A.
All stormwater management, collection, conveyance, erosion control, and floodplain considerations shall be accomplished in accordance with the following provisions:
(1)
Prior to the final approval or commencement of any regulated activity within the jurisdiction of this chapter, the developer shall submit a stormwater management site plan to the Township for approval.
(a)
When plan applications, whether preliminary or final, are submitted in sections, a detailed stormwater management site plan for the entire project site shall be submitted. This detailed plan shall demonstrate how the stormwater of the proposed section will relate to the entire development. The amount and velocity at the discharge point of the section shall be included in the data submitted. If temporary facilities are required for construction of a section, such facilities shall be included in the submitted plans.
(b)
The type, location, and extent of all erosion and sedimentation control measures shall be shown on an erosion and sedimentation control plan that conforms to the requirements of the Soil Erosion and Sediment Control Manual of the Pennsylvania Department of Environmental Protection and the erosion and sedimentation control design standards of this chapter.
(c)
An operation and maintenance agreement, in recordable form acceptable to the Township, that clearly sets forth the ownership, operation and maintenance responsibility of all temporary and permanent stormwater management facilities and erosion and sedimentation control facilities as provided for in Article VII, Administration. The intent of these regulations is to provide private operation and maintenance of stormwater management and erosion and sedimentation control facilities, including regular inspection of the areas to assure proper maintenance and care of all stormwater management facilities in accordance with their design.
[Amended at time of adoption of Code (see Ch. 1, General Provisions, Art. I)]
(d)
A written report shall be submitted that includes the following information:
[1]
General description of the development site, including a description of existing natural and hydrologic features and any environmentally sensitive areas.
[2]
General description of the overall stormwater management concept for the project, including a description of permanent stormwater management techniques, structural and nonstructural BMPs to be employed.
[3]
Construction specifications of the materials to be used for structural stormwater management facilities.
[4]
Stormwater runoff calculations for both predevelopment and post-development conditions.
[5]
An erosion and sedimentation control plan narrative that conforms to the requirements of the Soil Erosion and Sediment Control Manual of the Pennsylvania Department of Environmental Protection and provides a description of all erosion and sedimentation control measures, temporary as well as permanent, including the staging of earth moving activities, sufficient in detail to clearly indicate their function.
[6]
For all proposed detention basins and retention basins, except temporary sedimentation basins, the documentation shall include a plotting or tabulation of storage volumes with corresponding water surface elevations and the outflow rates for those water surfaces.
[7]
For all proposed detention basins and retention basins, except temporary sediment basins, documentation shall set forth the design hydrograph, the routing method or a method of equal caliber acceptable to the Township Engineer, utilized to determine the function of the basin.
(2)
All stormwater runoff flowing over the project site shall be considered in the design of the stormwater management facilities.
(3)
Stormwater drainage systems shall be provided in order to permit unimpeded flow along natural watercourses, except as modified by stormwater management facilities or open channels consistent with this chapter.
(4)
Where a development site is traversed by watercourses, a drainage easement shall be provided conforming substantially to the line of such watercourses.
(5)
The PADEP, Chapter 105, Rules and Regulations, apply to the construction, modification, operation or maintenance of both existing and proposed water obstructions and encroachments throughout the watershed, including work in wetlands. Inquiries on permit requirements or other concerns shall be addressed to PADEP's regional office.
(6)
When it can be shown that, due to topographic conditions, natural drainageways on the development site cannot adequately provide for drainage, open channels may be constructed conforming substantially to the line and grade of such natural drainageways. Work within natural drainageways shall be subject to approval by PADEP.
(7)
Any stormwater management facilities or any facilities that constitute water obstructions (e.g., culverts, bridges, outfalls, or stream enclosures, etc.) that are regulated by this chapter, that will be located in or adjacent to waters of the commonwealth (including wetlands), shall be subject to approval by PADEP. When there is a question whether wetlands may be involved, it is the responsibility of the applicant or his agent to show that the land in question cannot be classified as wetlands; otherwise, approval to work in the area must be obtained from PADEP.
