[Ord. No. 4190, 2-1-2021]
A.
Prior to issuance of a permit for lot or common improvements, including streets and other public areas, the applicant shall submit an erosion and sediment control plan per Chapter 540, Erosion and Sedimentation Control Regulations, and in accordance with regulations and standards found in the Engineering and Plan Preparation Manual for Public Facilities (Title V, Appendix A).
B.
Sediment control elements shall be installed and implemented prior to commencement of the development process.
C.
Piles of dirt located on the development site shall be leveled within sixty (60) days after excavation. Piles of dirt may remain longer with approval from the Public Works Director based on erosion and sediment control measures remaining in place.