A. 
Applicants proposing regulated activities in the Township which are not exempt under § 158-6 shall submit a stormwater management site plan (SWM site plan) to the Township for review and approval in accordance with Article III and Article IV. SWM site plans approved by the Township shall be on site throughout the duration of the regulated activity.
B. 
The stormwater management and runoff control criteria and standards in this chapter shall apply to the total proposed regulated activity, even if it is to take place in stages. the measurement of impervious surfaces shall include all of the impervious surfaces in the total proposed regulated activity even if the development is to take place in stages.
C. 
No regulated activity within the Township shall commence until:
(1) 
The Township issues approval of an SWM site plan, which demonstrates compliance with the requirements of this chapter; and
(2) 
The applicant has received a letter of adequacy or approval for the erosion and sediment control plan review by the Township and the Conservation District (if required), and has received all other local, state and federal permit approvals required for the project involving the regulated activity.
D. 
Neither submission of an SWM site plan under the provisions herein nor compliance with the provisions of this chapter shall relieve any person from responsibility for damage to any person or property otherwise imposed by law.
E. 
The applicant shall design the site to minimize disturbances to land, site hydrology, and natural resources, and to maintain the natural hydrologic regime, drainage patterns and flow conditions. The applicant shall apply the procedures set forth in § 158-16 for the overall site design and for selection, location and design of features and BMPs to be used to comply with the requirements of this chapter.
F. 
To the maximum extent practicable, post-construction stormwater shall be discharged within the drainage area of the same stream or water body receiving the runoff prior to construction of the proposed regulated activity.
G. 
For regulated activities with one acre or more of proposed earth disturbance, existing drainage peak rate discharges up to and including the 100-year storm onto or through adjacent property(ies) or downgradient property(ies), including diffuse drainage discharge, shall not be altered in any manner without written permission from and, where applicable as determined by the municipality, an easement and agreement with, the affected landowner(s) for conveyance of discharges onto or through their property(ies). Such discharge shall be subject to any applicable discharge criteria specified in this chapter.
H. 
Areas located outside of the site (i.e., areas outside of the regulated activity) that drain through a proposed site are not subject to water quality and volume control, infiltration, stream channel protection, or peak flow rate control requirements (as presented in §§ 158-17, 158-18, 158-19, and 158-20). Drainage facilities located on the site shall be designed to safely convey flows from outside of the site through the site.
I. 
If site conditions preclude capture of runoff from limited portions of the disturbed area for achieving water quality volume control standards, stream channel protection standards, and the two-year storm event peak runoff rate reduction standards for new development required by this chapter, the applicant shall propose alternate methods to mitigate the bypass of the BMPs, subject to the approval of the Municipal Engineer. In no case shall resulting peak rate be greater than the predevelopment peak rate for the equivalent design storm.
J. 
For all regulated activities, erosion and sediment control BMPs shall be designed, implemented, operated, and maintained during the regulated activities (i.e., during construction) as required to meet the purposes and requirements of this chapter, to meet the erosion and sediment control requirements of the Township, if applicable, and to meet all requirements under Title 25 of the Pennsylvania Code and the Clean Streams Law.[1]
[1]
Editor's Note: See 35 P.S. § 691.1 et seq.
K. 
For all regulated activities, permanent BMPs and conveyances shall be designed, implemented, operated, and maintained to meet the purposes and requirements of this chapter and to meet all requirements under Title 25 of the Pennsylvania Code, the Clean Streams Law, and the Storm Water Management Act.[2]
[2]
Editor's Note: See 35 P.S. § 691.1 et seq. and 32 P.S. § 680.1 et seq.
L. 
The design of all BMPs and conveyances shall incorporate sound engineering principles and practices in a manner that does not aggravate existing stormwater problems as identified by the Township. The Township reserves the right to disapprove any design that would result in construction in an area affected by existing stormwater problem(s) or continuation of an existing stormwater problem(s).
M. 
Existing wetlands, either on the site or on an adjacent property, shall not be used to meet the minimum design requirements for stormwater management or stormwater runoff quality treatment. Stormwater discharges to existing wetlands shall not degrade the quality or hydrologic integrity of the wetland.
N. 
Hot spots runoff controls. Specific structural or pollution prevention practices may be required, as determined to be necessary by the Municipal Engineer, to pretreat runoff from hot spots prior to infiltration. Following is a list of examples of hot spots:
(1) 
Vehicle salvage yards and recycling facilities;
(2) 
Vehicle fueling stations;
(3) 
Vehicle service and maintenance facilities;
(4) 
Vehicle and equipment cleaning facilities;
(5) 
Fleet storage areas (bus, truck, etc.);
(6) 
Industrial sites based on standard industrial classification codes;
(7) 
Marinas (service and maintenance areas);
(8) 
Outdoor liquid container storage;
(9) 
Outdoor loading/unloading facilities;
(10) 
Public works storage areas;
(11) 
Facilities that generate or store hazardous materials;
(12) 
Commercial container nursery;
(13) 
Contaminated sites/brownfields;
(14) 
Other land uses and activities, as designated by the Township.
O. 
Contaminated and brownfield sites. Where BMPs may contribute to the migration of contaminants in groundwater, the water quality and runoff volume, stream channel protection, and peak rate control standards shall be met; however, at the Municipal Engineer's discretion, the minimum infiltration requirement may be reduced or eliminated commensurate with the contaminated area, and the required water quality and runoff control measures may be increased to mitigate the reduced infiltration requirement for the contaminated area.
P. 
Additional water quality requirements. The Township may require additional stormwater control measures for stormwater discharges to special management areas, including, but not limited to:
(1) 
Water bodies listed as "impaired" by PADEP.
