A.
The developer shall meet with the Highway Department, Water District and Sewer Department and the Board's consulting engineer and Town Planner prior to commencement of any road construction to discuss the sequence of road construction and the Town's expectation of how the work will be performed.
B.
No water main, drain, catch basins, utility, road subgrade or surface or any other improvements shall be backfilled, paved over or otherwise permanently covered until inspected by the Highway Superintendent and/or the Board's Agent, who shall confer with the Superintendent of the Sewer Department and the Water District in the field at the site, and found to be in conformance with these Rules and Regulations and applicable Town of Raynham specifications.
C.
The subdivider shall notify, in writing, the designated inspector at least 48 hours prior to the time of each required inspection. The subdivider shall provide safe and convenient access to all parts of work to be inspected.
D.
The contractor is required to perform all work in compliance with the approved definitive plan and Massachusetts Department of Transportation standards. If noncompliant work and/or unfavorable work conditions are observed, the inspector may then recommend to the Highway Superintendent that all work cease for good cause. The Highway Superintendent may then issue a work stoppage order. Failure to comply with work stoppage will forfeit the opportunity for the developer to seek street acceptance as a public way. No additional obligation to the Town or liability for that stoppage shall be incurred.
[Amended 1-19-2023]
E.
No work shall be approved unless it has been inspected, and any work covered before being inspected shall be uncovered and inspected at the owner's expense.
F.
No paving activities shall take place from November 15 to April 15, except for maintenance. The Highway Superintendent may approve waivers from this restriction.