Prior to placing any pavement, manhole frames and covers, valve boxes, and other such utility access structures shall be adjusted in elevation by the Contractor if needed to match the surface of the new pavement. For overlaying existing pavement, cast iron or ductile iron extensions rated for not less than H-20 loading of a manufacturer and model approved by the Engineer or the designated representative of the Engineer may be used. For other than overlaying of existing pavement, the Contractor shall adjust the height of manhole frames and covers, valve boxes, and other such utility access in a manner acceptable to the Engineer or designated representative of the Engineer and to the grades required for the new pavement. Stabilize and compact subgrade or base material as shown on plans for pavement. Dry subgrade or base to be moistened prior to concrete placement.
(Ordinance 2007-106, App. B, adopted 3/20/07)