(2) 
Areas of known existing flooding problems.
(3) 
Critical areas with sensitive resources (e.g., state-designated special protection waters, cold water fisheries, carbonate geology or other groundwater recharge areas that may be highly vulnerable to contamination, drainage areas to water supply reservoirs, etc.).
Q. 
Applicants shall utilize the Pennsylvania Stormwater Best Management Practices Manual (PA BMP Manual), as amended, or other sources acceptable to the Municipal Engineer, for testing and design standards for BMPs, and where there is a conflict with the provisions of this chapter, the most restrictive applies.
R. 
For areas underlain by karst or carbonate geology that may be susceptible to the formation of sinkholes and other karst features, the location, type, and design of infiltration BMPs shall be based on a site evaluation conducted by a qualified licensed professional and based on the PA BMP manual or other design guidance acceptable to the Municipal Engineer.
The following permit or other regulatory requirements may apply to certain regulated activities and shall be met prior to (or as a condition of) final approval by the Township of the SWM site plan and prior to commencement of any regulated activities, as applicable:
A. 
All regulated activities subject to permit or regulatory requirements by PADEP under regulations at Title 25 Pennsylvania Code Chapter 102, or erosion and sediment control requirements of the Township.
B. 
Work within natural drainage ways subject to permit by PADEP under Title 25 Pennsylvania Code Chapter 105.
C. 
Any BMP or conveyance that would be located in or adjacent to surface waters of the commonwealth, including wetlands, subject to permit by PADEP under Title 25 Pennsylvania Code Chapter 105.
D. 
Any BMP or conveyance that would be located on or discharged to a state highway right-of-way, or require access to or from a state highway and be subject to approval by PennDOT.
E. 
Culverts, bridges, storm sewers, or any other facilities which must pass or convey flows from the tributary area and any facility which may constitute a dam subject to permit by PADEP under Title 25 Pennsylvania Code Chapter 105.
A. 
No regulated activity within the Township shall commence until:
(1) 
The Township receives documentation that the applicant has received:
(a) 
A letter of adequacy from the Conservation District or other approval from PADEP in compliance with Title 25 Chapter 102 of the Pennsylvania Code of an erosion and sediment control plan for construction activities, if applicable;
(b) 
A PADEP NPDES construction activities permit as required under Title 25 Pennsylvania Code Chapter 92a, if applicable;
[Amended at time of adoption of Code (see Ch. 1, General Provisions, Art. I)]
(c) 
Evidence of any other permit(s) or approvals required for the regulated activities; and
(2) 
An erosion and sediment control plan has been approved by the Township, if required.
B. 
A copy of the erosion and sediment control plan and any required permit(s), as required by PADEP regulations, shall be available on the site at all times.
C. 
Additional erosion and sediment control measures shall be applied where infiltration BMPs are proposed, at a minimum including those required in § 158-18M.
The applicant shall design the site to minimize the disturbances to land, site hydrology, and natural resources, and to maintain the natural hydrologic regime, drainage patterns and flow conditions. The applicant shall demonstrate in its SWM site plan (as required in § 158-26C) that the design sequence, objectives and techniques described below were applied to the maximum extent practicable in the site design of the regulated activity while complying with all other requirements of this chapter. The site design shall:
A. 
First, identify and delineate all existing natural resources and natural and man-made hydrologic features listed in § 158-26B(8) that are located within the site, or receive discharge from, or may be impacted by the proposed regulated activity.
B. 
Second, provide a prioritized listing of these resources and features to identify:
(1) 
Those to be incorporated into the site design in a manner that provides protection from any disturbance or impact from the proposed regulated activity;
(2) 
Those to be protected from further disturbance or impact but for which the proposed regulated activity will provide improvement to existing conditions;
(3) 
Those that can be incorporated into and utilized as components of the overall site design in a manner that protects or improves their existing conditions while utilizing their hydrologic function within the limits of their available capacity (e.g., for infiltration, evapotranspiration, or reducing pollutant loads, runoff volume or peak discharge rates, etc.) to reduce the need for or size of constructed BMPs; and
(4) 
Those that may be considered for alteration, disturbance or removal.
C. 
Third, develop the site design to achieve the following:
(1) 
Recognize and incorporate the priorities identified in § 158-16B as the basis for the proposed site layout, grading, construction, and permanent ground cover design;
(2) 
Minimize earth disturbance (both surface and subsurface);
(3) 
Maximize protection of or improvement to natural resources and special management areas;
(4) 
Minimize the disturbance of natural site hydrology, in particular natural drainage features and patterns, discharge points and flow characteristics, natural infiltration patterns and characteristics, and natural channel and floodplain conveyance capacity;
(5) 
Incorporate natural hydrologic features and functions identified in § 158-16B into the site design to protect and utilize those features and their hydrologic functions to reduce the need for or size of constructed BMPs;
(6) 
Maximize infiltration and the use of natural site infiltration features, patterns and conditions, and evapotranspiration features;
(7) 
Apply selective grading design methods to provide final grading patterns or preserve existing topography in order to evenly distribute runoff and minimize concentrated flows;
(8) 
Minimize the cumulative area to be covered by impervious surfaces and:
(a) 
Minimize the size of individual impervious surfaces;
(b) 
Separate large impervious surfaces into smaller components;
(c) 
Disconnect runoff from one impervious surface to another; and
(d) 
Utilize porous materials in place of impervious wherever practicable.
(9) 
Minimize the volume and peak discharge rates of stormwater generated;
(10) 
Avoid or minimize stormwater runoff pollutant loads and receiving stream channel erosion;
(11) 
Locate infiltration and other BMPs:
(a) 
At or as near to the source of generation as possible; and
(b) 
At depths that are as shallow as possible.
