[Amended 10-12-2004]
A.
Design standards. All subdivisions shall be designed to meet the requirements of public safety, including, but not limited to, pedestrian and vehicle traffic safety, adequate stormwater drainage and sewage disposal, and with due regard for the rights, health and welfare of the inhabitants of the Town of Wakefield, including the future residents of the proposed subdivision.
B.
Conformance with plans and regulations. All improvements specified herein or shown on the approved definitive plan shall be installed by the applicant at no cost to the Town and in strict conformance with these rules and regulations and the approved plan.
C.
Construction inspection. In order that the Director of Public Works and Manager of the Municipal Light Department may properly inspect the work as it progresses, the applicant or subdivider will keep them informed at all times of the progress of the work as set forth in Form K,[1] and will continuously provide safe and convenient access to all parts of the work for inspection by the Director of Public Works and Manager of the Municipal Light Department or by such persons as they may designate for that purpose. No work will be approved that has been covered before such inspection.
[1]
Editor's Note: Form K is included at the end of this chapter.
D.
Initial utility as-built plans. Prior to installation of bituminous concrete binder on the roadway, the applicant must submit initial utility as-built plans to the Planning Board to verify the correct installation of utilities. The applicant is required to receive approval of the initial utility as-built plans by the Town Engineer before bituminous binder course is installed for the roadway. All discrepancies between the approved definitive plan and the initial utility as-built plans must be resolved before approval from the Planning Board may be granted.
The initial utility as-built plans shall follow the requirements listed in General Information, § 320-10C(1) and (2)(a) and include:
(1)
A plan at a scale acceptable to the Board.
(2)
Location and dimensions of the roadway and sidewalks.
(3)
Location and dimensions of all stormwater system components.
(4)
A roadway profile detailing the grade, depth, rim and invert elevations, and location of all subsurface utilities such as sewer, water, stormwater, and gas.
(5)
Plans shall utilize the horizontal datum of the Massachusetts State Plane Coordinate System NAD83 and the NAVD88 vertical datum.
These features may be included on the same plan only if the plan is deemed readable to the Board.
E.
As-built plans. Prior to release of sureties or covenant, the developer/contractor shall provide, within 10 days of substantial completion, as-built drawings to the Town of Wakefield Planning Board. The as-built drawings shall be drafted in a correct, readable and professional manner in a format compatible with the Town of Wakefield's DPW CAD system and digital basemap. All plans shall utilize the horizontal datum of the Massachusetts State Plane Coordinate System NAD83 and the NAVD88 vertical datum (all measurements shall be in feet).
The as-built plans shall follow the same format as described for definitive plans and meet all the requirements listed in General Information, § 320-10C(1) and (2)(a) in the current Subdivision Rules and Regulations, § 320-10, and shall include, but not be limited to:
(1)
Property lines and recorded easement information (i.e., bearings and distances).
(2)
The location of all planimetric features or all features visible above ground (i.e., building locations, granite street monuments, edge of pavement, curbing, gutters, painted and curbed islands, pavement markings, directional signage, retaining walls, sidewalks, ramps, fences, railroad tracks, street trees, number of parking spaces including individual rows and overall count, etc.).
(3)
Accessways such as curb cuts, driveways, etc.
(4)
Typical dimensions (i.e., road lanes, parking spaces, radii, etc.).
(5)
The location of all utilities and related structures contained within the construction limits as evidenced by on-site observation or as determined by records provided by utility companies and/or other sources (with reference as to the source of information).
(6)
Location of utility poles, junction boxes, hand holes, valves, cleanouts, curb boxes, pull boxes, streetlights, overheads wires and cables, etc.
(7)
The location and depth of all utilities contained within the construction limits, including but not limited to, storm, sanitary, water, electric, gas, cable, telephone and fire alarm. The contractor shall show all rim and invert elevations, including size, material and class of all pipes (also including invert elevations at buildings).
(8)
The depth of waterlines or force mains shall be shown at stations along the pipe run, and also the location of accessories including, but not limited to, post indicator valves (PIV), reduced pressure zone valves (RPZ), hydrants, bends and valves.
(9)
Contours at one-foot intervals of the entire site, in addition to spot elevations depicted on a fifty-foot grid (maximum). Spot elevations shall be obtained along all site elements, including but not limited to, ramps, retaining walls, aprons, etc. In such cases as retaining walls and curbs, the top and bottom elevations shall both be shown.
(10)
Finished ground floor and cellar elevations for existing and proposed buildings and pads located on the project site.
(11)
Benchmark information used to establish datum to be clearly shown.
(12)
If overall scale of the as-built drawing does not accommodate more detailed areas, then an enlargement of the area should be created to depict in a legible format.
The developer/contractor shall submit to the Town of Wakefield one mylar, three sets of prints and two compact disks in a format compatible with the Town of Wakefield's DPW CAD system and digital base mapping as verified by the DPW Engineering Division. The As-Built plans shall be reviewed and certified by a licensed surveyor and stamped to certify accuracy.
F.
Street acceptance plans. Prior to release of sureties or covenant, the developer/contractor shall provide, within 10 days of substantial completion, a street acceptance plan to the Town of Wakefield Planning Board. The street acceptance plan shall be drafted in a correct, readable and professional manner in a format compatible with the Town of Wakefield's DPW CAD system and digital basemap. All plans shall utilize the horizontal datum of the Massachusetts State Plane Coordinate System NAD83 and the NAVD88 vertical datum (all measurements shall be in feet).
The street acceptance plans shall follow the same format as described for the property rights and dimensional standards plan, § 320-10C(3) of the current Subdivision Rules and Regulations, and shall include, but not limited to:
(1)
All requirements listed in General Information, § 320-10C(1) and (2)(a).
(2)
The length of each straight property and right-of-way line segment to the nearest one-hundredth of a foot and the bearing thereof to the nearest five seconds.
(3)
The length, central angle, radius, length of tangent for each curved property and right-of-way line segment to the same degree of precision as the straight lines and clearly identifying each non-tangent curve.
(6)
All property parcels in private ownership with lot areas clearly listed with boundary lines, areas, and dimensions of all lots with all lots designated numerically and in sequence. Lots not conforming to the Zoning Bylaws shall bear the following notation: "Lot # _____ shall not be used as a separate building lot;
(8)
The installed bounds, markers and/or monuments for the right-of-way located and shown with metes and bounds.
(9)
A legal text description of the metes and bounds of the right-of-way.
(10)
If applicable, the Town boundary line.
The developer/contractor shall submit to the Town of Wakefield one mylar, three sets of prints and two compact disks in a format compatible with the Town of Wakefield's DPW CAD system and digital base mapping as verified by the DPW Engineering Division. The street acceptance plans shall be reviewed and certified by a licensed surveyor and stamped to certify accuracy.