1.1
Description of Work.
A.
The work consists of furnishing and installing a grinder pump system including excavation and backfill, bedding material, grinder pump, pump chamber with accessway, piping and valves, electrical work, factory and on-site testing, and all other incidentals as specified and as shown on the contract drawings.
B.
All approvals and permits as set forth in the New Shoreham Sewer Ordinance and Regulations and the Department of Environmental Management requirements, when applicable, shall be obtained prior to the installation of the low pressure grinder pump station system.
1.2
Special Requirements.
A.
Contractor shall obtain all required permits as set forth in the Town of New Shoreham Sewer Ordinance and the Regulations of the New Shoreham Board of Sewer Commissioners prior to undertaking construction of sanitary sewage service connection(s).
B.
The Sewer Superintendent shall be notified 24 hours in advance to inspect the installation.
1.3
Submittals.
A.
Contract Documents. Submit contract documents of proposed low pressure sewer grinder pump system including design calculations.
B.
Operation and Maintenance Service. Submit an operation and maintenance service contract for each grinder pump unit.
C.
Record Drawings. At completion of project, submit record drawings of installed system.
1.4
Qualifications of Material and Equipment.
A.
Specific manufacturers' names and catalog numbers are used herein to establish quality and design of a particular item.
B.
Wherever in the specifications any item of equipment or material is designated by reference to a particular brand, manufacturer, or trade name, it is understood that a reviewed equal product, acceptable to the New Shoreham Board of Sewer Commissioners (NSBSC), may be submitted by the Contractor.
C.
If the Contractor proposes to use a material which, while suitable for the intended use, deviates in any way from the detailed requirements, he shall inform the NSBSC in writing of the nature of such deviations at the time the material is submitted for review, and shall request a review of the deviation from the requirements.
D.
In requesting a review of deviations or substitutions, the Contractor shall provide evidence leading to a reasonable certainty that the proposed substitution or deviation shall provide a result at least equal in quality to that specified. If, in the opinion of the NSBSC, the evidence presented by the Contractor does not provide a sufficient basis for such reasonable certainty, the NSBSC will reject such substitution or deviation without further investigation, in which case it shall be the responsibility of the Contractor to provide another product which is satisfactory to the NSBSC.