(12) 
Prioritize the selection and design of BMPs as follows:
(a) 
Nonstructural and vegetation BMPs; then
(b) 
Structural (surface and subsurface) BMPs.
(13) 
For flow volumes requiring conveyance from the source of generation to a BMP for management, give preference to open channel conveyance techniques that provide infiltration and water quality benefits, and landscape-based management in common open space areas, where practicable; and
(14) 
Consider additional guidance for incorporating natural hydrology into then site and BMP designs, methods and techniques that support the objectives of §§ 158-16B and 158-16C. Appendix B[1] presents additional discussion of natural hydrology site design and sources of information for "conservation design," "low impact design," and "sustainable design."
[1]
Editor's Note: The appendixes of this chapter are on file in the Township offices.
D. 
The procedures set forth above shall be utilized to the maximum extent practicable for the overall site design and selection, location and design of features and BMPs to be used to comply with the requirements of §§ 158-17, 158-18, 158-19, and 158-20.
To control post-construction stormwater impacts from regulated activities and meet state water quality requirements, BMPs shall be provided in the site design that replicate predevelopment stormwater infiltration and runoff conditions, such that post-construction stormwater discharges do not degrade the physical, chemical, or biological characteristics of the receiving waters. The applicant shall comply with the following water quality and runoff volume requirements for all regulated activities, including all new development and redevelopment activities:
A. 
The post-construction total runoff volume shall not exceed the predevelopment total runoff volume for all storms equal to or less than the two-year, twenty-four-hour duration precipitation (design storm). The water quality and runoff volume to be managed shall consist of any runoff volume generated by the proposed regulated activity over and above the predevelopment total runoff volume and shall be captured and permanently retained or infiltrated on the site. Permanent retention options may include, but are not limited to, reuse, evaporation, transpiration, and infiltration.
B. 
For modeling purposes, the predevelopment ground cover conditions shall be determined using the corresponding ground cover assumptions presented in § 158-21D of this chapter.
C. 
The design of the facility outlet shall provide for protection from clogging and unwanted sedimentation.
D. 
BMPs that moderate the temperature of stormwater shall be used to protect the temperature of receiving waters.
E. 
Water quality improvement shall be achieved in conjunction with achieving the infiltration requirements of § 158-18. The infiltration volume required under § 158-18 may be included as a component of the water quality volume. If the calculated water quality and runoff volume is greater than the volume infiltrated, then the difference between the two volumes shall be managed for water quality and runoff volume control through other techniques or practices but shall not be discharged from the site.
F. 
Runoff from the disturbed area shall be treated for water quality prior to entering existing waterways or water bodies. If a stormwater management practice does not provide water quality treatment, then water quality BMPs shall be utilized to provide pre-treatment prior to the runoff entering the stormwater management practice.
G. 
The Township may require additional water quality and runoff control measures for stormwater discharging to special management areas, such as those listed in § 158-13P.
H. 
When the regulated activity contains or is divided by multiple drainage areas, the water quality and runoff volume shall be separately addressed for each drainage area.
I. 
Weighted averaging of runoff coefficients shall not be used for manual computations or input data for water quality and runoff volume calculations.
J. 
Areas located outside of the site (i.e., areas outside of the regulated activity) may be excluded from the calculation of the water quality and runoff volume requirements.
K. 
Water quality and volume control practices shall be selected and designed to meet the criteria of § 158-16C that apply to water quality and volume control.
Providing for infiltration consistent with the natural hydrologic regime is required to compensate for the reduction in the recharge that occurs when the ground surface is disturbed or impervious surface is created or expanded. The applicant shall achieve the following infiltration requirements:
A. 
Wherever possible, infiltration should be designed to accommodate the entire water quality and runoff volume required in § 158-17.
B. 
For regulated activities involving new development, the volume of a minimum of one inch of runoff from all proposed impervious surfaces shall be infiltrated.
C. 
For regulated activities involving redevelopment, whichever is less of the following volume options shall be infiltrated:
(1) 
The volume of a minimum of one inch of runoff from all proposed impervious surfaces; or
(2) 
The total water quality and runoff volume required in § 158-17 of this chapter.
D. 
If the requirements of § 158-18B or C cannot be physically accomplished, then the applicant shall be responsible for demonstrating with data or calculations to the satisfaction of the Municipal Engineer why this infiltration volume cannot be physically accomplished on the site (e.g., shallow depth to bedrock or limiting zone, open voids, steep slopes, etc.) and what alternative volume can be infiltrated; however, in all cases at least the first 1/2 inch of runoff volume should be infiltrated.
E. 
Only if a minimum of at least 0.5 inch infiltration requirement cannot be physically accomplished on the site shall a waiver from § 158-18 be considered by the Township.
F. 
If site conditions preclude capture of runoff from portions of the impervious surfaces, the infiltration volume for the remaining area shall be increased an equivalent amount to offset the loss.
G. 
When a project contains or is divided by multiple watersheds, the infiltration volume shall be separately addressed for each watershed.
H. 
Existing impervious surfaces located in areas outside of the site (i.e., outside of the regulated activity) may be excluded from the calculation of the required infiltration volume.
I. 
A detailed soils evaluation of the site shall be conducted by a qualified professional and at a minimum shall address soil permeability, depth to bedrock, and subgrade stability. The general process for designing the infiltration BMP shall be conducted by a qualified licensed professional and shall be consistent with the PA BMP Manual (as amended) (or other guidance acceptable to the Municipal Engineer) and in general shall:
(1) 
Analyze hydrologic soil groups as well as natural and man-made features within the site to determine general areas of suitability for infiltration practices. In areas where development on fill material is under consideration, conduct geotechnical investigations of subgrade stability; infiltration may not be ruled out without conducting these tests.
