A.
All regulated activities in the municipality which do not fall under the exemption criteria shown in § 190-105 of this chapter shall submit a stormwater management plan consistent with this chapter, Title 25 of the Pa. Code, and the Clean Streams Law,[1] to the municipality for review and approval. These criteria shall apply to the total proposed development even if development is to take place in stages. Impervious surface shall include, but not be limited to, any roof, parking or driveway areas and any new streets and sidewalks. Any areas designed to be gravel or crushed stone shall be assumed to be impervious.
[1]
Editor's Note: See 35 P.S. § 691.1 et seq.
B.
Stormwater drainage systems shall be provided in order to permit unimpeded flow along natural watercourses, except as modified by stormwater management facilities designed to encourage infiltration, groundwater recharge, and improved water quality.
C.
Existing points of concentrated drainage that discharge onto adjacent property shall not be altered without written approval of the affected property owner(s) and shall be subject to any applicable discharge criteria specified in this chapter.
D.
Areas of existing sheet flow discharge shall be maintained wherever possible. If sheet flow is proposed to be concentrated and discharged onto adjacent property, the developer must document that adequate downstream conveyance facilities exist to safely transport the concentrated discharge, or otherwise prove that no erosion, sedimentation, flooding or other harm will result from the concentrated discharge; and submit written approval from the affected adjacent property owner(s).
E.
For all subdivision and land development applications, the tributary area discharging drainage to any location along the site property boundary shall not increase by more than 25% over the predevelopment condition without written approval from the adjacent affected property owner(s).
F.
Where a development site is traversed by watercourses, drainage easements shall be provided conforming to the line of such watercourses. The width of the easement shall be adequate to provide for the unimpeded flow of stormwater runoff from the one-hundred-year storm event. Terms of the easement shall prohibit excavation, the placing of fill or structures, and any alterations that may adversely affect the flow of stormwater within any portion of the easement. Periodic maintenance of the easement shall be required by the landowner to ensure proper runoff conveyance.
G.
When it can be shown that, due to topographic conditions, natural drainageways on the site cannot adequately provide for drainage, open channels may be constructed conforming substantially to the line and grade of such natural drainageways. Work within natural drainageways shall be subject to approval by PADEP through the joint permit application process, or, where deemed appropriate by PADEP, through the general permit process.
H.
Any stormwater management facilities regulated by this chapter that will be located in or adjacent to waters of the commonwealth or wetlands shall be subject to approval by PADEP through the joint permit application process or, where deemed appropriate by PADEP, the general permit process. When there is a question whether wetlands may be involved, it is the responsibility of the developer or his agent to show that the land in question cannot be classified as wetlands, otherwise approval to work in the area must be obtained from PADEP.
I.
Any stormwater management facilities regulated by this chapter that would be located on state highway rights-of-way, or discharge stormwater to facilities located within a state highway right-of-way, shall be subject to approval by the Pennsylvania Department of Transportation (PADOT).
J.
Low-impact development methods should be used to minimize site disturbance and impervious surface. Infiltration of stormwater runoff through seepage beds, infiltration trenches, etc., are encouraged, where soil conditions permit, to reduce the size or eliminate the need for retention/detention facilities.
K.
Roof drains and sump pumps shall discharge to a natural watercourse, drainage swale, or stormwater easement. Roof drains and sump pumps shall not be connected to a storm sewer or street drainage structure unless designed as part of a stormwater management facility. In no case shall roof drains or sump pumps be connected to a sanitary sewer.
L.
Whenever a watercourse is located within a development site, it shall remain open in the natural state and location and shall not be piped, impeded, or altered (except for road crossings). It is the responsibility of the developer to stabilize existing eroded stream/channel banks.
M.
Special requirements for watersheds draining to high-quality (HQ) and exceptional-value (EV) waters: The temperature and quality of water and streams that have been declared as exceptional-value and high-quality are to be maintained as defined in Chapter 93, Water Quality Standards, Title 25, Pennsylvania Department of Environmental Protection Rules and Regulations. Temperature-sensitive BMPs and stormwater conveyance systems are to be used and designed with storage pool areas and supply outflow channels, and shaded with trees. This will require modification of berms for permanent ponds and the relaxation of restrictions on planting vegetation within the facilities, provided that capacity for volumes and rate control is maintained. At a minimum, the southern half of pond shorelines shall be planted with shade or canopy trees within 10 feet of the pond shoreline. In conjunction with this requirement, the maximum slope allowed on the berm area to be planted is 10:1. This will lessen the destabilization of berm soils due to root growth. A long-term maintenance schedule and management plan for the thermal control BMPs is to be established and recorded for all development sites.
N.
All stormwater runoff shall be pretreated for water quality prior to discharge to surface or groundwater as required by § 190-305 of this chapter.
O.
The applicant shall provide adequate documentation to permit review of any alternate stormwater BMPs not addressed by this chapter. The municipality may obtain PADEP assistance to evaluate and approve alternative control measures.