENERAL DEFINITIONS)
|
RESIDENTIAL BUILDING. For this code, includes Group R-2, R-3,
and R-4 buildings three (3) stories or less in height above grade
|
(CHAPTER 1 [RE] SCOPE AND ADMINISTRATION)
|
(SECTION R101 SCOPE AND GENERAL REQUIREMENTS)
|
R101.1 Title. This code shall be known as the Energy
Conservation Code of St. Charles County, Missouri, and shall be cited
as such. It is referred to herein as "this code."
|
(SECTION R103 CONSTRUCTION DOCUMENTS)
|
R103.1 General. Construction documents and other
data shall be submitted as required by the Code Official, with each
application for a permit. The Code Official shall be prepared by a
registered design professional where required by the statutes of the
jurisdiction in which the project is to be constructed. Where special
conditions exist, the Code Official is authorized to require necessary
construction documents to be prepared by a registered design professional.
|
Exception: The Code Official shall
have the authority to waive the submission of construction documents
or other supporting data if the Code Official determines they are
not necessary to confirm compliance with this code.
|
R103.1.2 Electronic submission. Where
design documents, including, but not limited to, plot plans, site
plans, design drawings, specifications, etc. are originally created
electronically, the Building Official is authorized to require electronic
submittal of documents in a portable document format (PDF) or similar
format for review. Where design documents were originally prepared
on paper and are submitted in a paper form, the Code Official is authorized
to charge a fee for converting those drawings to PDF equal to the
cost incurred by County staff recreating the document and not to exceed
more than one dollar ($1.00) per page.
|
Exception: Where submittal documents
were originally prepared by hand and are eleven (11) inches by seventeen
(17) inches or less, the fee for document conversion shall not be
charged.
|
(SECTION R109 STOP WORK ORDER)
|
R109.2 Issuance. The stop work order shall be in
writing and shall be given to the owner of the property, the owner's
authorized agent or the person performing the work. Upon issuance
of a stop work order, the cited work shall immediately cease. The
stop work order shall state the reason for the order and the conditions
under which the cited work will is authorized to resume. Any person
served with a stop work order shall pay an administrative penalty
of up to two hundred fifty dollars ($250.00).
|
(SECTION R110 MEANS OF APPEALS)
|
R110.1 General. For the purposes of this code,
all appeals shall be in accordance with the procedure established
for the Building Code of St. Charles County, Missouri, in Section
113 of 500.010.
|
R110.2 Limitations on authority. Delete in its
entirety.
|
R110.3 Qualifications. Delete in its entirety.
|
(CHAPTER 2 [RE] DEFINITIONS)
|
(SECTION R202 GENERAL DEFINITIONS)
|
RESIDENTIAL BUILDING. For this code, includes Group R-2, R-3,
and R-4 buildings three (3) stories or less in height above grade.
|
(CHAPTER 4 [RE] RESIDENTIAL ENERGY EFFICIENCY)
|
(SECTION R402 BUILDING THERMAL ENVELOPE)
|
Replace Table R402.1.3 entitled "Insulation Minimum R-Values
And Fenestration Requirements By Component" with the table provided
below:
|
TABLE R402.1.3
| ||||||||||
---|---|---|---|---|---|---|---|---|---|---|
INSULATION MINIMUM R-VALUES AND FENESTRATION REQUIREMENTS BY
COMPONENTa
| ||||||||||
CLIMATE ZONE
|
FENESTRATION U-FACTORb,i
|
SKYLIGHTb U-FACTOR
|
GLAZED FENESTRATION SHGCb,e
|
CEILING R-VALUE
|
WOOD FRAME WALL R-VALUEg
|
MASS WALL R-VALUEh
|
FLOOR R-VALUE
|
BASEMENTc,g WALL R-VALUE
|
SLABd R-VALUE & DEPTH
|
CRAWL SPACEc,g WALL R-VALUE
|
4A
|
.35
|
.60
|
NR
|
38
|
13
|
5/10
|
19
|
10ci or 13j
|
10, 2 ft
|
10/13
|
For SI: 1 foot = 304.8 mm.
| ||
NR = Not Required.
| ||
ci = continuous insulation.
| ||
a.
|
R-values are minimums. U-factors and SHGC are maximums. Where
insulation is installed in a cavity that is less than the label or
design thickness of the insulation, the installed R-value of the insulation
shall be not less than the R-value specified in the table.
| |
b.
|
The fenestration U-factor column excludes skylights. The SHGC
column applies to all glazed fenestration.
| |
Exception: In Climate Zones 0 through 3, skylights
shall be permitted to be excluded from glazed fenestration SHGC requirements
provided that the SHGC for such skylights does not exceed 0.30.
| ||
c.
|
"5ci or 13" means R-5 continuous insulation (ci) on the interior
or exterior surface of the wall or R-13 cavity insulation on the interior
side of the wall. "10ci or 13" means R-10 continuous insulation (ci)
on the interior or exterior surface of the wall or R-13 cavity insulation
on the interior side of the wall. "15ci or 19 or 13 & 5ci" means
R-15 continuous insulation (ci) on the interior or exterior surface
of the wall; or R-19 cavity insulation on the interior side of the
wall; or R-13 cavity insulation on the interior of the wall in addition
to R-5 continuous insulation on the interior or exterior surface of
the wall.
| |
d.
|
R-5 insulation shall be provided under the full slab area of
a heated slab in addition to the required slab edge insulation R-value
for slabs. as indicated in the table. The slab-edge insulation for
heated slabs shall not be required to extend below the slab.
| |
e.
|
There are no SHGC requirements in the Marine Zone.
| |
f.
|
Basement wall insulation is not required in Warm Humid locations
as defined by Figure R301.1 and Table R301.1.
| |
g.
|
The first value is cavity insulation; the second value is continuous
insulation. Therefore, as an example, "13 & 5" means R-13 cavity
insulation plus R-5 continuous insulation.
| |
h.
|
Mass walls shall be in accordance with Section R402.2.5. The
second R-value applies where more than half of the insulation is on
the interior of the mass wall.
| |
i.
|
A maximum U-factor of 0.32 shall apply in Climate Zones 3 through
8 to vertical fenestration products installed in buildings located
either:
| |
1.
|
Above four thousand (4,000) feet in elevation; or
| |
2.
|
In windborne debris regions where protection of openings is
required by Section R301.2.1.2 of the International Residential Code.
| |
j.
|
Exception: Unfinished basements may have up to
a maximum of twenty percent (20%) of the total basement wall area
exposed above the outside finished grade/ground level as uninsulated
concrete foundation walls. The foundation wall area above the outside
grade/ground level that may be uninsulated is determined by the formula
[.20 times the basement wall height of all walls (including insulated
exterior frame walls for walkout basements and walls common to both
basement and attached garages) times the perimeter of these basement
walls]. In unfinished areas, the basement foundation wall insulation
shall extend down to the basement floor slab or to a minimum of twenty-four
(24) inches below outside finished grade when the grade is above the
floor slab elevation.
|