(2) 
Provide field tests, such as double ring infiltrometer or other hydraulic conductivity tests (at the elevation of the proposed infiltration surface) to determine the appropriate hydraulic conductivity rate. Standard septic/sewage percolation tests are not acceptable for design purposes.
(3) 
Design the infiltration facility for the required retention (infiltration) volume based on field-determined infiltration capacity (and apply safety factor as per applicable design guidelines) at the elevation of the proposed infiltration surface.
(4) 
On-lot infiltration features are encouraged; however, it shall be demonstrated to the Municipal Engineer that the soils are conducive to infiltration on the identified lots.
J. 
Infiltration BMPs shall be selected based on suitability of soils and site conditions and shall be constructed on soils that have the following characteristics:
(1) 
A minimum depth of 24 inches between the bottom of the BMP and the top of the limiting zone. Additional depth may be required in areas underlain by karst or carbonate geology (see § 158-18N).
(2) 
An infiltration rate sufficient to accept the additional stormwater volume and drain completely as determined by field tests conducted by the applicant.
(3) 
The infiltration facility shall completely drain the retention (infiltration) volume within three days (72 hours) from the end of the design storm.
K. 
All infiltration practices shall:
(1) 
Be selected and designed to meet the criteria of § 158-16C that are applicable to infiltration;
(2) 
Be set back at least 25 feet from all buildings and features with subgrade elements (e.g., basements, foundation walls, etc.) and be set back at least 10 feet from property lines or right-of-way, unless otherwise approved by the Municipal Engineer;
(3) 
For any infiltration practice that collects runoff from shared or multiple features and that is located within 50 feet of a building or feature with subgrade elements (e.g., basements, foundation walls, etc.), the bottom elevation shall be set below the elevation of the subgrade element.
(4) 
All infiltration practices shall be installed with a minimum of 50 feet from water supply well and septic disposal areas.
L. 
Infiltration facilities shall, to the maximum extent practicable, be located to avoid introducing contaminants to groundwater.
(1) 
When a hot spot is located in the area draining to a proposed infiltration facility, an evaluation of the potential of groundwater contamination from the proposed infiltration facility shall be performed, including a hydrogeologic investigation (if necessary) by a qualified licensed professional to determine what, if any, pretreatment or additional design considerations are needed to protect groundwater quality.
(2) 
When located within a wellhead protection area of a public water supply well, infiltration practices shall be in conformance with the applicable approved source water protection assessment or source water protection plan.
(3) 
The applicant shall provide appropriate safeguards against groundwater contamination for land uses that may cause groundwater contamination should there be a mishap or spill.
M. 
During site construction, all infiltration practice components shall be protected from compaction due to heavy equipment operation or storage of fill or construction material. Infiltration areas shall also be protected from sedimentation. Areas that are accidentally compacted or graded shall be remediated to restore soil composition and porosity. Adequate documentation to this effect shall be submitted to the Municipal Engineer for review. All areas designated for infiltration shall not receive runoff until the contributory drainage area has achieved final stabilization.
N. 
Where sediment transport in the stormwater runoff is anticipated to reach the infiltration system, appropriate permanent measures to prevent or collect sediment shall be installed prior to discharge to the infiltration system.
O. 
Where roof drains are designed to discharge to infiltration practices, they shall have appropriate measures to prevent clogging by unwanted debris (for example, silt, leaves and vegetation). Such measures shall include but are not limited to leaf traps, gutter guards and cleanouts.
P. 
All infiltration practices shall have appropriate positive overflow controls.
Q. 
No sand, salt or other particulate matter may be applied to a porous surface material for winter ice conditions.
R. 
The following procedures and materials shall be required during the construction of all subsurface facilities:
(1) 
Excavation for the infiltration facility shall be performed with equipment that will not compact the bottom of the seepage bed/trench or like facility.
(2) 
The bottom of the bed and/or trench shall be scarified prior to the placement of aggregate.
(3) 
Only clean aggregate with documented porosity, free of fines, shall be allowed.
(4) 
The tops, bottoms and sides of all seepage beds, trenches, or like facilities shall be covered with drainage fabric. Fabric shall be nonwoven fabric acceptable to the Municipal Engineer.
(5) 
Stormwater shall be distributed throughout the entire seepage bed/trench or like facility and provisions for the collection of debris shall be provided in all facilities.
For regulated activities involving new development with one or more acres of earth disturbance, the applicant shall comply with the following stream channel protection requirements to minimize stream channel erosion and associated water quality impacts to the receiving waters:
A. 
The peak flow rate of the post-construction two-year, twenty-four-hour design storm shall be reduced to the predevelopment peak flow rate of the one-year, twenty-four-hour duration precipitation, using the NRCS Type II distribution.
B. 
To the maximum extent practicable, and unless otherwise approved by the Municipal Engineer, the post-construction one-year, twenty-four-hour storm flow shall be detained for a minimum of 24 hours and a maximum not to exceed 72 hours from a point in time when the maximum volume of water from the one-year, twenty-four-hour storm is stored in a proposed BMP (i.e., when the maximum water surface elevation is achieved in the facility). Release of water can begin at the start of the storm (i.e., the invert of the orifice is at the invert of the proposed BMP).
C. 
For modeling purposes, the predevelopment ground cover conditions shall be determined using the corresponding ground cover assumptions presented in § 158-21D of this chapter.
D. 
The minimum orifice size in the outlet structure to the BMP shall be three inches in diameter unless otherwise approved by the Municipal Engineer, and a trash rack shall be installed to prevent clogging. For sites with small drainage areas contributing to the BMP that do not provide enough runoff volume to allow a twenty-four-hour attenuation with the three-inch orifice, the calculations shall be submitted showing this condition.
