Type of Application | Period of Time for Action by Planning Board/Zoning Board of Adjustment (days) |
|---|---|
Minor subdivision or resubdivision | 45 |
Preliminary plat — 10 lots or less | 45 |
Preliminary plat — more than 10 lots | 95 |
Preliminary site plan — 10 acres of land or less | 45 |
Preliminary site plan — more than 10 acres of land | 95 |
Final plat | 45 |
Final site plan | 45 |
Failure of the Planning Board/Zoning Board of Adjustment to act within the period prescribed shall constitute approval and a certificate of the secretary of the Planning Board/Zoning Board of Adjustment as to the failure of the Planning Board/Zoning Board of Adjustment to act shall be issued on request of the applicant, which certificate shall be sufficient in lieu of the written endorsement or other evidence of approval as herein required, and shall be so accepted by the County Recording Officer for purposes of filing subdivision plats. |