Inspector
Admin. Cost
Total Fee
Plan review and initial acceptance inspections:
 
 
 
Base building only:
 
 
 
0 to 5,000 sq. ft.
$150.00
$25.00
$175.00
5,001 to 15,000 sq. ft.
$200.00
$25.00
$225.00
15,001 to 25,000 sq. ft.
$250.00
$25.00
$275.00
25,001 to 50,000 sq. ft.
$350.00
$25.00
$375.00
Over 50,001 sq. ft.
$500.00
$25.00
$525.00
Water based fire suppression system inspection
$200.00
$25.00
$225.00
Fire alarm system inspection
$250.00
$25.00
$275.00
Mechanical hood/fire extinguishing system inspection
$150.00
$25.00
$175.00
Reinspection fees
 
 
 
2nd inspection
$25.00
$25.00
$50.00
3rd inspection or more
$50.00
$25.00
$75.00
Portable fuel tank during construction inspection
$50.00
$25.00
$75.00
Gas or oil well fire inspection
$1,000.00
$25.00
$1,025.00
Gas or oil well tank farm (including piping from gas or oil well)
$1,000.00
$25.00
$1,025.00
(Ordinance 07-13, ex. A, adopted 12/11/07)