E. 
When the calculated orifice size is below three inches, gravel filters (or other methods) are recommended to discharge low-flow rates subject to the Municipal Engineer's satisfaction. When filters are utilized, maintenance provisions shall be provided to ensure filters meet the design function.
F. 
All proposed stormwater facilities shall make use of measures to extend the flow path and increase the travel time of flows in the facility.
G. 
When a regulated activity contains or is divided by multiple drainage areas, the peak flow rate control shall be separately addressed for each drainage area.
The applicant shall comply with the following peak flow rate control requirements for all regulated activities including those that involve new development and redevelopment as applicable:
A. 
Parcels that are located in the Conestoga River Watershed shall be designed to have a post-construction peak flow less than or equal to 30% of predevelopment peak flow conditions as dictated by Conestoga River Watershed Act 167 plan in § 158-14B and C;
[Amended at time of adoption of Code (see Ch. 1, General Provisions, Art. I)]
B. 
Post-construction peak flow rates from any regulated activity not located in the Conestoga River Watershed shall not exceed the predevelopment peak flow rates as shown for each of the design storms specified in Table 308.1.
Table 308.1
Peak Rate Control Standards
(Peak Flow Rate of Post-Construction Design Storm Shall be Reduced to the Peak Flow Rate of Corresponding Predevelopment Design Storm Shown in Table)
Predevelopment Design Storm
Post-Construction Design Storm Frequency
(24-hour duration)
New Development Regulated Activities
Redevelopment Regulated Activities
2-Year
1-Year
2-Year
5-Year
5-Year
5-Year
10-Year
10-Year
10-Year
25-Year
25-Year
25-Year
50-Year
50-Year
50-Year
100-year
100-year
100-year
C. 
For modeling purposes, the predevelopment ground cover conditions shall be determined using the corresponding ground cover assumptions presented in § 158-21D of this chapter.
D. 
For regulated activities involving only redevelopment, no peak flow rate controls are required when and only if the total proposed impervious surface area is at least 20% less than the total existing impervious surface area to be disturbed by the regulated activity. In all cases where this requirement is not met, the redevelopment regulated activity shall achieve the peak flow rate controls presented in Table 308.1, using the redevelopment ground cover assumptions presented in § 158-21D.
E. 
Only the area of the proposed regulated activity shall be subject to the peak flow rate control standards of this chapter. Undisturbed areas for which the discharge point has not changed are not subject to the peak flow rate control standards.
F. 
Areas located outside of the site (i.e., areas outside of the regulated activity) that drain through a proposed site are not subject to peak flow rate control requirements. Drainage facilities located on the site shall be designed to safely convey flows from outside of the site through the site.
G. 
When a regulated activity contains or is divided by multiple drainage areas, the peak flow rate controls shall be separately addressed for each drainage area.
H. 
The effect of structural and nonstructural stormwater management practices implemented as part of the overall site design may be taken into consideration when calculating total storage volume and peak flow rates.
I. 
Regulated activities located within the Conestoga River Watershed shall achieve the applicable peak flow release rate control requirements presented in the approved PA Act 167 Plan for that watershed as presented in the Conestoga River Watershed Release Rate Map in Appendix F of this chapter.[1]
[1]
Editor's Note: The appendixes of this chapter are on file in the Township offices.
A. 
Stormwater runoff from all regulated activity sites with a drainage area of greater than five acres shall be calculated using a generally accepted calculation technique(s) that is based on the NRCS Soil Cover Complex Method. Table 309.1 summarizes acceptable computation methods. The method selected for use shall be based on the individual limitations and suitability of each method for a particular Site. The use of the Rational Method to estimate peak discharges for drainage areas greater than five acres shall be permitted only upon approval by the Municipal Engineer.
Table 309.1
Acceptable Computation Methodologies for SWM Site Plan
Method
Developed By
Applicability
TR-20 (or commercial computer package based on TR-20)
USDA NRCS
Applicable where use of full hydrology computer model is desirable or necessary
TR-55 (or commercial computer package based on TR-55)
USDA NRCS
Applicable for land development plans where limitations described in TR-55 are met
HEC-1/HEC-HMS
U.S. Army Corps of Engineers
Applicable where use of a full hydrologic computer model is desirable or necessary
Rational Method (or commercial computer package based on Rational Method)
Emil Kuichling (1889)
For sites up to 5 acres, or as approved by the Township
Other methods
Varies
Other computation methodologies approved by the Township
B. 
All calculations using the Soil Cover Complex Method shall use the appropriate design rainfall depths for the various return period storms consistent with this chapter. Rainfall depths used shall be obtained from NOAA Atlas 14 values consistent with a partial duration series. When stormwater calculations are performed for routing procedures or infiltration, water quality and runoff volume functions, the duration of rainfall shall be 24 hours.
C. 
All calculations using the Rational Method shall use rainfall intensities consistent with appropriate times-of-concentration (duration) and storm events with rainfall intensities obtained from NOAA Atlas 14 partial duration series estimates, or the latest version of the PennDOT Drainage Manual (PDM Publication 584). Times-of-concentration shall be calculated based on the methodology recommended in the respective model used. Times of concentration for channel and pipe flow shall be computed using Manning's equation.
D. 
The applicant shall utilize the following ground cover assumptions for all predevelopment water quality and runoff volume, infiltration volume and peak flow rate calculations:
(1) 
For regulated activities involving new development, the following ground cover assumptions shall be used:
(a) 
For areas that are woods (as defined in Article II of this chapter), predevelopment calculations shall assume ground cover of "woods in good condition."
