[Amended 11-2-2010]
The final plan shall be accompanied by a performance guarantee or, at the sole discretion of the Planning Board, a conditional agreement.
A.
Performance guarantees may be tendered in one of the following forms:
(1)
Certified check payable to the Town of Camden; or
(2)
Savings account passbook issued in the name of the Town of Camden; or
(3)
Irrevocable letter of credit from a financial institution acceptable to the Planning Board; or
(4)
Faithful performance bond running to the Town of Camden and issued by a surety company licensed to do business in the State of Maine; or
(5)
Sufficient deed to the Town of Camden for a lot or lots within the subdivision.
B.
Except for the form of guarantee described in Subsection A(5) above, the amount of the guarantee shall be 125% of the cost of furnishing, installing, connecting and completing in good working condition all of the street grading, paving, storm drainage, utilities, and other similar improvements, as specified in the final plan. The guarantee given in the form of land, as described in Subsection A(5) above, shall carry an appraised market value of 150% of the cost of the proposed improvements. All guarantees shall be conditioned upon the completion of all such improvements within two years from the date of the approval of the final plan, as recorded on the subdivision plat, with extensions to this deadline only as permitted in Article VIII of this chapter. If a performance guarantee as described in Subsection A above has been satisfactorily filed with the Town, building permits may be issued for construction within the subdivision prior to completion of required improvements, but prior to occupancy of a building or dwelling unit, the improvements serving that building or dwelling unit shall be in place and serviceable.