A.
Purpose. The purpose of this section is to ensure installation and completion of Public Facilities to serve a development in accordance with the UDC.
B.
Submitting plans.
1.
Subdivision Construction Plans must be submitted in the form required provided by the City Engineer. The City will not accept incomplete Subdivision Construction Plans and will return incomplete plans to the applicant.
2.
Subdivision Construction Plans are not considered filed until approval is received from all applicable Water, Wastewater, Electric and Gas utility providers other than the City, and TXDOT, if applicable.
3.
The Subdivider will submit to the City an Opinion of Probable Cost prepared by the Professional Engineer that prepared the Subdivision Construction Plans, and a costs and quantity breakout for the Public Facilities, which the City will use as a basis for requiring a Performance Bond and inspection fees.
(i)
Prior to the Pre-Construction Meeting, the City Engineer, at their discretion, may require the Subdivider to provide an updated Opinion of Probable Cost based on the contracted amount to construct Public Facilities;
(ii)
The City Engineer may adjust the amount of the Performance Bond based on changes to the Opinion of Probable Cost during construction;
(iii)
The City may charge inspection fees for inspections performed during construction;
(iv)
Prior to Acceptance, the Subdivider must submit final documentation including all change orders. This amount will determine the Maintenance Bond.
C.
Responsible official and decision-making authority for subdivision construction plans.
1.
Review and approval action. The City Engineer is the Responsible Official for review and approval of Subdivision Construction Plans.
2.
Outside review. If an outside consultant is contracted to review Subdivision Construction Plans, the City is entitled to reimbursement from the Subdivider for additional review fees.
3.
Decision-maker action. The City Engineer will approve, approve subject to conditions, or deny the Subdivision Construction Plans.
D.
Approval required and timing of construction. The City Engineer must approve the Subdivision Construction Plans in accordance with this Section 2.4 Subdivision Construction Plans and Procedures prior to the approval or recordation of the Final Plat.
E.
Criteria for approval. The City Engineer must approve the Subdivision Construction Plans if:
1.
The Subdivision Construction Plans are consistent with the approved Preliminary Plat; and
2.
The Subdivision Construction Plans conform to the subject property's zoning (including zoning design standards) or Development Agreement, as applicable, and to the standards for Adequate Public Facilities, contained in the UDC or adopted Technical Manuals, and all other applicable City ordinances.
F.
Effect. Approval of Subdivision Construction Plans authorizes the applicant to:
3.
The applicant may also be issued a Building Permit if the City has approved a Building Permit application and all other Building Permit requirements have also been met. The City will not issue a Certificate of Occupancy until Public Facilities have been accepted and the Final Plat has been recorded.
G.
Expiration date for subdivision construction plans. The approval of Subdivision Construction Plans remains in effect for a period of one (1) year from the date of approval, or for the duration of construction of the project, provided that Progress Towards Completion, in accordance with TLGC Chapter 245.005, continues or the City approves an extension of the Subdivision Construction Plans in accordance with subsection 2.4.1.H.
H.
Extension of subdivision construction plans beyond expiration date.
1.
General.
(i)
The City Engineer may extend approval of the Subdivision Construction Plans for a period of six (6) additional months beyond the expiration date.
(ii)
The Subdivider must make the request for extension in writing to the City Engineer a minimum of thirty (30) calendar days before the expiration date and include an explanation of why the approval extension is requested.
2.
Decision by the City Engineer.
(i)
The City Engineer will review the extension request, and approve, approve with conditions, or deny the extension request within thirty (30) calendar days following the date of the extension request.
(ii)
If the City Engineer fails to act on an extension request within thirty (30) calendar days, the extension is approved.
(iii)
The City Engineer will provide written notice of the approval to the Subdivider.
3.
Consideration. The City Engineer will extend Subdivision Construction Plans approval for a period of six (6) additional months beyond the expiration date if:
(i)
A Final Plat has been submitted, approved or filed of record for any portion of the property shown on the Subdivision Construction Plans;
(ii)
The Subdivision Construction Plans comply with current ordinances (i.e., ordinances that have been adopted after approval of the original Subdivision Construction Plans) that impact the health, safety and general welfare of the City;
(iii)
Demonstrable forward progress has been made to proceed with construction or required improvements; or
4.
Conditions. In granting an extension, the City Engineer may impose such conditions as are needed to ensure that the land will be developed in a timely fashion and that the public interest is served. Any extension may be predicated upon compliance with new development regulations or the Subdivider waiving any vested rights.
(Ordinance 475 adopted 6/28/22; Ordinance 534 adopted 5/28/2024)