(b) 
For all other areas (including all impervious surfaces), predevelopment calculations shall assume ground cover of "meadow."
(2) 
For regulated activities involving redevelopment, the following ground cover assumptions shall be used:
(a) 
For areas that are woods (as defined in Article II of this chapter), predevelopment calculations shall assume ground cover of "woods in good condition."
(b) 
For areas that are not woods or not impervious surfaces, predevelopment calculations shall assume ground cover of "meadow."
(c) 
For areas that are impervious surfaces, predevelopment calculations shall assume at least 20% of the existing impervious surface area to be disturbed as "meadow" ground cover.
(3) 
The applicant shall determine which stormwater standards apply to the proposed regulated activity as follows:
(a) 
Stormwater standards for new development shall apply to all proposed regulated activities that involve only new development activities as defined in this chapter.
(b) 
Stormwater standards for redevelopment shall apply to all proposed regulated activities that involve only redevelopment activities as defined in this chapter.
(c) 
At the discretion of the Municipal Engineer, regulated activities that involve a combination of both new development and redevelopment activities, as defined in this chapter, may either:
[1] 
Apply the stormwater standards (redevelopment or new development) that are associated with the activity that involves the greatest amount of land area; or
[2] 
Apply the redevelopment and new development stormwater standards to the corresponding redevelopment and new development portions of the proposed regulated activity.
E. 
Runoff curve numbers (CN) for both predevelopment and proposed (post-construction) conditions to be used in the Soil Cover Complex Method shall be obtained from Table C-1 in Appendix C of this chapter.[1]
[1]
Editor's Note: The appendixes of this chapter are on file in the Township offices.
F. 
Runoff coefficients (C) for both predevelopment and proposed (post-construction) conditions for use in the Rational Method shall be obtained from Table C-2 in Appendix C of this chapter.[2]
[2]
Editor's Note: The appendixes of this chapter are on file in the Township offices.
G. 
Weighted averaging of runoff coefficients shall not be used for manual computations or input data for water quality and runoff volume calculations.
H. 
Hydraulic computations to determine the capacity of pipes, culverts, and storm sewers shall be consistent with methods and computations contained in the Federal Highway Administration Hydraulic Design Series Number 5 (Publication No. FHWA-NHI-01-020 HDS No. 5, as amended). Hydraulic computations to determine the capacity of open channels shall be consistent with methods and computations contained in the Federal Highway Administration Hydraulic Engineering Circular Number 15 (Publication No. FHWA-NHI-05-114 HEC 15, as amended). Values for Manning's roughness coefficient (n) shall be consistent with Table C-3 in Appendix C of the chapter.[3]
[3]
Editor's Note: The appendixes of this chapter are on file in the Township offices.
I. 
Runoff calculations shall include the following assumptions:
(1) 
Average antecedent moisture conditions (for the Soil Cover Complex Method only for example, TR-55, TR-20).
(2) 
A Type II distribution storm (for the Soil Cover Complex Method only for example, TR-55, TR-20).
A. 
Any BMP intended to hold standing water for four days or longer shall be designed to incorporate biologic controls consistent with the West Nile Guidance found in Appendix D,[1] PADEP document 363-0300-001 "Design Criteria - Wetlands Replacement/Monitoring," as amended (or contact the Pennsylvania State Cooperative Wetland Center or the Penn State Cooperative Extension Office for design information).
[1]
Editor's Note: The appendixes of this chapter are on file in the Township offices.
B. 
Any stormwater basin required or regulated by this chapter designed to store runoff and requiring a berm or earthen embankment shall be designed to provide an emergency spillway to safely convey flow up to and including the 100-year proposed conditions. The height of embankment shall provide a minimum two feet of freeboard above the maximum pool elevation computed when the facility functions for the 100-year proposed conditions inflow. Should any BMP require a dam safety permit under 25 Pa. Code Chapter 105 regulations, the facility shall be designed in accordance with and meet the regulations of 25 Pa. Code Chapter 105 concerning dam safety. Title 25 Pa. Code Chapter 105 may require the safe conveyance of storms larger than the 100-year event.
C. 
Any drainage conveyance facility and/or channel not governed by 25 Pa. Code Chapter 105 regulations shall be designed to convey, without damage to the drainage facility or roadway, runoff from the twenty-five-year-storm event. Larger storm events (fifty-year and 100-year storms) shall also be safely conveyed in the direction of natural flow without creating additional damage to any drainage facilities, nearby structures, or roadways.
D. 
Conveyance facilities to or existing from stormwater management facilities (i.e., detention basins) shall be designed to convey the design flow to or from the facility.
E. 
Roadway crossings or structures located within designated floodplain areas shall be able to convey runoff from a 100-year design storm consistent with Federal Emergency Management Agency National Flood Insurance Program - Floodplain Management Requirements.
F. 
Any facility located within a PennDOT right-of-way shall comply with PennDOT minimum design standards and permit submission and approval requirements.
G. 
Adequate erosion protection and energy dissipation shall be provided along all open channels and at all points of discharge. Design methods shall be consistent with the Federal Highway Administration Hydraulic Engineering Circular Number 11 (Publication No. FHWA-IP-89-016, as amended) and the PADEP Erosion and Sediment Pollution Control Program Manual (Publication No. 363-2134-008, as amended), or other design guidance acceptable to the Municipal Engineer.
A. 
Stormwater conveyance - swales.
(1) 
Open ditches shall be avoided but properly designed, graded, and turfed drainage swales shall be permitted in lieu of storm sewers in commercial and industrial areas and, where approved by the Township Engineer, in residential areas.
