In all areas of special flood hazards the following provisions
are required for all new construction and substantial improvements:
(1) All
new construction or substantial improvements shall be designed (or
modified) and adequately anchored to prevent flotation, collapse or
lateral movement of the structure resulting from hydrodynamic and
hydrostatic loads, including the effects of buoyancy;
(2) All
new construction or substantial improvements shall be constructed
by methods and practices that minimize flood damage;
(3) All
new construction or substantial improvements shall be constructed
with materials resistant to flood damage;
(4) All
new construction or substantial improvements shall be constructed
with electrical, heating, ventilation, plumbing, and air-conditioning
equipment and other service facilities that are designed and/or located
so as to prevent water from entering or accumulating within the components
during conditions of flooding;
(5) All
new and replacement water supply systems shall be designed to minimize
or eliminate infiltration of floodwaters into the system;
(6) New
and replacement sanitary sewage systems shall be designed to minimize
or eliminate infiltration of floodwaters into the system and discharge
from the systems into floodwaters; and
(7) On-site
waste disposal systems shall be located to avoid impairment to them
or contamination from them during flooding.
(Ordinance 91-03, sec. 1, adopted 2/12/91; Ordinance 98-59, sec. 1, adopted 9/22/98; 1957
Code, sec. 6A-15; Ordinance 2012-16 adopted 3/27/12)
In all areas of special flood hazards where base flood elevation data has been provided as set forth in section
3-12-7,
3-12-42(8), or
3-12-73(c), the following provisions are required:
(1) Residential
construction.
New construction and substantial improvement of any residential structure shall have the lowest floor (including basement), elevated to or above the base flood elevation. A registered professional engineer, architect, or land surveyor shall submit a certification to the floodplain administrator that the standard of this subsection as proposed in section
3-12-43(a)(1), is satisfied.
(2) Nonresidential
construction.
New construction and substantial improvements
of any commercial, industrial or other nonresidential structure shall
either have the lowest floor (including basement) elevated to or above
the base flood level or together with attendant utility and sanitary
facilities, be designed so that below the base flood level the structure
is watertight with walls substantially impermeable to the passage
of water and with structural components having the capability of resisting
hydrostatic and hydrodynamic loads and effects of buoyancy. A registered
professional engineer or architect shall develop and/or review structural
design, specifications, and plans for the construction, and shall
certify that the design and methods of construction are in accordance
with accepted standards of practice as outlined in this subsection.
A record of such certification which includes the specific elevation
(in relation to mean sea level) to which such structures are floodproofed
shall be maintained by the floodplain administrator.
(3) Enclosures.
New construction and substantial improvements, with fully enclosed
areas below the lowest floor that are usable solely for parking of
vehicles, building access or storage in an area other than a basement
and which are subject to flooding shall be designed to automatically
equalize hydrostatic flood forces on exterior walls by allowing for
the entry and exit of floodwaters. Designs for meeting this requirement
must either be certified by a registered professional engineer or
architect or meet or exceed the following minimum criteria:
(A) A minimum of two openings on separate walls having a total net area
of not less than 1 square inch for every square foot of enclosed area
subject to flooding shall be provided.
(B) The bottom of all openings shall be no higher than 1 foot above grade.
(C) Openings may be equipped with screens, louvers, valves, or other
coverings or devices provided that they permit the automatic entry
and exit of floodwaters.
(4) Manufactured
homes.
(A) Require that all manufactured homes to be placed within zone A on
a community’s FHBM or FIRM shall be installed using methods
and practices which minimize flood damage. For the purposes of this
requirement, manufactured homes must be elevated and anchored to resist
flotation, collapse, or lateral movement. Methods of anchoring may
include, but are not limited to, use of over-the-top or frame ties
to ground anchors. This requirement is in addition to applicable state
and local anchoring requirements for resisting wind forces.
(B) Require that manufactured homes that are placed or substantially
improved within zones A1-30, AH, and AE on the community’s FIRM
on sites: (i) outside of a manufactured home park or subdivision;
(ii) in a new manufactured home park or subdivision; (iii) in an expansion
to an existing manufactured home park or subdivision; or (iv) in an
existing manufactured home park or subdivision on which a manufactured
home has incurred substantial damage as a result of a flood, be elevated
on a permanent foundation such that the lowest floor of the manufactured
home is elevated to or above the base flood elevation and be securely
anchored to an adequately anchored foundation system to resist flotation,
collapse, and lateral movement.
(C) Require that manufactured homes be placed or substantially improved
on sites in an existing manufactured home park or subdivision with
zones A1-30, AH and AE on the community’s FIRM that are not
subject to the provisions of subsection (4) of this section be elevated
so that either:
(i) The lowest floor of the manufactured home is at or above the base
flood elevation; or
(ii) The manufactured home chassis is supported by reinforced piers or
other foundation elements of at least equivalent strength that are
no less than 36 inches in height above grade and be securely anchored
to an adequately anchored foundation system to resist flotation, collapse,
and lateral movement.
(5) Recreational
vehicles.