(8)
Should any stormwater management facility require a dam safety permit under PADEP Chapter 105, the facility shall be designed in accordance with Chapter 105 and meet the regulations of Chapter 105 concerning dam safety which may be required to pass storms larger than one-hundred-year event.
(9)
No detention basin, storm pipe, or swale or any other stormwater management facility shall discharge directly onto any publicly used Township, state or private road but shall discharge into a culvert under or along the road.
(10)
Any stormwater management facilities regulated by this chapter that will be located on, or discharged onto state highway rights-of-way shall be subject to approval by PennDOT.
(11)
Stormwater management facilities located within or affecting the floodplain of any watercourse shall comply with the requirements of the floodplain regulations provided in Chapter 350, Zoning, or any future ordinances regulating construction or development within areas of the Township subject to flooding.
(12)
The minimum floor elevations for all structures that would be affected by a basin, other temporary impoundments, or open conveyance systems where ponding may occur shall be two feet above the one-hundred-year water surface.
(a)
If basement or underground facilities are proposed, detailed calculations addressing the effects of the stormwater ponding on the structure and water-proofing and/or flood proofing design information shall be provided for review and approval.
(13)
All existing and natural watercourses, channels, drainage systems and areas of surface water concentration shall be maintained in their existing condition unless an alteration is approved by the appropriate regulatory agency.
(14)
Stormwater management facilities intended to receive and infiltrate runoff from regulated activities shall be selected based on suitability of soils and site conditions and shall be constructed on soils that have the following characteristics:
(a)
Infiltration testing shall be conducted in accordance with BMP Manual.
(b)
Acceptable soil will have a percolation rate of at least 0.1 inch per hour and not more than 10 inches per hour (after application of the appropriate safety factor from the BMP manual).
(c)
A minimum separation of 24 inches of acceptable soil between the bottom of the facility and the limiting zone, unless it is demonstrated to the satisfaction of the Township that the selected BMP has design criteria which allow for a smaller separation.
(d)
A stabilized infiltration rate sufficient to accept the additional stormwater load and drain completely as determined by field tests conducted by the applicant's professional designer.
(e)
The Township shall be notified 24 hours prior to infiltration tests being conducted as to provide an opportunity for the Township to witness the tests.
(15)
Stormwater discharge points onto an adjacent property shall comply with the following:
(a)
Stormwater flows onto adjacent property shall not be created, relocated, or peak rate increased without written notification of the adjacent property owner(s) by the developer including the establishment of an easement.
(b)
Stormwater runoff from a project site shall flow directly into a natural watercourse or into an existing storm sewer system. If neither of these is available, the applicant shall obtain an easement from the downstream landowner(s) to allow the site's runoff discharge to reach a natural watercourse or an existing storm sewer system through the easement. If an easement is obtained, post-developed flow characteristics must be similar to the runoff characteristics (spread, velocity, and peak rate) of the predeveloped flows. The easement from the downstream property owner(s) shall be to allow for a piped storm sewer system, an overland flow system, or a combination of the two. The downstream system design shall conform to the design requirements of this chapter.
(c)
When the applicant provides verification that the downstream landowner(s) refuses to grant an easement at reasonable terms in the sole opinion of the Township, the site shall be designed such that the discharge from the applicant's site shall be in a nonerosive, sheet flow condition. For all design year storms, including the one-hundred-year storm, runoff from the applicant's site shall flow onto the adjacent property in a manner similar to the runoff characteristics (spread, velocity, and peak rate) of the predeveloped flow. The use of level spreaders is prohibited.
(d)
Stormwater runoff shall not be transferred from one watershed to another unless the watersheds are subwatersheds of a common watershed which join together within the perimeter of the property, or both of the following apply:
[1]
The effect of the transfer does not alter the peak discharge (in conformance with the requirements of the Act 167 Plan) onto adjacent lands; and
[2]
Drainage easements from the affected landowners are provided.
[a]
For the purposes of this subsection, affected landowners shall include all landowners receiving runoff that was transferred from one watershed to another watershed that does not join together within the perimeter of the project site, from the point of discharge from the project site to the location in the watershed where the transferred runoff discharges to a receiving watercourse located within the watershed that the runoff was transferred from.
