(a)
The code official or authorized designee,
who are/is charged with approval of site plans and/or site preparation
permits, may require, the construction of tree protection, silt traps,
mulching, temporary or permanent planting of areas exposed by grading,
construction of diversions, channel linings, grade stabilization structures,
and bank protection structures. All construction sites will have construction
fencing to preclude workers from trespassing onto adjoining property
and to contain debris and trash.
(b)
Code official or authorized designee
may require other acts and impose other limits and restraints which
are deemed necessary and reasonable to prevent flooding, erosion,
and damage to trees. The code official or authorized designee may
also require the applicant to furnish technical information to substantiate
the adequacy of erosion and/or flood control proposals.
(Ordinance 2019-08-26-02 adopted 8/26/19)
(a)
Construction operations, including
the delivery of materials and equipment, which produce noise disturbances,
are only permitted between the hours of 7:00 a.m. to 7:00 p.m. weekdays
and 8:00 a.m. to 7:00 p.m. weekends.
(b)
Construction requiring an early morning
concrete pour will be required to notify and receive prior approval
from the code official in the form of a condition on the building
permit. The contractor will be required to notify the city police
department, the building and development services department and residential
properties within 200' of the date, hours of construction, a contact
phone number, and the expected duration.
(Ordinance 2021-07-19-05 adopted 7/19/21; Ordinance 2023-12-18-04 adopted 12/18/2023)
(a)
Prior to issuance of a permit, no
building material or construction equipment of any kind shall be placed
or stored upon any lot. Such material shall be placed within the property
lines of the lot on which the improvements are to be made. Construction
equipment and materials may not be stored on any public street.
(b)
No tracked equipment with any kind
of metal cleats or shoes will be driven on any hard surface city streets
without adequate protection with tires or planking, etc.
(Ordinance 2019-08-26-02 adopted 8/26/19)
A stabilized driveway, including
proper size culvert and road base with 2" to 3" bull rock placed in
the first 20 feet of the construction entrance, is required when vehicular
access to the property is needed during construction. The ends of
the culverts shall be protected from crushing.
(Ordinance 2019-08-26-02 adopted 8/26/19)
The contractor shall verify in advance of proposed cuts or trenches in the street rights-of-way or public utility easements, and that utility lines in the immediate vicinity of the project have been identified and, if necessary, located and marked on the ground at the site. A separate utility development permit is required for excavation in the city’s right-of-way. (Refer to the city’s utility development ordinance, article
20.03.)
(Ordinance 2019-08-26-02 adopted 8/26/19)
For all new construction, a portable
chemical toilet must be placed on each site and not in the street
right-of-way before any construction activity is begun. Toilets must
be so located so the doors open into the lot on which the construction
is taking place. Chemical toilets are required for all construction
sites where use of another sanitary system is not available on the
same lot at all times.
(Ordinance 2019-08-26-02 adopted 8/26/19)
Blasting is prohibited within the
city limits.
(Ordinance 2019-08-26-02 adopted 8/26/19)
(a)
It shall be the applicants responsibility
to provide one commercial dumpster on each site prior to beginning
any construction activity. It shall be the applicants responsibility
during the construction that the receptacle be emptied promptly when
it becomes full.
(b)
Brush piles must be removed or mulched
within 48 hours of cutting.
(c)
The applicant shall collect, remove
and place in an appropriate solid waste container all broken or discarded
construction material from the construction site which has accumulated
on the site or any adjacent public or private property. The applicant
shall remove mud, soil, and stone deposits from city streets. No construction
material shall be destroyed by burning in the city. Any materials
resulting from the cleaning out of mixer trucks shall be deposited
only within the boundary of the site being worked.
(Ordinance 2019-08-26-02 adopted 8/26/19)