Require that recreational vehicles placed on sites within zones A1-30, AH, and AE on the community’s FIRM either: (A) be on the site for fewer than 180 consecutive days; or (B) be fully licensed and ready for highway use; or (C) meet the permit requirements of section
3-12-43(a), and the elevation and anchoring requirements for manufactured homes in subsection
(4) of this section. A recreational vehicle is ready for highway use if it is on its wheels or jacking system, is attached to the site only by quick disconnect type utilities and security devices, and has no permanently attached additions.
(6) First-floor
elevation.
In addition to the requirements in subsections
(1) through
(5) above, any building or structure which has the lowest floor erected in that portion of the city designated as an area of special flood hazard on the flood insurance rate map shall be designed and constructed to place the first-floor elevation a minimum of one (1) foot above the base flood elevation as such elevation is determined by the city engineer.
(7) Equipment
and mechanical items.
All new construction or substantial
improvements shall be constructed with electrical, heating, ventilation,
plumbing and air-conditioning equipment and other service facilities
a minimum of one (1) foot above the base flood elevation as such elevation
is determined by the city engineer.
(Ordinance 91-03, sec. 1, adopted 2/12/91; Ordinance 98-59, sec. 1, adopted 9/22/98; 1957
Code, sec. 6A-16; Ordinance 2012-16 adopted 3/27/12; Ordinance
2020-27 adopted 8/11/20)
(a) All subdivision proposals including the placement of manufactured home parks and subdivisions shall be consistent with sections
3-12-2,
3-12-3, and
3-12-4 of this article.
(b) All proposals for the development of subdivisions including the placement of manufactured home parks and subdivisions shall meet floodplain development permit requirements of section
3-12-8,
3-12-43, and the provisions of this division.
(c) Base flood elevation data shall be generated for subdivision proposals and other proposed development including the placement of manufactured home parks and subdivisions which is greater than 50 lots or 5 acres, whichever is lesser, if not otherwise provided pursuant to section
3-12-7 or section
3-12-42(8) of this article.
(d) All
subdivision proposals including the placement of manufactured home
parks and subdivisions shall have adequate drainage provided to reduce
exposure to flood hazards.
(e) All
subdivision proposals including the placement of manufactured home
parks and subdivisions shall have public utilities and facilities
such as sewer, gas, electrical and water systems located and constructed
to minimize or eliminate flood damage.
(Ordinance 2012-16 adopted 3/27/12)
Located within the areas of special flood hazard established in section
3-12-7, are areas designated as shallow flooding. These areas have special flood hazards associated with flood depths of 1 to 3 feet where a clearly defined channel does not exist, where the path of flooding is unpredictable, and where velocity flow may be evident. Such flooding is characterized by ponding or sheet flow; therefore, the following provisions apply:
(1) All
new construction and substantial improvements of residential structures
have the lowest floor (including basement) elevated to or above the
base flood elevation or the highest adjacent grade at least as high
as the depth number specified in feet on the community’s FIRM
(at least 2 feet if no depth number is specified).
(2) All
new construction and substantial improvements of nonresidential structures:
(A) Have the lowest floor (including basement) elevated to or above the
base flood elevation or the highest adjacent grade at least as high
as the depth number specified in feet on the community’s FIRM
(at least 2 feet if no depth number is specified); or
(B) Together with attendant utility and sanitary facilities be designed
so that below the base specified flood depth in an AO zone, or below
the base flood elevation in an AH zone, level the structure is watertight
with walls substantially impermeable to the passage of water and with
structural components having the capability of resisting hydrostatic
and hydrodynamic loads of effects of buoyancy.
(3) A registered professional engineer or architect shall submit a certification to the floodplain administrator that the standards of this section, as proposed in section
3-12-43 are satisfied.
(4) Require
within zones AH or AO adequate drainage paths around structures on
slopes, to guide floodwaters around and away from proposed structures.
(Ordinance 2012-16 adopted 3/27/12)
Located within areas of special flood hazard established in section
3-12-7, are areas designated as floodways. Since the floodway is an extremely hazardous area due to the velocity of floodwaters which carry debris, potential projectiles and erosion potential, the following provisions shall apply:
(1) Encroachments
are prohibited, including fill, new construction, substantial improvements
and other development within the adopted regulatory floodway unless
it has been demonstrated through hydrologic and hydraulic analyses
performed in accordance with standard engineering practice that the
proposed encroachment would not result in any increase in flood levels
within the community during the occurrence of the base flood discharge.
(2) If subsection
(1) above is satisfied, all new construction and substantial improvements shall comply with all applicable flood hazard reduction provisions of this division.
(3) Under the provisions of 44 CFR chapter
1, section 65.12, of the National Flood Insurance Program regulations, a community may permit encroachments within the adopted regulatory floodway that would result in an increase in base flood elevations, provided that the community first completes all of the provisions required by section 65.12.
(Ordinance 91-03, sec. 1, adopted 2/12/91; Ordinance 98-59, sec. 1, adopted 9/22/98; 1957
Code, sec. 6A-17; Ordinance 2012-16 adopted 3/27/12)