A.
The developer shall notify the Town at least 48 hours before commencing any construction, before beginning any work in conjunction with stormwater management system construction, and upon completion of the project.
B.
Regular inspections shall be made and documented for each ESD planning technique and practice and structural stormwater management measure at the stages of construction specified in the Design Manual by the Town, its authorized representative, or certified by a professional engineer licensed in the State of Maryland. At a minimum, all ESD and other nonstructural practices shall be inspected upon completion of final grading, the establishment of permanent stabilization, and before issuance of use and occupancy approval.
D.
The owner/developer and on-site personnel shall be notified, in writing, when violations are observed. Written notification shall describe the nature of the violation and the required corrective action.
E.
No work shall proceed on the next phase of development until the Town inspects and approves the work previously completed and furnishes the developer with the results of the inspection reports as soon as possible after completion of each required inspection.