Any person, firm, contractor or utility must obtain a street
opening permit prior to excavation of any Town street and/or way by
filling out the most current street opening application provided by
the Public Works Director or his/her designee.
After the application for the permit is completed, the contractor
will review the area to be excavated with the Public Works Director
or his/her designee.
The following requirements will be adhered to unless exceptions
or additions are noted on the permit:
A. Contractor will provide proper
traffic and safety control at all times.
B. One-way traffic will be maintained.
C. Pavement will be excavated along
neat lines.
D. Sewer pipe will be placed on
a bed of not less than six inches of sand-type granular material having
no stones greater than one inch in diameter.
[Amended at time of adoption of Code (see Ch. 1, General
Provisions, Art. II)]
E. No backfilling will be conducted
without authorization of the Public Works Director.
F. Backfill material shall be same
granular material as the bed for a distance of one foot over sewer
pipe.
G. The remainder of backfill shall
be of granular material having stones no larger than four inches in
diameter.
H. Backfilling will be by layer
method, compacted in eight-inch layers by vibrator method, or as approved
by the Public Works Director, up to the finish grade.
I. Pavement will not be placed without
authorization of the Public Works Director and shall not be less than
the thickness of existing pavement.
[Amended at time of adoption of Code (see Ch. 1, General
Provisions, Art. II)]
J. Any pavement damage by contractor
will be replaced as so directed by the Public Works Director.
K. The installation of new utilities
or the relocation of existing utilities must adhere to the minimum
horizontal separation standards below:
Utilities
|
Minimum Separation
(feet)
|
Recommended Separation
(feet)
|
---|
Water and sewer
|
10
|
10
|
Water and storm drains
|
6
|
10
|
Water and natural gas
|
6
|
10
|
Water and electric
|
6
|
6
|
Water and telephone/cable
|
6
|
6
|
Sewer and storm drains
|
6
|
10
|
Sewer and natural gas
|
6
|
6
|
Sewer and electric
|
6
|
6
|
Sewer and telephone/cable
|
6
|
6
|
Storm drains and natural gas
|
4
|
6
|
Storm drains and electric
|
4
|
6
|
Storm drains and telephone/cable
|
4
|
6
|
Electric and natural gas
|
4
|
4
|
Electric and telephone/cable
|
4
|
4
|
Telephone/cable and natural gas
|
4
|
4
|
Separation distances are from outside dimension to outside.
The minimum vertical separation is one foot. The crossing of utilities
should be as close to 90° as possible. Separation distances include
the utility pole separation.
|
[Amended 12-12-2016 by Ord. No. 12-2016]
A. Upon acceptance by the Public
Works Director, 90% of the impact fee calculated from the final disturbed
area shall be refunded, minus any funds as directed by the Public
Works Director for additional or future repair to that excavated portion
of the Town street, way, or property in order to return such portion
to its original condition prior to such excavation.
B. If satisfactory repairs are not
done in a timely fashion and upon reasonable notice to the permit
holder to do the same, the Town will accomplish the final restoration
and will deduct the cost from any fees to be refunded to the permit
holder.
C. It shall be the duty of the permit
holder to guarantee and maintain the site of the excavation work in
the same condition it was prior to the excavation for 12 months after
restoring it to its original condition.
Any emergency deemed such by the Public Works Director or his
designee in his absence, shall not need an opening permit prior to
work, and the Public Works Director or such designee shall be notified
as soon as possible, and contractor/owner will secure an after-the-fact
permit pursuant to the requirements of this article.
Any contractor or owner found in violation of this article shall
be subject to a fine of not more than $2,000, exclusive of the Town's
costs and attorney's fees which shall be recoverable to the Town.
The Town of Winslow may in addition to any civil penalties, costs
and attorney's fees, be paid all its resulting and compensatory damages,
costs and expenses related to any violation of this article.