A.
Preconstruction Conference. Before the initiation of any work within the subdivision, the applicant must arrange for a preconstruction conference with the Planning Office, at which time a work schedule, outlining all steps within the development process, must be submitted by the applicant. Following approval of the work schedule by the Planning Office, the applicant will be required to notify the Planning Office, in writing, of any deviations from the proposed work schedule.
B.
Notification. The Planning Office and Town Engineer must be separately notified, at least 48 hours (excluding Saturdays, Sundays, and legal holidays) before beginning any of the following work:
(1)
Cutting of trees for street construction.
(2)
Clearing and grubbing of a right-of-way.
(3)
Installation of storm drainage facilities.
(4)
Installation of water and sanitary sewer facilities.
(5)
Placing of material for subbase.
(6)
Excavation for the underground electric distribution system.
(7)
Application of gravel in or above subbase.
(8)
Laying of bituminous concrete bottom course.
(9)
Laying of bituminous concrete top course.
(10)
Installation of curbing and curb inlets.
(11)
Spreading of gravel in sidewalks.
(12)
Laying bituminous concrete for sidewalks and aprons.
(13)
Spreading of loam for grass plots.
(14)
Grading of slopes.
(15)
Construction of retaining walls.
(16)
Setting of bounds.
C.
Allocation of Risk. If any of the above-designated work is commenced without proper notification being given as specified, such work is performed at the risk of the applicant or owner; and the Town Engineer may order the removal of them at the expense of the applicant or owner. All inspections performed by the Town Engineer or her or his designee are at the expense of the applicant. Subdivision bonds will not be released until all such expenses have been paid to the Board.