Section 01560 - Storm Water Pollution Prevention
Section 02229 - Excavation Safety
(Ordinance 2007-106, App. B, adopted 3/20/07)
The cost for performing the work described in this Section shall be included in related items of work unless specifically shown otherwise on the Bid Form. All excavation required for locating existing underground utilities will not be measured or paid for as a separate item of work unless specifically shown otherwise on the Bid Form. Include cost for locating existing underground utilities in related items of work.
(Ordinance 2007-106, App. B, adopted 3/20/07)
The applicable provisions of the following standards shall apply as if written here in their entirety:
ASTM American Society for Testing of Materials |
OSHA Occupational Safety and Health Administration |
AASHTO American Association of State Highway and Transportation Officials |
(Ordinance 2007-106, App. B, adopted 3/20/07)
When requested, submit adequate amounts of backfill material for evaluation by the Engineer or the designated representative of the Engineer.
(Ordinance 2007-106, App. B, adopted 3/20/07)
The Contractor shall comply with the requirements of all pertinent regulatory agencies as applicable to the project.
(Ordinance 2007-106, App. B, adopted 3/20/07)
No open excavation or trenches shall be left overnight without proper lighting and barricades. Schedule backfilling such that there is a minimum of excavations and trenches that are left open during times when no work is occurring.
(Ordinance 2007-106, App. B, adopted 3/20/07)