A.
Scope.
(1)
No person shall commence to erect, alter, occupy or convert any structure or building, alter the use of any land or structure, or commence grading until the Zoning Officer issues a zoning permit authorizing such change or construction.
(2)
No person shall excavate or store material or equipment on a lot in connection with the erection, construction, placement, reconstruction, alteration, repair, extension, replacement, restoration or conversion of any structure, building or sign until the Zoning Officer issues a zoning permit authorizing such activity.
(3)
No person shall expand or change a nonconforming use, nor add to a nonconforming structure, nor change the use of land on which a nonconforming use or structure is situate, until the Zoning Officer issues a zoning permit authorizing such activity.
B.
Types of uses.
(1)
A zoning permit for a permitted use may be issued by the Zoning Officer.
(2)
A zoning permit for a use requiring a special exception or variance shall be issued by the Zoning Officer only upon the written order of the Zoning Hearing Board after a hearing.
(3)
A zoning permit for a conditional use shall be issued by the Zoning Officer only upon the written order of the Borough Council following a review by the Planning Commission.
C.
Application.
(1)
All applications for a zoning permit shall be in writing on a form provided by the Borough of Bath Zoning Officer and shall be submitted to the Zoning Officer together with the required fee.
(2)
By whom applications are made. All requests for permits shall be made in writing by the legal or equitable owner of the subject property or their authorized agents or appointees. The owner or equitable owner shall execute an affidavit through which he/she/it states, under oath, that any agent is authorized to make the application pursuant to this section.
(3)
Compliance with other statutes. Prior to the issuance of any zoning permit, the Zoning Officer shall review the application for such permit to determine if all other governmental permits known by the Zoning Officer to be needed (such as those required by the Pennsylvania Department of Labor and Industry for fire safety of rental units or business establishments, the Pennsylvania Sewage Facilities Act[1] or the Federal Water Pollution Control Act) have been obtained. No permit shall be issued until this determination has been made. The Borough is not responsible for notifying the applicants of all permits needed.
[1]
Editor's Note: See 35 P.S. § 750.1 et seq.
(4)
Review. In addition to the required reviews, the Zoning Officer may submit a copy of any plan and application to any appropriate agencies and/or individuals (e.g., Planning Commission, Borough Engineer, etc.) for review and comment.
D.
Plans and specifications. Requests for zoning permits shall be accompanied by two copies of a plot plan which shall:
(1)
Be drawn to the scale one inch equals 20 feet.
(2)
Show the size and location of all new construction as well as the location of all existing buildings, structures and signs.
(3)
Show the dimensions and area, in square feet and in acres, of the lot and buildings situate thereon.
(4)
Show the distance of all lot lines to the building restriction line.
(5)
Show the location of all streets.
(6)
Show all established and proposed street, driveway, parking area and finished lot grades.
(7)
Show all proposed and existing parking and loading areas.
E.
Conditions of permit. The Zoning Officer shall not issue a zoning permit unless the following conditions have been met or are satisfied:
(1)
Written approval, where required, from the Zoning Hearing Board or Borough Council with all conditions required by the Zoning Hearing Board or Borough Council attached thereto, has been received.
(2)
A written statement from the Zoning Officer that the conditions as listed in the Zoning Hearing Board's or Borough Council's written approval have been met, satisfied or are substantially complete, shall have been placed in the Borough's file regarding the application.
(3)
All applications and support documents have been revised in accordance with the conditions of any approval given by the Zoning Hearing Board or Borough Council.
(4)
The building and use conform to the provisions of this chapter and all other chapters in the Borough except for:
(a)
Variances to this chapter granted or special exceptions allowed and approved by the Zoning Hearing board as hereinbefore set forth.
(b)
Nonconforming buildings or uses existing prior to the enactment of this chapter.
(c)
Conditional uses allowed or approved by Council.
(d)
Special exceptions granted by the Zoning Hearing Board.
F.
Issuance.
(1)
The Zoning Officer shall issue or refuse an application for a zoning permit for a use permitted by right within 30 days after the date of such application was made except as specifically provided for in this chapter, or if an extension is granted by the applicant.
(2)
A zoning permit shall be issued in at least triplicate.
(3)
One copy shall be conspicuously posted by the applicant on the premises. No person shall perform building operations of any kind unless a zoning permit is being displayed as required by this chapter.
(4)
After the issuance of a zoning permit by the Zoning Officer, no changes of any kind shall be made to the application, permit, plans, specifications or other documents submitted with the application without the written consent of the Zoning Officer.
G.
Compliance with permit. All work to or any use of any building, structure, sign or land shall conform to the approved application and plan for which the zoning permit was issued and any approved amendments thereto. The permit shall not be construed as authority to violate, cancel or set aside the provisions of this or any other chapter unless otherwise expressly stated upon the zoning permit.
H.
Duration of zoning permit.
(1)
Except where the duration of the use or building is limited by action of the Zoning Hearing Board, Borough Council or provisions of this chapter or any amendment thereto, a zoning permit shall be valid until such time as there is a change in use or condition for which the zoning permit was originally issued.
(2)
Where the duration of the use or building has been limited by action of the Zoning Hearing Board, Borough Council or provisions of this chapter, or any amendment thereto, the life of the zoning permit shall be equally limited. In the event that a variance has been granted or other action has been authorized by the Zoning Hearing Board, the applicant shall secure the necessary permits and commence the authorized action, construction or alteration within 180 days of the final action of the Zoning Hearing Board. The applicant may request, in writing, extensions of the one-hundred-eighty-day period stating the reasons for delay. Unless the Zoning Hearing Board finds such reasons for delay justifiable, it may refuse to extend the one-hundred-eighty-day period and may, after expiration of said one-hundred-eighty-day period, rescind or revoke the granted variance, authorization and permit. When it is suspected that the authorized construction or development will commence in phases over an extended period of time, the Zoning Hearing Board may establish a schedule for the procurement of permits in lieu of the one-hundred-eighty-day period specified hereinabove. Such permit issued shall become invalid if the authorized work is suspended or abandoned for a period of one year after the time of commencing work. Upon expiration or invalidation of the zoning permit, all other permits issued thereon shall become invalid.