AH ZONE
Areas subject to inundation by 1% annual chance shallow flooding
(usually areas of ponding) where average depths are between one and
three feet. Base flood elevations (BFEs) derived from detailed hydraulic
analyses are shown in this zone.
AO ZONE
Areas subject to inundation by 1% annual chance shallow flooding
(usually sheet flow on sloping terrain) where average depths are between
one and three feet.
APPEAL
A request for a review of the local administrator's
interpretation of any provision of this chapter or a request for a
variance.
AREA OF SHALLOW FLOODING
A designated AO or AH zone on a community's Digital
Flood Insurance Rate Map (DFIRM) with a 1% annual or greater chance
of flooding to an average depth of one to three feet where a clearly
defined channel does not exist, where the path of flooding is unpredictable
and where velocity flow may be evident. Such flooding is characterized
by ponding or sheet flow.
AREA OF SPECIAL FLOOD HAZARD
Land in the floodplain within a community subject to a 1%
or greater chance of flooding in any given year. It is shown on the
FIRM as Zone V, VE, V1-30, A, AO, A1-A30, AE, A99, or AH.
BASE FLOOD
A flood having a 1% chance of being equaled or exceeded in
any given year.
BASE FLOOD ELEVATION (BFE)
The flood elevation shown on a published Flood Insurance
Study (FIS) including the Flood Insurance Rate Map (FIRM). For zones
AE, AH, AO, and A1-30 the elevation represents the water surface elevation
resulting from a flood that has a 1% or greater chance of being equaled
or exceeded in any given year.
BASEMENT
Any area of the building having its floor subgrade (below
ground level) on all sides.
BEST AVAILABLE FLOOD HAZARD DATA
The most recent available flood risk guidance FEMA has provided.
The best available flood hazard data may be depicted on but not limited
to Advisory Flood Hazard Area Maps, Work Maps or preliminary FIS and
FIRM.
BEST AVAILABLE FLOOD HAZARD DATA ELEVATION
The most recent available flood elevation FEMA has provided.
The best available flood hazard data elevation may be depicted on
an Advisory Flood Hazard Area Map, Work Map or preliminary FIS and
FIRM.
BREAKAWAY WALL
A wall that is not part of the structural support of the
building and is intended through its design and construction to collapse
under specific lateral loading forces without causing damage to the
elevated portion of the building or supporting foundation system.
CUMULATIVE SUBSTANTIAL IMPROVEMENT
Any reconstruction, rehabilitation, addition, or other improvement
of a structure that equals or exceeds 50% [lower threshold e.g.: replace
50% with 40%] of the market value of the structure at the time of
the improvement or repair when counted cumulatively for 10 years.
DEVELOPMENT
Any man-made change to improved or unimproved real estate,
including but not limited to buildings or other structures, mining,
dredging, filling, grading, paving, excavation or drilling operations,
or storage of equipment or materials located within the area of special
flood hazard.
ELEVATED BUILDING
A nonbasement building built, in the case of a building in
an area of special flood hazard, to have the top of the elevated floor,
elevated above the base flood elevation plus freeboard by means of
piling, columns (posts and piers), or shear walls parallel to the
flow of the water, and adequately anchored so as not to impair the
structural integrity of the building during a flood up to the magnitude
of the base flood. In an area of special flood hazard "elevated building"
also includes a building elevated by means of fill or solid foundation
perimeter walls with openings sufficient to facilitate the unimpeded
movement of floodwaters.
EROSION
The process of gradual wearing away of land masses.
EXISTING MANUFACTURED HOME PARK OR SUBDIVISION
A manufactured home park or subdivision for which the construction
of facilities for servicing the lots on which the manufactured homes
are to be affixed (including, at a minimum, the installation of utilities,
the construction of streets, and either final site grading or the
pouring of concrete pads) is completed before the effective date of
the floodplain management regulations adopted by a community.
FLOOD INSURANCE RATE MAP (FIRM)
The official map on which the Federal Insurance Administration
has delineated both the areas of special flood hazards and the risk
premium zones applicable to the community.
FLOOD INSURANCE STUDY (FIS)
The official report in which the Federal Insurance Administration
has provided flood profiles, as well as the Flood Insurance Rate Map(s)
and the water surface elevation of the base flood.
FLOOD or FLOODING
A general and temporary condition of partial or complete
inundation of normally dry land areas from:
A.
The overflow of inland or tidal waters; and/or
B.
The unusual and rapid accumulation or runoff of surface waters
from any source.
FLOODPLAIN MANAGEMENT REGULATIONS
Zoning ordinances, subdivision regulations, building codes,
health regulations, special purpose ordinances (such as a floodplain
ordinance, grading ordinance and erosion control ordinance) and other
applications of police power. The term describes such state or local
regulations, in any combination thereof, which provide standards for
the purpose of flood damage prevention and reduction.
FLOODPROOFING
Any combination of structural and nonstructural additions,
changes, or adjustments to structures which reduce or eliminate flood
damage to real estate or improved real property, water and sanitary
facilities, structures and their contents.
FLOODWAY
The channel of a river or other watercourse and the adjacent
land areas that must be reserved in order to discharge the base flood
without cumulatively increasing the water surface elevation more than
0.2 foot.
FREEBOARD
A factor of safety usually expressed in feet above a flood
level for purposes of floodplain management. Freeboard tends to compensate
for the many unknown factors that could contribute to flood heights
greater than the height calculated for a selected size flood and floodway
conditions, such as wave action, bridge openings, and the hydrological
effect of urbanization of the watershed.
