[Ord. 93-5 § 901, 1993; Ord. 99-24 § 1, 1999; Ord. No. 2012-09, §§ 1, 2, 11-27-2012; Ord. 2013-13, § 1, 11-26-13; Ord. No. 2022-17, 11-22-2022; Ord. No. 2024-27C, 12-26-2024]
A.
Every application for development shall be accompanied by a certified check(s) payable to the "Borough of Ship Bottom" in accordance with the following schedule of administrative charges and escrow account deposits. Where one application for development includes several approval requests the sum of the individually required administrative charges and escrow account deposits shall be paid, with separate checks for the total administrative charges and for the total escrow account deposits. Fees and copies of requested items, special meetings, and other items also included in the fee schedule.
Type | Administrative Charges | Plus | Escrow Account Deposits | ||
|---|---|---|---|---|---|
1. | Informal Review | ||||
a. | One 15 minute appearance | None required | + | None required | |
b. | Any additional appearance | $200 | + | $750 | |
2. | Subdivisions | ||||
a. | Minor subdivision plat | $625 | + | $2,000 | |
b. | Preliminary major division plat | $1,500 | + | $2,500 plus $75 per lot | |
c. | Final major subdivision plat | $750 | + | $1,500 plus $55 per lot | |
d. | Amended minor, preliminary major and/or final major subdivision plat | 50% of original administrative charges | + | 50% of original escrow account deposits | |
e. | Request for reapproval or extension of time | $425 | + | $1,000 per lot | |
3. | Site Plans | ||||
a. | Minor site plan: | $750 | + | $2,500 | |
b. | Preliminary major site plan | $1,500 | + | $2,500 for first acre or part of acre, plus $500 for each additional acre or part of acre, plus $100 per dwelling unit in the case of multiple-family units and/or $0.10 per gross square foot of building area in the case of nonresidential buildings | |
c. | Final major site plan | $950 | + | $1,000 for first acre or part of acre, plus $250 for each additional acre or part of acre, multiple-family units and/or $0.05 per gross square foot of building area in the case of nonresidential buildings | |
d. | Amended minor, preliminary major and/or final major site plan | 50% of original administrative charges | + | 50% of escrow account deposits. | |
e. | Request for reapproval or extension of time | $425 | + | $500 per acre or part of acre | |
4. | Conditional uses (in addition to fees for required site plan or subdivision review) | $500 | + | $1,000 for first acre or part of acre, plus $50 for each additional acre or part of acre. | |
5. | Variances | ||||
a. | Appeals (40:55D-70a): | $500 | + | $2,000 | |
b. | Interpretation (40:55D-70b) | $500 | + | $2,000 | |
c. | Bulk (40:55D-70c) | $500 per application | + | $2,000 for first variance plus $50 for each additional variance | |
d. | Use and others (40:55D-7-d) | $625 | + | $2,000 | |
e. | Permit (40:55D-34 and 35) | $500 | + | $2,000 | |
6. | Waivers | $225 | + | $125 for first waiver plus $25 for each additional waiver | |
7. | Requested special meeting of land use review board | $2,000 | + | None required | |
8. | Holdover meeting | $250 for regular meeting; $500 for special meeting | + | None required | |
9. | Certified list of property owners or certified list of public utilities | $0.25 per name or $10, whichever is greater | + | None required | |
10. | Copy of minutes, resolution or decisions | $1 per page for first copy of a page, plus $0.25 per copy for each additional copy of a page | + | None required | |
11. | Transcription of meeting proceedings | At cost | + | None required | |
12. | Copy of tape of public hearing | $35 per tape | + | None required | |
13. | Subdivision approval certificate | $50 per certificate | + | None required | |
14. | Certificate of nonconformity (40:55D-68) | $50 per certificate | + | None required | |
15. | Zoning permit | ||||
a. | Fence, sign | $25 per permit | + | None required | |
b. | HVAC, deck rebuild, pavers, pools | $75 per permit | + | None required | |
c. | New structures, house raises | $150 per permit | + | None required | |
d. | Bulkheads, docks and piers | $175 per permit | + | None required | |
16. | Resale certificate of occupancy | ||||
a. | Single-family dwelling | $50 per dwelling unit | + | None required | |
b. | Duplex/commercial | $100 | + | None required | |
c. | Triplex or quad | $50 per dwelling unit | + | ||
17. | Public utility registration for notice | $10 | + | None required | |
18. | Application for construction in beach dune area (Subsections 16.72010(C) and 16.72.010(D)) | $700 | + | $750 | |
a. | Permit for beach dune area construction | $250 | + | None required | |
b. | Permit for bulkhead construction | $4 per linear foot | + | None required | |
19. | Permit only for soil removal in beach dune area (Subsection 16.72.010(D)) | $50 | + | None required | |
20. | The fees noted above are estimated to cover costs incurred by the board for the review of the initial application. Additional fees totaling 50% of the original fee shall be posted by the applicant for each plan review submitted after the original submission. | ||||
B.