(2) 
Swales shall be designed not only to carry the required discharge without excessive erosion, but also to increase the time of concentration, reduce peak discharge and velocity, and permit the water to percolate into the soil. Permanent open swales shall be designed to convey a 100-year storm event computed from the Manning's Equation.
(3) 
Open swales shall be stabilized with vegetation or other materials in accordance with Title 25 Pa. Code Chapter 102, Rules and Regulations of the Pennsylvania Department of Environmental Protection. Slopes for swale banks shall not exceed one foot vertical for every four feet horizontal.
B. 
Stormwater conveyance - closed conveyance, including inlets, manholes, etc.
(1) 
Storm sewers, as required, shall be placed under or immediately at the back of the shoulder, when parallel to the street within the right-of-way. When located in undedicated land, they shall be placed within an easement not less than 20 feet wide as approved by the Township Engineer.
(2) 
Storm sewers shall have a minimum diameter of 15 inches for reinforced concrete pipe and a minimum grade of 1/2%. High-density polyethylene pipe (HDPE) may be proposed and installed under manufacturer's specification and with specific permission by the Township Engineer. All pipe may be subject to video inspection upon completion of installation and prior to acceptance of public improvements. Changes in alignment shall be by straight sections connected by inlets or manholes.
(3) 
Storm sewer sizes shall be selected in accordance with storm intensity frequency of 25 years in all residential subdivisions or land developments unless otherwise specified by the Township Engineer. All storm piping shall be in accordance with PennDOT specifications. Piping shall be saw-cut at ends, as needed, and not hammered or broken.
(4) 
Inlets and manholes shall be spaced at intervals not exceeding 300 feet, and shall be located wherever branches are connected or sizes are changed, and wherever there is a change in alignment or grade. For drainage lines of at least 36 inches' diameter, inlets and manholes may be spaced at intervals of 400 feet.
(5) 
Inlets, manholes, covers, and frames shall conform to Pennsylvania Department of Transportation specifications. At street intersections, inlets shall be placed in the tangent and not the curved portion of the curbing.
(6) 
Curb inlets shall be located at curb tangents on the uphill side of street intersections and at intervals along the curbline to control the maximum amount of encroachment of runoff on the roadway pavement so that same does not exceed a width of four feet during the design storm event. Design and location of curb inlets shall be approved by the Township. The maximum amount of flow through an intersection may not exceed one inch.
(7) 
The capacity of all stormwater pipes shall be calculated utilizing the Manning's Equation for open channel flow as applied to closed conduit flow. The Manning's roughness coefficient shall be 0.13 for all concrete pipe. In cases where pressure flow may occur, the hydraulic grade line shall be calculated throughout the storm sewer system to verify that at least one foot of freeboard will be provided in all inlets and manholes for the design storm event.
(8) 
The capacity of all inlets shall be based on a maximum surface flow to the inlet of 3.5 cfs, calculated based on the design storm event. The maximum flow to inlets located in low points (such as sag vertical curves) shall include the overland flow directed to the inlet as well as all bypass runoff from upstream inlets. The bypass flow from upstream inlets shall be calculated using inlet efficiency curves included in PennDOT Design Manual, Part 2, latest edition. If the surface flow to an inlet exceeds 3.5 cfs, additional inlets shall be provided upstream of the inlet to intercept the excessive surface flow.
(9) 
Stormwater systems shall be designed to produce a minimum velocity of 3.0 feet per second when flowing full. The maximum permissible velocity shall be 10.0 feet per second. Pipe slopes shall not be less than 0.5%.
(10) 
Open-end pipes must be fitted with concrete endwalls and wing walls in accordance with PennDOT Standards.
(11) 
All storm sewer pipes shall be laid to a minimum depth of one foot from subgrade to crown of pipe.
(12) 
Trench backfill within any paved area, including the Township right-of-way, Township cartway or private roadways must be backfilled to the base of the road section with 2A, per PennDOT 408, backfill and compaction standards. Trenches within open space or grassed may be backfilled with select fill beyond the proper pipe bedding. Alternative pipe bedding may be approved in areas of excessive moisture or if proposed by the applicant according to the manufacturers specifications. All pipe backfill details must be approved by the Township Engineer.
(13) 
Modified inlet boxes shall be used when required in accordance with the PennDOT RC standards. Pipes shall not be allowed to enter the corner of boxes. The crown of the pipe shall be at least 12 inches below the top of the precast inlet or manhole box.
C. 
Bridges and culverts shall have ample waterway to carry expected flows, based on a minimum storm frequency of 100 years. Bridge and/or culvert construction shall be in accordance with the Pennsylvania Department of Transportation specifications and shall meet the requirements of the Pennsylvania Department of Environmental Protection. Culverts shall be provided with wing walls and constructed for the full width of the right-of-way. The cartway area over the bridge shall be 24 inches wider, on either side, than the road connecting with the bridge, or, if the character of the road is expected to change for future planning, the cartway of the bridge shall be made to anticipate this condition. On either side of the bridge cartway, the bridge railing must be set back from the edge of the final cartway a minimum of eight feet and this area may be used to place sidewalks, present or future.
D. 
Detention or retention basins for the control of stormwater peak discharges shall meet the following requirements:
(1) 
Basins shall be installed prior to any earthmoving or land disturbances which they will serve. The phasing of their construction shall be noted in the narrative and on the plan.
(2) 
Soils used for the construction of basins shall have low-erodibility factors ("K" factors).
(3) 
Detention basins designed to hold the excess volume of runoff from a two-year storm should be located on soils with a moderate to high percolation rate in order to encourage recharge and reduce potential for stagnant water conditions. Where soils with moderate to high percolation rates are found at higher elevations of a site, such detention facilities may require incorporation into building lot layout. Drainage easements and deed restrictions against the alteration of such detention areas shall be executed to the satisfaction of the Board.
