(a)
The director shall provide an application requiring all users discharging to the POTW(s) to provide information necessary to evaluate discharges to the POTW(s) and satisfy EPA requirements.
(b)
Existing users and significant industrial users shall update the application under the following conditions:
(c)
Existing significant industrial users.
If a significant industrial user is currently operating under a wastewater discharge permit issued by the director and is discharging wastewater into the POTW(s) prior to the effective date of this division and wishes to continue such discharges in the future, the user shall, within ninety (90) days after said date, or for a shorter time period if allowed by the director, submit a revised wastewater discharge application in accordance with this section, and shall not cause or allow discharges to the POTW(s) to continue after one hundred eighty (180) days of the effective date of this division except in accordance with a wastewater discharge permit reissued by the director.
(d)
New users.
(1)
In order to comply with the objectives of section 13-2-101, any user, deemed necessary by the director, who proposes to begin or recommence discharging into the POTW(s) must complete such application prior to the beginning or recommencing of such discharge.
(2)
Wastewater discharge applications are mandatory for significant industrial users proposing to begin or recommence discharge to the POTW(s).
(e)
The control authority reserves the right to take the following time periods from the receipt of the completed application to review the application information to determine the conditions which must be met prior to discharge:
(Ordinance 2011-01, sec. 1, adopted 1/11/11)