The Stormwater Authority or its designated agent shall make
inspections as outlined in the regulations to verify and document
compliance with the land disturbance permit.
The Stormwater Authority may require the applicant to post,
before the start of land disturbance or construction activity, a surety
bond, irrevocable letter of credit, cash, or other acceptable security.
The form of the bond shall be approved by the Stormwater Authority
and shall be in an amount deemed sufficient by the Stormwater Authority
to ensure that the work will be completed in accordance with the permit.
If the project is phased, the Stormwater Authority may release part
of the bond as each phase is completed in compliance with the permit.