No building shall be erected on any lot within a subdivision without separate written permission for each lot. This permission is in addition to any other permits required for building, such as a permit from the Building Inspector required by other town bylaws.
A. The developer shall submit a written request for lot releases to the Board. Such request(s) shall include the Definitive Plan Book and plan number(s), the Deed Book and page number(s) of the approval, the Deed Book and page number(s) of the covenant, subdivision lot number(s), requested for lot release and the Assessor's Map and parcel number(s) of the lot(s) requested for release.
B. Upon receipt of such properly submitted request(s) for release, the Board shall schedule such request(s) for the next available regular Board meeting.
C. The Board shall review the request in terms of progress of the developer (generally, and in terms of the construction schedule), condition of the site, compliance with applicable regulations and requirements, and surety posted with the Board.
D. Prior to consideration of lot release the developer shall provide the Board with a layout plan and as-built (progress print) bearing a wet stamp and signature of the Registered Land Surveyor and Professional Engineer.
E. Prior to the issuance of lot release, certification shall be provided to the Department of Public Works that all approved street lights have been installed, energized and operational within the planned occupied areas.