[Ord. 138, 7/17/1996, § 600; as amended by Ord. 178, 12/1/2004]
1.
The applicant shall construct all roads, streets, lanes or alleys, together with all other improvements, including grading, paving, curbs, gutters, sidewalks, street lights, fire hydrants, water mains, street signs, shade trees, storm drainage facilities, sanitary sewers, landscaping, traffic control devices, open space and restricted areas, trails, and erosion and sediment control measures in conformance with the final plan as approved, and applicable provisions of the Pennsylvania Department of Transportation Specifications, Publication 408, dated 1994, or the latest revision thereto, or other applicable regulations.
2.
No plan shall be finally approved for recording, and no building permits shall be issued until the developer has completed all required improvements or has provided a performance guarantee in accordance with § 22-311, hereof.
3.
All trenches or other excavations in existing or proposed Township streets shall be backfilled in accordance with the following:
A.
Backfilling shall be done as promptly as possible.
B.
As reviewed and approved by the Township Engineer, the trench shall be backfilled with hand-placed screenings or #57 aggregate (2B) to a height of at least one foot above the top of the conduit, pipe or pipe bell. These screenings shall be thoroughly hand-tamped around the side of the pipe. These screenings shall be placed with the hand shovels and not from trucks or with the use of power equipment and shall be free from refuse, boulders, rocks, unsuitable organic material or other material which, in the opinion of the Township Engineer, is unsuitable.
C.
When the pipe is located in a dedicated street or any place where paving (including driveways) may be placed, the remainder of the trench shall be backfilled with 2RC or other approved materials and promptly compacted. The backfill material shall be mechanically tamped in approximately six-inch layers.
D.
Where openings have been made in existing Township roads, paving shall be restored in accordance with the paving standards contained in this chapter. Openings made in State roads shall be restored in accordance with the Pennsylvania Department of Transportation specifications. Permits shall be required before paving is opened in any existing State or Township road.
E.
Where openings are made behind the curb line the opening shall be covered with good topsoil to a depth of six inches and seeded or sodded to the satisfaction of the Township Engineer.
F.
Whenever the trenches have not been properly filled or if settlement occurs, they shall be refilled, compacted, smoothed off and finally made to conform to the surface of the ground.
G.
Frozen earth shall not be used for backfilling, nor shall any backfilling be done when materials already in the trench are frozen.
H.
Where excavated material, or any portion thereof, is deemed by the Township Engineer to be unsuitable for backfilling, the developer shall procure and place backfill material approved by the Township, and the unsuitable material disposed of properly.
4.
At all times during the construction of the project, stone construction entrances shall be positioned at all points exiting the site to facilitate the cleaning of mud and debris from all vehicles leaving the site.
5.
No burning or burying of trash or debris shall be permitted on the construction site. To ensure that all trash and debris is removed, a trash container of adequate capacity shall be placed at various locations on the work site.
6.
It shall be the developer's responsibility to notify all emergency service agencies serving East Vincent Township when construction will begin and where the site is located.