HIGHEST ADJACENT GRADE
The highest natural elevation of the ground surface prior
to construction next to the proposed or existing walls of a structure.
HISTORIC STRUCTURE
Any structure that is:
A.
Listed individually in the National Register of Historic Places
(a listing maintained by the Department of Interior) or preliminarily
determined by the Secretary of the Interior as meeting the requirements
for individual listing on the National Register;
B.
Certified or preliminarily determined by the Secretary of the
Interior as contributing to the historical significance of a registered
historic district or a district preliminarily determined by the Secretary
to qualify as a registered historic district;
C.
Individually listed on a state inventory of historic places
in states with historic preservation programs which have been approved
by the Secretary of the Interior; or
D.
Individually listed on a local inventory of historic places
in communities with historic preservation programs that have been
certified either:
(1)
By an approved state program as determined by the Secretary
of the Interior; or
(2)
Directly by the Secretary of the Interior in states without
approved programs.
LOWEST FLOOR
The lowest floor of the lowest enclosed area (including basement).
An unfinished or flood-resistant enclosure, usable solely for the
parking of vehicles, building access or storage in an area other than
a basement is not considered a building's lowest floor provided
that such enclosure is not built so to render the structure in violation
of other applicable nonelevation design requirements of 44 CFR Section
60.3.
MANUFACTURED HOME
A structure, transportable in one or more sections, which
is built on a permanent chassis and is designed for use with or without
a permanent foundation when attached to the required utilities. The
term "manufactured home" does not include a recreational vehicle.
NEW CONSTRUCTION
Structures for which the start of construction commenced
on or after the effective date of a floodplain regulation adopted
by a community and includes any subsequent improvements to such structures.
NEW MANUFACTURED HOME PARK OR SUBDIVISION
A manufactured home park or subdivision for which the construction
of facilities for servicing the lots on which the manufactured homes
are to be affixed (including at a minimum, the installation of utilities,
the construction of streets, and either final site grading or the
pouring of concrete pads) is completed on or after the effective date
of the floodplain management regulations adopted by the municipality.
RECREATIONAL VEHICLE
A vehicle which is built on a single chassis; 400 square
feet or less when measured at the longest horizontal projections;
designed to be self-propelled or permanently towable by a light-duty
truck; and designed primarily not for use as a permanent dwelling
but as temporary living quarters for recreational, camping, travel,
or seasonal use.
START OF CONSTRUCTION
A.
For other than new construction or substantial improvements
under the Coastal Barrier Resources Act (P.L. No. 97-348) includes
substantial improvements and means the date the building permit was
issued, provided the actual start of construction, repair, reconstruction,
rehabilitation, addition, placement, or other improvement was within
180 days of the permit date. The actual start means either the first
placement of permanent construction of a structure on a site such
as the pouring of a slab or footings, the installation of pilings,
the construction of columns, or any work beyond the stage of excavation,
or the placement of a manufactured home on a foundation.
B.
Permanent construction does not include land preparation, such
as clearing, grading and filling nor does it include the installation
of streets and/or walkways, nor does it include excavation for a basement,
footings or piers, or foundations or the erection of temporary forms,
nor does it include the installation on the property of accessory
buildings, such as garages or sheds not occupied as dwelling units
or not part of the main structure. For a substantial improvement,
the actual start of construction means the first alteration of any
wall, ceiling, floor, or other structural part of a building, whether
or not that alteration affects the external dimensions of the building.
STRUCTURE
A walled and roofed building, a manufactured home, or a gas
or liquid storage tank that is principally aboveground.
SUBSTANTIAL DAMAGE
Damage of any origin sustained by a structure whereby the
cost of restoring the structure to it's before damaged condition
would equal or exceed 50% of the market value of the structure before
the damage occurred. Substantial damage also means flood-related damages
sustained by a structure on two or more separate occasions during
a ten-year period for which the cost of repairs at the time of each
such flood event, on the average, equals or exceeds 25% of the market
valve of the structure before the damages occurred.
SUBSTANTIAL IMPROVEMENT
Any reconstruction, rehabilitation, addition, or other improvement
of a structure during a ten-year period the cost of which equals or
exceeds 50% of the market value of the structure before the "start
of construction" of the improvement. Substantial improvement also
means "cumulative substantial improvement." This term includes structures
which have incurred substantial damage, regardless of the actual repair
work performed or repetitive loss. The term does not, however, include
either:
A.
Any project for improvement of a structure to correct existing
violations of state or local health, sanitary or safety code specifications
which have been identified by the local code enforcement officer and
which are the minimum necessary to assure safe living conditions;
or
B.
Any alteration of a historic structure, provided that the alteration
will not preclude the structure's continued designation as a
historic structure.
VARIANCE
A grant of relief from the requirements of this chapter that
permits construction in a manner that would otherwise be prohibited
by this chapter.
VIOLATION
The failure of a structure or other development to be fully
compliant with this chapter. A new or substantially improved structure
or other development without the elevation certificate, other certifications,
or other evidence of compliance required in 44 CFR § 60.3(b)(5),
(c)(4), (c)(10), (e)(2), (e)(4), or (e)(5) is presumed to be in violation
until such time as that documentation is provided.
If any section, subsection, paragraph, sentence, clause, or
phrase of this chapter shall be declared invalid for any reason whatsoever,
such a decision shall not affect the remaining portions of the Ordinance,
which shall remain in full force and effect, and for this purpose
the provisions of this chapter are hereby declared to be severable.
Adoption. This chapter shall take effect immediately upon final
passage and publication according to law.