[Ord. No. 2007-(O)-42 § 27-
1; Ord. No. 2007-(O)-54 § 27-1]
The "Leadership in Energy & Environmental Design (LEED)"
standards and guidelines are herein incorporated by reference, as
amended and supplemented and may be found at http://www.usgbc.org,
or by contacting the U.S. Green Building Council, 1015 18th Street,
NW, Suite 508, Washington, DC 20036.
[Ord. No. 2007-(O)-42 § 27-2; Ord. No. 2007-(O)-54 § 27-2]
a. The Town of Kearny supports the use of green building practices and
adopts the USGBC's Leadership in Energy Design ("LEED") Rating
System for the design and construction of new buildings and major
renovations and additions to Town-funded facility projects.
b. The Town adopts a policy that Town-funded facility projects and Town-owned
facilities meet a minimum LEED "Silver" rating.
[Ord. No. 2007-(O)-42 § 27-3; Ord. No. 2007-(O)-54 § 27-3]
a. Applicants for projects within a formally designated Redevelopment
Area are encouraged, but not required, to comply with LEED criteria.
b. Only projects proposing to meet a minimum accreditation level of
LEED Certification shall be eligible for the incentives in this section.
[Ord. No. 2007-(O)-42 § 27-4; Ord. No. 2007-(O)-54 § 27-4]
To encourage redevelopment projects to achieve formal LEED certification from the USGBC, the Town of Kearny has established a Green Building Density Incentive, which shall be provided to applications for new buildings and additions within a formally designated Redevelopment Area upon compliance with the requirements of Section
27-5 below.
In all designated redevelopment areas, unless otherwise specifically
provided, the following incentives shall apply:
a. LEED Platinum - Additional 0.30 floor area ratio (FAR) or additional
three dwelling units per acre, where residential uses are permitted;
b. LEED Gold - Additional 0.25 floor area ratio (FAR) or additional
two dwelling units per acre, where residential uses are permitted;
c. LEED Silver - Additional 0.20 floor area ratio (FAR) or additional
one dwelling unit per acre;
d. LEED Certified - Additional 0.15 floor area ratio (FAR) or additional
0.5 dwelling unit per acre, where residential uses are permitted.
[Ord. No. 2007-(O)-42 § 27-5; Ord. No. 2007-(O)-54 § 27-5]
Redevelopment projects seeking the incentives available for
LEED accreditation must submit the following information to the Town
for each project application:
a. USGBC Registration. The applicant shall register the proposed project
with the USGBC, and shall submit written proof of such registration,
prior to any incentive being granted by the Town.
b. Name of LEED Accredited Professional Working on the Project. Each
project must include a LEED accredited professional as part of the
project team. This team member advises the project team on LEED issues
and ensures that the specific LEED credits for the project are achieved.
c. LEED Scorecard. A LEED scorecard must be submitted as part of its
plan. The scorecard must be accompanied by an explanation of how each
credit will be achieved or why the credit cannot be achieved for the
project. Prior to the issuance of specific permits, reports must be
submitted outlining progress on achieving LEED credits.
d. Plans. All plans submitted for review and approval shall contain
the project components listed on the LEED scorecard.
e. Maintenance Plan. A maintenance plan for each of the proposed LEED
components on the scorecard shall be submitted for review and approval.
f. Certificate of Zoning. A certificate of zoning or resolution of variance
approval granted pursuant to green building incentives as provided
in this section shall contain conditions that such LEED certification
be achieved and maintained.
g. Performance Guarantee. Prior to the issuance of a certificate of
zoning or resolution of variance approval, a performance guarantee
shall be delivered by the applicant and property owner to assure that
the conditions of the approval are satisfied.
h. Monthly Reports. Progress of the implementation of the green building
components shall be monitored on a monthly basis with report by the
project's LEED accredited professional to the Construction Official.
i. As-built Analysis. An as-built analysis of the project in relation
to the approved project shall be prepared by an independent LEED accredited
professional architect upon completion of the project. The cost of
the independent LEED accredited professional architect shall be borne
by the applicant.
j. Application for LEED. Applicant shall be required to apply for LEED
certification and rating to the USGBC near or at completion of the
project.
k. LEED Certification. Upon delivery by applicant of certification by
the USGBC that the project achieved the approved level of LEED certification,
the Town shall issue a final certificate of occupancy.
[Ord. No. 2007-(O)-42 § 27-6; Ord. No. 2007-(O)-54 § 27-6]
a. If the applicant is unable to include the approved LEED components
during the project implementation, any comparable alternate green
building components must be approved in writing by the Town. All such
alternate shall maintain the minimum required rating for the level
of LEED certification sought.
b. In cases where an application cannot comply with the approved green
building design requirements due solely to the inability to install
a LEED-recognized green building component, the applicant may seek
a waiver from the original approving authority from such requirement.
1. A request for LEED waiver must be made by the applicant in writing.
2. A request for LEED waiver shall specify the regulation from which
the waiver is requested and a detailed reason(s) for the request.
3. The issuer of the certificate of zoning or variance approval shall
consider the request for waiver and grant such waiver, upon finding
that the LEED waiver is necessary to install the green building component
and that such waiver shall not result in a threat to public health,
safety and/or order.
4. The issuer of the certificate of zoning or variance approval shall
have 10 business days to render a decision on the waiver request.
5. The Town reserves the right to require a waived requirement when
deemed necessary by the issuer of the certificate of zoning or variance,
upon evidence of a substantive change of an application or unforeseen
circumstances.