The identified floodplain area shall be:
(a) Any areas of Township of Amity classified as special flood hazard
areas (SFHAs) in the Flood Insurance Study (FIS) and the accompanying
Flood Insurance Rate Maps (FIRMs) dated July 3, 2012, and issued by
the Federal Emergency Management Agency (FEMA) or the most recent
revision thereof, including all digital data developed as part of
the Flood Insurance Study.
The above-referenced FIS and FIRMs, and any subsequent revisions
and amendments are hereby adopted by the Township of Amity and declared
to be a part of this chapter.
(b) Any community identified flood hazard areas.
[Ord. No. 278, 6/20/2012]
The identified floodplain area shall consist of the following
specific areas:
(a) The Floodway Area/District identified as Floodway in the FIS which
represents the channel of a watercourse and the adjacent land areas
that must be reserved in order to discharge the base flood without
cumulatively increasing the water surface elevation by more than one
foot at any point. This term shall also include floodway areas which
have been identified in other available studies or sources of information
for those special floodplain areas where no floodway has been identified
in the FIS.
Within any floodway area, no encroachments, including fill,
new construction, substantial improvements, or other development shall
be permitted unless it has been demonstrated through hydrologic and
hydraulic analysis performed in accordance with standard engineering
practice that the proposed encroachment would not result in any increase
in flood levels within the community during the occurrence of the
base flood discharge.
No new construction or development shall be allowed, unless
a permit is obtained from the Department of Environmental Protection
Regional Office.
(b) The AE Area/District without floodway shall be those areas identified
as an AE Zone on the FIRM included in the FIS prepared by FEMA and
for which base flood elevations have been provided in the FIS but
no floodway has been delineated.
In AE Area/District without floodway, no new development shall
be permitted unless it can be demonstrated that the cumulative effect
of all past and projected development will not increase the BFE by
more than one foot.
(c) The A Area/District shall be those areas identified as an A Zone
on the FIRM included in the FIS prepared by FEMA and for which no
1% annual chance flood elevations have been provided. For these areas,
elevation and floodway information from other federal, state, or other
acceptable source shall be used when available. Where other acceptable
information is not available, the elevation shall be determined by
using the elevation of a point on the boundary of the identified floodplain
area which is nearest the construction site.
In lieu of the above, the municipality may require the applicant
to determine the elevation with hydrologic and hydraulic engineering
techniques. Hydrologic and hydraulic analyses shall be undertaken
only by professional engineers or others of demonstrated qualifications,
who shall certify that the technical methods used correctly reflect
currently accepted technical concepts. Studies, analyses, computations,
etc., shall be submitted in sufficient detail to allow a thorough
technical review by the municipality.
(d) Community identified flood hazard areas shall be those areas where
Amity Township has identified local flood hazard or ponding areas,
as delineated and adopted on a "local flood hazard map" using best
available topographic data and locally derived information such as
flood of record, historic high water marks, soils or approximate study
methodologies.
(e) No permit shall be granted for any construction, development, use,
or activity within any floodway area that would cause any increase
in the BFE.
(f) No permit shall be granted for any construction, development, use,
or activity within any AE Area/District without floodway unless it
is demonstrated that the cumulative effect of the proposed development
would not, together with all other existing and anticipated development,
increase the BFE more than one foot at any point.
(g) No new construction or development shall be located within the area
measured 50 feet landward from the top-of-bank of any watercourse.
[Ord. No. 278, 6/20/2012]
The identified floodplain area may be revised or modified by
the Township Board of Supervisors where studies or information provided
by a qualified agency or person documents the need for such revision.
However, prior to any such change, approval must be obtained from
the FEMA. Additionally, as soon as practicable, but not later than
six months after the date such information becomes available, a community
shall notify the FEMA of the changes by submitting technical or scientific
data.
[Ord. No. 278, 6/20/2012]
Should a dispute concerning any identified floodplain boundary
arise, an initial determination shall be made by the floodplain administrator
and any party aggrieved by this decision or determination may appeal
to the Township Board of Supervisors. The burden of proof shall be
on the appellant.
[Ord. No. 278, 6/20/2012]
Prior to development occurring in areas where annexation or
other corporate boundary changes are proposed or have occurred, the
community shall review flood hazard data affecting the lands subject
to boundary changes. The community shall adopt and enforce floodplain
regulations in areas subject to annexation or corporate boundary changes
which meet or exceed those in 44 CFR 60.3.