Monuments shall have been set in their required locations and certified to the Town.
Final grading shall be completed within the right-of-way, and all spoil shall be removed from the site.
All street and traffic signs shall be properly set in their designated locations.
A.
Record drawings and all testing results shall be supplied to the Town and are subject to their review and approval at least 15 calendar days prior to any dedication procedures.
B.
Record maps shall be prepared by a licensed professional and eight prints and a reproducible (Mylar) shall be submitted to the Town's Building Department. The record drawings shall contain, at a minimum, the following information:
(1)
The locations, sizes, elevations, lengths, slopes and invert and top elevations of all structures in sewer systems.
(2)
The elevations of any drainage swales and drainage structures to be dedicated to the Town.
(3)
The locations, including ties to all valves, curb boxes and hydrants to permanent structures.
(5)
Any other significant details affecting the operation or maintenance of any system by the Town.
(6)
The location of all facilities shall be tied to visible and reproducible objects.
The submission and acceptance of the two-year maintenance bonds shall be required for all improvements to be offered to the Town for dedication. Maintenance bonds shall be written by a surety licensed to do business in New York State, and they shall be in the amount of 10% of the final construction cost. Bonds shall be approved as to form and content by the Town Attorney prior to any dedication procedure.[1]