(4) 
Energy dissipaters and/or level spreaders shall be installed at points where pipes or drainage ways discharge to or from basins. Generally, outlet pipes designed to carry the predevelopment, two-year storm flow will be permitted to discharge to a stream with only an energy dissipater. Storms of a ten-year or greater intensity should be spread across floodplains by level spreaders; rock material found on the site is suggested for their construction.
(5) 
The following slope restrictions shall apply to basins:
(a) 
Exterior slopes of compacted soil shall not exceed one foot vertical for three feet horizontal, and may be further reduced if the soil has unstable characteristics.
(b) 
Interior side slopes of the basin shall not exceed one foot vertical in three feet horizontal except, with approval of the Township:
[1] 
Where maximum water depth will not exceed three feet; or
[2] 
When a two-inch rainfall in one hour will not fill the basin in one hour; or
[3] 
Where concrete, stone, or brick walls are used with side slopes proposed to be steeper than one foot vertical in three feet horizontal, in which case the basin shall be fenced by a permanent wire fence 42 inches in height and a ramp of durable, nonslip materials for maintenance vehicles shall be provided for access into the basin.
[4] 
Minimum basin interior slope shall be 2% unless designed as an infiltration basin.
(6) 
Outlet structures within basins which will control peak discharge flows and distribute the flows by pipes to discharge areas shall be constructed of concrete, coated (e.g., polymer, bituminous) galvanized steel, or aluminum and shall have childproof, nonclogging trash racks overall design openings exceeding 12 inches in diameter, except those openings designed to carry perennial stream flows. Where spillways will be used to control peak discharges in excess of the ten-year storm, the control weirs shall be constructed of concrete of sufficient mass and structural stability to withstand the pressures of impounded waters and outlet velocities. Concrete outlet aprons shall be designed as level spreaders and shall extend at a minimum to the toe of the basin slope. The incorporation of large stones found on the site into the concrete apron to provide a more natural appearance is suggested. Construction shall comply with PennDOT Form 408 specifications.
(7) 
Inlet and outlet structures will be located at maximum distances from one another. The Township Engineer may require a rock filter berm or rock-filled gabions between inlet and outlet areas when the distance is deemed insufficient for sediment trapping. All inlets shall either be located above the bottom of the basin or shall discharge to areas of the basin which slope downward to lower elevations of the basin.
(8) 
Detention or retention basin berms shall have a minimum ten-foot top width.
(9) 
Detention or retention basin berms shall be provided with an impervious clay core and shall be keyed into the existing ground surface at least 1 1/2 feet.
(10) 
Detention basin outlet pipes shall be provided with two concrete anti-seep collars per pipe. Detention basin outlet pipes shall be reinforced concrete pipe.
(11) 
Detention basin emergency spillways shall be constructed of a stabilized, non-erodible material with maximum three to one side slopes.
(12) 
The discharge (or outfall) as well as the emergency spillway, dam breast areas, or water storage area of a detention basin shall be located at least a minimum distance from the original property line of the parcel being developed or any new property lines that are created; according to the following table:
(a) 
One acre drainage area: 25 feet.
(b) 
Two-acre to four-acre drainage area: 50 feet.
(c) 
Four-acre to 10-acre drainage area: 75 feet.
(d) 
Over 10 acres: 100 feet.
(13) 
Storm retention basins, if used, shall be described by metes and bounds, which area shall be known as an "easement for maintenance and access" and shall be deed-restricted against removal or modification without the express consent of West Nantmeal Township.
(14) 
Temporary and permanent grasses or stabilization measures shall be established on the sides of all earthen basins within 15 days of initial construction. Their maintenance and repair shall be the direct responsibility of the developer during the site preparation process, prior to a formal maintenance guarantee being established as per § 158-37 of this chapter.
E. 
The grading of driveway entrances shall be so designed that normal stormwater flow along the street gutter or roadside swale shall not be interrupted thereby, and that stormwater runoff from driveways shall not be discharged directly into the cartway.
F. 
When utilizing the NRCS Method for West Nantmeal Township use the following rainfall depths for a 24-hour Type II storm:
(1) 
One-year: 2.6 inches.
(2) 
Two-year: 3.2 inches.
(3) 
Ten-year: five inches.
(4) 
Twenty-five-year: 5.6 inches.
(5) 
Fifty-year: 6.3 inches.
(6) 
One-hundred-year: 7.2 inches.
A. 
No regulated activities within West Nantmeal Township shall commence until West Nantmeal Township receives an approval from the Conservation District of an erosion and sediment control plan for construction activities, if applicable.
B. 
DEP has regulations that require an erosion and sediment control plan for any earth disturbance activity of 5,000 square feet or more, under 25 Pa. Code § 102.4(b).
C. 
In addition, under 25 Pa. Code Chapter 92a, a DEP NPDES construction activities permit is required for regulated activities.
[Amended at time of adoption of Code (see Ch. 1, General Provisions, Art. I)]
D. 
Evidence of any necessary permit(s) for regulated activities from the appropriate DEP regional office or Chester Conservation District must be provided to West Nantmeal Township. The issuance of an NPDES construction permit [or permit coverage under the statewide General Permit (PAG-2)] satisfies the requirements of § 158-27A.
E. 
A copy of the erosion and sediment control plan and any required permit, as required by DEP regulations, shall be available on the project site at all times.
F. 
Areas proposed for infiltration BMPs shall be protected from sedimentation and compaction during the construction phase to maintain maximum infiltration capacity.
G. 
Infiltration BMPs shall not be constructed nor receive runoff until the entire drainage area contributory to the infiltration BMP has achieved final stabilization.