[Ord. No. 10-2022, 7/20/2022]
1. 
Fees shall be established by the Borough of Conshohocken to cover plan review and inspection costs incurred by the Borough of Conshohocken. All fees shall be paid by the applicant at the time of the SWM site plan submission. No permit to begin any work on the project shall be issued until the requisite fees have been paid. A fee schedule shall be established by resolution of the Council of the Borough of Conshohocken based on whether the property is residential/owner occupied or a commercial or rental property. The Borough of Conshohocken shall periodically update the fee schedule to ensure that its costs are adequately reimbursed. The Borough of Conshohocken may include all costs incurred in the review fee charged to an applicant.
2. 
The review fee may include, but not be limited to, costs for the following:
A. 
Administrative/clerical processing.
B. 
Review of the SWM site plan.
C. 
Attendance at meetings.
D. 
Review of the operation and maintenance responsibilities and agreements, including financial guarantees.
E. 
Inspections during construction and at the completion of construction including, but not limited to, preliminary site preparation, rough grading, stormwater management facilities, BMPs, and appurtenances, establishment of ground covers, and all restoration work.
(1) 
The applicant shall notify the Borough Engineer a minimum of 48 hours in advance of commencing of each of these phases. The Borough Engineer, upon such notification, shall make field inspections on the site to determine if work in progress and the completed operations have been performed in accordance with the SWM site plan.
(2) 
Any portion of the work which does not comply with the approved SWM site plan must be corrected by the applicant within 10 days. No work may proceed on any subsequent phases of the SWM site plan until the required corrections have been made.
F. 
Review of the as-built plans.
G. 
Any additional work required to enforce any permit provisions regulated by this chapter, correct violations, and assure proper completion of stipulated remedial actions.