(16)
Unless an alternate design is submitted to the Township for review, and said design is prepared by a licensed (in the Commonwealth of Pennsylvania) geologist or geotechnical engineer:
(a)
No stormwater facilities shall be placed in, over or within a distance that will impact the following features:
(b)
The minimum isolation distance from stormwater management facilities to the listed geologic features shall be as follows:
(c)
Stormwater runoff from any regulated activity shall not be discharged into sinkholes.
(d)
It shall be the developer's responsibility to verify if the development is underlain by carbonate geology. The certificate provided in the Appendix[1] shall be attached to all stormwater management site plans and signed and sealed by the developer's qualified professional.
[1]
Editor's Note: The appendix is included as an attachment to this chapter.
(e)
Whenever a stormwater facility will be located in an area underlain by carbonate geology, a geological evaluation of the proposed location by a registered professional geologist shall be conducted to determine subsurface conditions, including soil permeability, depth to bedrock, subgrade stability, and susceptibility to sinkhole formation.
(f)
Impermeable liners may be used to reduce or eliminate the separation distances listed in § 286-25A(16)(a) and (b).
(17)
The calculated peak rates of runoff for stormwater originating on the project site must meet one of the following conditions for all watersheds flowing from the project site:
(a)
Match predevelopment hydrograph.
[1]
Developers and/or landowners are encouraged to provide infiltration facilities or utilize other techniques which will allow the post-development one-hundred-year hydrograph to match the predevelopment one-hundred-year hydrograph, along all parts of the hydrograph, for the development site.
[2]
To match the predevelopment hydrograph, the post-development peak rate must be less than or equal to the predevelopment peak rate, and the post-development runoff volume must be less than or equal to the predevelopment volume for the same storm event.
[3]
A shift in hydrograph peak time of up to five minutes and a rate variation of up to 5% at a given time may be allowable to account for the timing effect of BMPs used to manage the peak rate and runoff volume.
(b)
Where the predevelopment hydrograph cannot be matched, the calculated peak rates of runoff for stormwater originating on the project site must meet the following conditions, for all watersheds flowing from the project site:
[1]
The two year post-development rate of runoff (peak flow) from any regulated activity shall be less than or equal to 50% of the calculated two year predeveloped rate (peak flow) except where:
[2]
Where an application meets one of the above exceptions, the two year post-developed rate of runoff (peak flow) shall be less than or equal to the calculated two year predeveloped rate of runoff (peak flow).
[3]
Post-development runoff from any regulated activity shall not exceed the peak rates of runoff prior to development for all other design storms (five-, ten-, twenty-five-, fifty-, and one-hundred-year storm events).
(c)
Developers have the option to propose a regional stormwater management plan or participate in a regional stormwater management plan developed by others.
[1]
A regional stormwater management plan may include off-site volume and rate control, as appropriate and supported by a detailed design approved by the Township.
[2]
A regional stormwater management plan must meet all of the volume and rate control standards required by this chapter for the area defined by the regional stormwater management plan, but not necessarily for each individual development site.
[3]
Appropriate agreements must be established to ensure the requirements of this chapter and the requirements of the regional stormwater management plan are met.
(18)
Areas proposed for infiltration BMPs shall be protected from sedimentation and compaction during the construction phase to maintain maximum infiltration capacity. Staging of earthmoving activities and selection of construction equipment shall consider this protection.
(19)
Infiltration BMPs shall not be constructed nor receive runoff from disturbed areas until the entire contributory drainage area to the infiltration BMP has achieved final stabilization.
(20)
If structure foundations, basements, or other underground facilities (whether on site or off site) would be affected by saturated soil due to a nearby stormwater management facility, detailed calculations addressing the impact of the saturated soil, and water-proofing design information, where applicable, shall be submitted for approval.
B.
In the case of any dispute in the methodology used in the design of any stormwater management site plan and/or in the presentation of such information, the Supervisors shall make the final determination on the design criteria, methodology, and form of presentation.