The administrative charges are flat fees to cover administrative expenses and are nonrefundable.
C.
The escrow account deposits are required to pay for the costs of professional services including engineering, planning, legal and other expenses connected with the review of submitted materials, including any traffic engineering review or other special analysis related to the Borough's review of the submitted materials, or any necessary studies regarding off-tract improvements. An applicant is responsible to reimburse the Borough for all expenses of professional personnel incurred and paid by the Borough for the review process of an application for development before a municipal agency, such as, but not limited to:
1.
Charges for reviews by professional personnel of applications, plans and accompanying documents;
2.
Issuance of reports by professional personnel to the municipal agency setting forth recommendations resulting from the review of any documents submitted by the applicant;
3.
Charges for any telephone conference or meeting requested or initiated by the applicant, his or her attorney or any of his or her experts or representatives;
4.
Review of additional documents submitted by the applicant and issuance of reports relating such documents;
5.
Review or preparation of easements, developer's agreements, deeds, approval resolutions, or the like;
6.
Preparation for and attendance at all meetings by professionals such as the board planner, traffic engineer or other experts as required; and
7.
The cost of expert advice or testimony obtained by the municipal agency for the purpose of corroborating testimony of applicant's experts.
D.
The escrow account deposits shall be placed in a separate account by the Borough treasurer chief financial officer at the direction of the admin officer and an accounting shall be kept of each applicant's deposit.
1.
All professional charges shall be paid from the account and charged to the applicant;
2.
Any moneys expended for professional services may be returned to the applicant within 90 days upon written request by the applicant and as authorized by the Borough council;
3.
If, at any time during the review procedure, 75% of the moneys posted shall have been expended, the applicant shall be required to post such additional sum as may be required by the administrative officer to cover professional costs;
4.
The applicant shall not be entitled to proceed with the application or any development until such time as the necessary moneys have been posted to guarantee payment of professional service fees;
5.
All payments charged to the deposit shall be pursuant to vouchers from the professionals stating the hours spent, the hourly rate and the expenses incurred;
6.
No professional submitting charges to the Borough for any review of an application for development shall charge for such services at any higher rate or in any different manner than would normally be charged to the Borough for similar work; and
7.
The Borough shall render a written final accounting to the developer on the uses to which the deposit was put and, thereafter, the Borough shall, upon written request, provide copies of the vouchers to the developer.
E.
Each applicant shall agree to pay all reasonable costs for professional review of the application. All such costs for review must be paid before any approved plat, plan or deed is signed and before any zoning permit, construction permit, certificate of occupancy, and/or other permit is issued.
F.
Payment by the Borough of any bill rendered by a professional to the municipality with respect to any service for which the municipality is entitled to reimbursement under this title shall in no way be contingent upon receipt by the municipality of reimbursement from the applicant, nor shall any payment to a professional be delayed pending the reimbursement from an applicant.
G.
If an applicant desires a court reporter, the cost for taking testimony and transcribing it and providing a copy of the transcript to the Borough shall be at the expense of the applicant who also shall arrange for the reporter's attendance.